Form 6-K
SECURITIES AND EXCHANGE COMMISSION
Washington, DC 20549
FORM 6-K
REPORT OF FOREIGN PRIVATE ISSUER
PURSUANT TO RULE 13a-16 OR 15d-16 OF
THE SECURITIES EXCHANGE ACT OF 1934
From: November 10, 2010
IVANHOE MINES LTD.
(Translation of Registrants Name into English)
Suite 654 999 CANADA PLACE, VANCOUVER, BRITISH COLUMBIA V6C 3E1
(Address of Principal Executive Offices)
(Indicate by check mark whether the registrant files or will file annual reports under cover of
Form 20-F or Form 40-F.)
Form 20-F- o Form 40-F- þ
(Indicate by check mark whether the registrant by furnishing the information contained in this form
is also thereby furnishing the information to the Commission pursuant to Rule 12g3-2(b) under the
Securities Exchange Act of 1934.)
Yes: o No: þ
(If Yes is marked, indicate below the file number assigned to the registrant in connection with
Rule 12g3-2(b): 82- .)
Enclosed:
Third quarter Financial Statements and MD&A
SIGNATURES
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused
this report to be signed on its behalf by the undersigned, thereunto duly authorized.
|
|
|
|
|
|
IVANHOE MINES LTD.
|
|
Date: November 10, 2010 |
By: |
/s/ Beverly A. Bartlett
|
|
|
|
BEVERLY A. BARTLETT |
|
|
|
Vice President &
Corporate Secretary |
|
THIRD QUARTER REPORT
SEPTEMBER 30, 2010
TABLE OF CONTENTS
|
|
|
|
|
ITEM 1. Financial Statements |
|
|
|
|
|
|
|
|
|
Unaudited Consolidated Balance Sheets as at September 30, 2010 and December 31, 2009 |
|
|
|
|
|
|
|
|
|
Unaudited Interim Consolidated Statements of Operations for the Three and Nine Month Periods ended September 30, 2010 and 2009 |
|
|
|
|
|
|
|
|
|
Unaudited Interim Consolidated Statement of Equity for the Nine Month Period ended September 30, 2010 |
|
|
|
|
|
|
|
|
|
Unaudited Interim Consolidated Statements of Cash Flows for the Three and Nine Month Periods ended September 30, 2010 and 2009 |
|
|
|
|
|
|
|
|
|
Notes to the Unaudited Interim Consolidated Financial Statements |
|
|
|
|
|
|
|
|
|
ITEM 2. Managements Discussion and Analysis of Financial Condition and Results of Operations |
|
|
|
|
|
|
|
|
|
2
IVANHOE MINES LTD.
Consolidated Balance Sheets
(Stated in thousands of U.S. dollars)
|
|
|
|
|
|
|
|
|
|
|
September 30, |
|
|
December 31, |
|
|
|
2010 |
|
|
2009 |
|
(Unaudited) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ASSETS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CURRENT |
|
|
|
|
|
|
|
|
Cash and cash equivalents (Note 4) |
|
$ |
1,440,119 |
|
|
$ |
965,823 |
|
Short-term investments |
|
|
7,505 |
|
|
|
14,999 |
|
Accounts receivable |
|
|
60,159 |
|
|
|
39,349 |
|
Inventories |
|
|
41,938 |
|
|
|
18,015 |
|
Prepaid expenses |
|
|
22,346 |
|
|
|
15,988 |
|
|
|
|
|
|
|
|
TOTAL CURRENT ASSETS |
|
|
1,572,067 |
|
|
|
1,054,174 |
|
|
|
|
|
|
|
|
|
|
LONG-TERM INVESTMENTS (Note 5) |
|
|
88,857 |
|
|
|
93,511 |
|
OTHER LONG-TERM INVESTMENTS (Note 6) |
|
|
212,419 |
|
|
|
145,035 |
|
PROPERTY, PLANT AND EQUIPMENT (Note 7) |
|
|
888,919 |
|
|
|
218,781 |
|
DEFERRED INCOME TAXES |
|
|
13,443 |
|
|
|
6,953 |
|
OTHER ASSETS |
|
|
11,795 |
|
|
|
16,227 |
|
|
|
|
|
|
|
|
TOTAL ASSETS |
|
$ |
2,787,500 |
|
|
$ |
1,534,681 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
LIABILITIES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CURRENT |
|
|
|
|
|
|
|
|
Accounts payable and accrued liabilities |
|
$ |
162,942 |
|
|
$ |
55,128 |
|
Amounts due under credit facilities (Note 8) |
|
|
16,892 |
|
|
|
17,544 |
|
Interest payable on long-term debt (Note 9 (b)) |
|
|
9,337 |
|
|
|
4,712 |
|
Convertible credit facility (Note 9 (a)) |
|
|
|
|
|
|
378,916 |
|
|
|
|
|
|
|
|
TOTAL CURRENT LIABILITIES |
|
|
189,171 |
|
|
|
456,300 |
|
|
|
|
|
|
|
|
|
|
CONVERTIBLE CREDIT FACILITY (Note 9 (b)) |
|
|
228,275 |
|
|
|
544,990 |
|
AMOUNTS DUE UNDER CREDIT FACILITIES (Note 8) |
|
|
38,865 |
|
|
|
37,979 |
|
DEFERRED INCOME TAXES |
|
|
10,721 |
|
|
|
10,888 |
|
ASSET RETIREMENT OBLIGATIONS |
|
|
33,475 |
|
|
|
5,436 |
|
|
|
|
|
|
|
|
TOTAL LIABILITIES |
|
|
500,507 |
|
|
|
1,055,593 |
|
|
|
|
|
|
|
|
CONTINGENCIES (Note 17) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
EQUITY |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
SHARE CAPITAL (Note 10) |
|
|
|
|
|
|
|
|
Authorized |
|
|
|
|
|
|
|
|
Unlimited number of preferred shares without
par value |
|
|
|
|
|
|
|
|
Unlimited number of common shares without par
value |
|
|
|
|
|
|
|
|
Issued and outstanding |
|
|
|
|
|
|
|
|
529,460,654 (2009 - 425,447,552) common shares |
|
|
2,997,636 |
|
|
|
1,886,789 |
|
SHARE PURCHASE WARRANTS (Note 10 (b) and (c)) |
|
|
18,443 |
|
|
|
27,386 |
|
BENEFICIAL CONVERSION FEATURE (Note 9 (a)) |
|
|
|
|
|
|
30,250 |
|
ADDITIONAL PAID-IN CAPITAL |
|
|
1,302,994 |
|
|
|
348,468 |
|
ACCUMULATED OTHER COMPREHENSIVE INCOME (Note 11) |
|
|
1,626 |
|
|
|
(14,578 |
) |
DEFICIT |
|
|
(2,048,936 |
) |
|
|
(1,800,179 |
) |
|
|
|
|
|
|
|
TOTAL IVANHOE MINES LTD. SHAREHOLDERS EQUITY |
|
|
2,271,763 |
|
|
|
478,136 |
|
|
|
|
|
|
|
|
NONCONTROLLING INTERESTS (Note 12) |
|
|
15,230 |
|
|
|
952 |
|
|
|
|
|
|
|
|
TOTAL EQUITY |
|
|
2,286,993 |
|
|
|
479,088 |
|
|
|
|
|
|
|
|
TOTAL LIABILITIES AND EQUITY |
|
$ |
2,787,500 |
|
|
$ |
1,534,681 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
APPROVED BY THE BOARD: |
|
|
|
|
|
|
|
/s/ D. Korbin
D. Korbin, Director
|
|
|
|
/s/ K. Thygesen
K. Thygesen, Director
|
|
|
The accompanying notes are an integral part of these consolidated financial statements.
3
IVANHOE MINES LTD.
Consolidated Statements of Operations
(Stated in thousands of U.S. dollars, except for share and per share amounts)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended |
|
|
Nine Months Ended |
|
|
|
September 30, |
|
|
September 30, |
|
|
|
2010 |
|
|
2009 |
|
|
2010 |
|
|
2009 |
|
(Unaudited) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
REVENUE |
|
$ |
6,597 |
|
|
$ |
11,871 |
|
|
$ |
38,182 |
|
|
$ |
26,078 |
|
COST OF SALES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Production and delivery |
|
|
(5,975 |
) |
|
|
(6,435 |
) |
|
|
(28,073 |
) |
|
|
(16,746 |
) |
Depreciation and depletion |
|
|
(1,027 |
) |
|
|
(2,202 |
) |
|
|
(5,854 |
) |
|
|
(4,243 |
) |
Write-down of carrying value of inventory |
|
|
(7,855 |
) |
|
|
|
|
|
|
(14,390 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
COST OF SALES |
|
|
(14,857 |
) |
|
|
(8,637 |
) |
|
|
(48,317 |
) |
|
|
(20,989 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
EXPENSES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Exploration (Note 2 and 10 (a)) |
|
|
(48,131 |
) |
|
|
(40,949 |
) |
|
|
(159,037 |
) |
|
|
(109,869 |
) |
General and administrative (Note 10 (a)) |
|
|
(15,005 |
) |
|
|
(12,464 |
) |
|
|
(38,052 |
) |
|
|
(30,778 |
) |
Depreciation |
|
|
(252 |
) |
|
|
(1,339 |
) |
|
|
(1,522 |
) |
|
|
(3,167 |
) |
Accretion of asset retirement obligations |
|
|
(51 |
) |
|
|
(40 |
) |
|
|
(142 |
) |
|
|
(104 |
) |
Gain on sale of other mineral property rights |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3,000 |
|
Write-down of carrying values of property, plant and equipment |
|
|
(1,764 |
) |
|
|
|
|
|
|
(1,764 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL EXPENSES |
|
|
(80,060 |
) |
|
|
(63,429 |
) |
|
|
(248,834 |
) |
|
|
(161,907 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
OPERATING LOSS |
|
|
(73,463 |
) |
|
|
(51,558 |
) |
|
|
(210,652 |
) |
|
|
(135,829 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
OTHER INCOME (EXPENSES) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Interest income |
|
|
3,772 |
|
|
|
512 |
|
|
|
10,939 |
|
|
|
1,942 |
|
Interest expense |
|
|
(6,280 |
) |
|
|
(4,066 |
) |
|
|
(27,957 |
) |
|
|
(13,083 |
) |
Accretion of convertible credit facilities (Note 9) |
|
|
(3,034 |
) |
|
|
(3,603 |
) |
|
|
(11,696 |
) |
|
|
(10,549 |
) |
Foreign exchange gains |
|
|
5,334 |
|
|
|
19,482 |
|
|
|
2,145 |
|
|
|
31,945 |
|
Listing fees SouthGobi |
|
|
|
|
|
|
(1,599 |
) |
|
|
|
|
|
|
(1,932 |
) |
Unrealized gains (losses) on long-term investments (Note 5 (d)) |
|
|
1,363 |
|
|
|
|
|
|
|
(3,849 |
) |
|
|
|
|
Unrealized gains on other long-term investments |
|
|
2,019 |
|
|
|
649 |
|
|
|
3,528 |
|
|
|
15 |
|
Realized gain on redemption of other long-term investments
(Note 6 (a)) |
|
|
34 |
|
|
|
198 |
|
|
|
121 |
|
|
|
1,334 |
|
Change in fair value of embedded derivatives (Note 9 (b)) |
|
|
49,772 |
|
|
|
|
|
|
|
120,633 |
|
|
|
|
|
Loss on conversion of convertible credit facility (Note 9 (b)) |
|
|
|
|
|
|
|
|
|
|
(154,316 |
) |
|
|
|
|
Write-down of carrying value of long-term investments
(Note 5 (c)) |
|
|
(68 |
) |
|
|
|
|
|
|
(485 |
) |
|
|
|
|
Gain on sale of long-term investment |
|
|
|
|
|
|
1,424 |
|
|
|
|
|
|
|
1,424 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
LOSS BEFORE INCOME TAXES AND OTHER ITEMS |
|
|
(20,551 |
) |
|
|
(38,561 |
) |
|
|
(271,589 |
) |
|
|
(124,733 |
) |
Recovery of income taxes |
|
|
3,782 |
|
|
|
7,778 |
|
|
|
5,956 |
|
|
|
7,552 |
|
Share of loss of significantly influenced investees (Note 5) |
|
|
(8,503 |
) |
|
|
(23,041 |
) |
|
|
(31,713 |
) |
|
|
(30,839 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
NET LOSS FROM CONTINUING OPERATIONS |
|
|
(25,272 |
) |
|
|
(53,824 |
) |
|
|
(297,346 |
) |
|
|
(148,020 |
) |
(LOSS) INCOME FROM DISCONTINUED OPERATIONS (Note 3) |
|
|
|
|
|
|
(21,903 |
) |
|
|
6,585 |
|
|
|
(12,841 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
NET LOSS |
|
|
(25,272 |
) |
|
|
(75,727 |
) |
|
|
(290,761 |
) |
|
|
(160,861 |
) |
NET LOSS ATTRIBUTABLE TO NONCONTROLLING
INTERESTS (Note 12) |
|
|
411 |
|
|
|
5,969 |
|
|
|
42,004 |
|
|
|
10,158 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NET LOSS ATTRIBUTABLE TO IVANHOE MINES LTD. |
|
$ |
(24,861 |
) |
|
$ |
(69,758 |
) |
|
$ |
(248,757 |
) |
|
$ |
(150,703 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
BASIC AND DILUTED (LOSS) EARNINGS PER SHARE
ATTRIBUTABLE TO IVANHOE MINES LTD. FROM |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CONTINUING OPERATIONS |
|
$ |
(0.05 |
) |
|
$ |
(0.13 |
) |
|
$ |
(0.56 |
) |
|
$ |
(0.37 |
) |
DISCONTINUED OPERATIONS |
|
|
|
|
|
|
(0.05 |
) |
|
|
0.01 |
|
|
|
(0.03 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
(0.05 |
) |
|
$ |
(0.18 |
) |
|
$ |
(0.55 |
) |
|
$ |
(0.40 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
WEIGHTED AVERAGE NUMBER OF
SHARES OUTSTANDING (000s) |
|
|
496,075 |
|
|
|
378,190 |
|
|
|
455,685 |
|
|
|
378,133 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The accompanying notes are an integral part of these consolidated financial statements.
4
IVANHOE MINES LTD.
Consolidated Statements of Equity
(Stated in thousands of U.S. dollars, except for share amounts)
(Unaudited)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Accumulated |
|
|
|
|
|
|
|
|
|
|
|
|
|
Share Capital |
|
|
|
|
|
|
Beneficial |
|
|
Additional |
|
|
Other |
|
|
|
|
|
|
|
|
|
|
|
|
|
Number |
|
|
|
|
|
|
Share Purchase |
|
|
Conversion |
|
|
Paid-In |
|
|
Comprehensive |
|
|
|
|
|
|
Noncontrolling |
|
|
|
|
|
|
of Shares |
|
|
Amount |
|
|
Warrants |
|
|
Feature |
|
|
Capital |
|
|
Income |
|
|
Deficit |
|
|
Interests |
|
|
Total |
|
|
Balances, December 31, 2009 |
|
|
425,447,552 |
|
|
$ |
1,886,789 |
|
|
$ |
27,386 |
|
|
$ |
30,250 |
|
|
$ |
348,468 |
|
|
$ |
(14,578 |
) |
|
$ |
(1,800,179 |
) |
|
$ |
952 |
|
|
$ |
479,088 |
|
Net loss |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(248,757 |
) |
|
|
|
|
|
|
(248,757 |
) |
Other comprehensive income (Note 11) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16,204 |
|
|
|
|
|
|
|
|
|
|
|
16,204 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Comprehensive loss |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(232,553 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Shares issued for: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Exercise of stock options |
|
|
2,612,500 |
|
|
|
29,794 |
|
|
|
|
|
|
|
|
|
|
|
(8,712 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
21,082 |
|
Exercise of share purchase warrants
(Note 10 (b)), net of issue costs of $2,695 |
|
|
46,026,522 |
|
|
|
399,316 |
|
|
|
(8,943 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
390,373 |
|
Conversion of Rio Tinto convertible credit
facility (Note 9 (a)) |
|
|
40,083,206 |
|
|
|
437,146 |
|
|
|
|
|
|
|
(36,314 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
400,832 |
|
Private placement (Note 10 (b)), net of
issue costs of $167 |
|
|
15,000,000 |
|
|
|
240,749 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
240,749 |
|
Consulting services |
|
|
261,900 |
|
|
|
3,421 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3,421 |
|
Share purchase plan |
|
|
28,974 |
|
|
|
421 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
421 |
|
Convertible credit facility (Note 9 (a)) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6,064 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6,064 |
|
Movement in noncontrolling interests (Note 12) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14,278 |
|
|
|
14,278 |
|
Dilution gains |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
933,807 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
933,807 |
|
Stock-based compensation |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
29,431 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
29,431 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Balances, September 30, 2010 |
|
|
529,460,654 |
|
|
$ |
2,997,636 |
|
|
$ |
18,443 |
|
|
$ |
|
|
|
$ |
1,302,994 |
|
|
$ |
1,626 |
|
|
$ |
(2,048,936 |
) |
|
$ |
15,230 |
|
|
$ |
2,286,993 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The accompanying notes are an integral part of these consolidated financial statements.
5
IVANHOE MINES LTD.
Consolidated Statements of Cash Flows
(Stated in thousands of U.S. dollars)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended |
|
|
Nine Months Ended |
|
|
|
September 30, |
|
|
September 30, |
|
|
|
2010 |
|
|
2009 |
|
|
2010 |
|
|
2009 |
|
(Unaudited) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
OPERATING ACTIVITIES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Cash used in operating activities (Note 13) |
|
$ |
(42,635 |
) |
|
$ |
(46,881 |
) |
|
$ |
(141,770 |
) |
|
$ |
(125,547 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
INVESTING ACTIVITIES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Proceeds from sale of discontinued operations |
|
|
|
|
|
|
1,725 |
|
|
|
6,442 |
|
|
|
38,725 |
|
Purchase of long-term investments |
|
|
(11,075 |
) |
|
|
(35 |
) |
|
|
(24,100 |
) |
|
|
(13,495 |
) |
Purchase of other long-term investments |
|
|
|
|
|
|
|
|
|
|
(80,000 |
) |
|
|
|
|
Proceeds from sale of other mineral property rights |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3,000 |
|
Proceeds from redemption of short-term investments |
|
|
|
|
|
|
|
|
|
|
15,000 |
|
|
|
|
|
Proceeds from sale of long-term investments |
|
|
|
|
|
|
2,625 |
|
|
|
1,800 |
|
|
|
2,625 |
|
Proceeds from redemption of other long-term investments |
|
|
57 |
|
|
|
320 |
|
|
|
201 |
|
|
|
2,041 |
|
Expenditures on property, plant and equipment |
|
|
(222,843 |
) |
|
|
(9,720 |
) |
|
|
(430,698 |
) |
|
|
(22,467 |
) |
Expenditures on other assets |
|
|
(143 |
) |
|
|
(177 |
) |
|
|
(190 |
) |
|
|
(856 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
Cash (used in) provided by investing activities of continued operations |
|
|
(234,004 |
) |
|
|
(5,262 |
) |
|
|
(511,545 |
) |
|
|
9,573 |
|
Cash used in investing activities of discontinued operations |
|
|
|
|
|
|
(1,707 |
) |
|
|
|
|
|
|
(5,887 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
Cash (used in) provided by investing activities |
|
|
(234,004 |
) |
|
|
(6,969 |
) |
|
|
(511,545 |
) |
|
|
3,686 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
FINANCING ACTIVITIES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Issue of share capital |
|
|
11,265 |
|
|
|
2,070 |
|
|
|
457,403 |
|
|
|
2,293 |
|
Proceeds from credit facilities |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
34,575 |
|
Repayment of credit facilities |
|
|
(354 |
) |
|
|
(1,628 |
) |
|
|
(785 |
) |
|
|
(1,997 |
) |
Noncontrolling interests reduction of investment in subsidiaries |
|
|
(2,529 |
) |
|
|
|
|
|
|
(2,529 |
) |
|
|
|
|
Noncontrolling interests investment in subsidiaries |
|
|
233,930 |
|
|
|
626 |
|
|
|
655,071 |
|
|
|
1,006 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Cash provided by financing activities |
|
|
242,312 |
|
|
|
1,068 |
|
|
|
1,109,160 |
|
|
|
35,877 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
EFFECT OF EXCHANGE RATE CHANGES ON CASH |
|
|
19,971 |
|
|
|
26,406 |
|
|
|
18,451 |
|
|
|
43,527 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NET CASH (OUTFLOW) INFLOW |
|
|
(14,356 |
) |
|
|
(26,376 |
) |
|
|
474,296 |
|
|
|
(42,457 |
) |
CASH AND CASH EQUIVALENTS, BEGINNING OF PERIOD |
|
|
1,454,475 |
|
|
|
368,029 |
|
|
|
965,823 |
|
|
|
384,110 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CASH AND CASH EQUIVALENTS, END OF PERIOD |
|
$ |
1,440,119 |
|
|
$ |
341,653 |
|
|
$ |
1,440,119 |
|
|
$ |
341,653 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CASH AND CASH EQUIVALENTS IS COMPRISED OF: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Cash on hand and demand deposits |
|
$ |
693,173 |
|
|
$ |
173,454 |
|
|
$ |
693,173 |
|
|
$ |
173,454 |
|
Short-term money market instruments |
|
|
746,946 |
|
|
|
168,199 |
|
|
|
746,946 |
|
|
|
168,199 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
1,440,119 |
|
|
$ |
341,653 |
|
|
$ |
1,440,119 |
|
|
$ |
341,653 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Supplementary cash flow information (Note 13)
The accompanying notes are an integral part of these consolidated financial statements.
6
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
1. |
|
SIGNIFICANT ACCOUNTING POLICIES |
These unaudited interim consolidated financial statements have been prepared in
accordance with United States of America generally accepted accounting principles
(U.S. GAAP). The accounting policies followed in preparing these consolidated
financial statements are those used by Ivanhoe Mines Ltd. (the Company) as set out in
the audited consolidated financial statements for the year ended December 31, 2009.
Certain information and note disclosures normally included for annual consolidated
financial statements prepared in accordance with U.S. GAAP have been omitted. These
interim consolidated financial statements should be read together with the audited
consolidated financial statements of the Company for the year ended December 31, 2009.
In the opinion of management, all adjustments considered necessary (including
reclassifications and normal recurring adjustments) to present fairly the financial
position, results of operations and cash flows at September 30, 2010 and for all
periods presented, have been included in these financial statements. The interim
results are not necessarily indicative of results for the full year ending December 31,
2010, or future operating periods. For further information, see the Companys annual
consolidated financial statements, including the accounting policies and notes thereto.
The Company operates two reportable segments, being its coal division located in
Mongolia, and its exploration and development division with projects located primarily
in Mongolia and Australia.
References to Cdn$ refer to Canadian currency, Aud$ to Australian currency, and $
to United States currency.
|
(b) |
|
Basis of presentation |
For purposes of these consolidated financial statements, the Company, subsidiaries of
the Company, and variable interest entities for which the Company is the primary
beneficiary, are collectively referred to as Ivanhoe Mines.
|
|
|
In January 2010, the Financial Accounting Standards Board Accounting Standards
Codification (ASC) guidance for fair value measurements and disclosures was
updated to require additional disclosures related to transfers in and out of level
1 and 2 fair value measurements and enhanced detail in the level 3 reconciliation.
The updated guidance clarified the level of disaggregation required for assets
and liabilities and the disclosures required for inputs and valuation techniques
be used to measure the fair value of assets and liabilities that fall in either
level 2 or level 3. The updated guidance was effective for the Companys fiscal
year beginning January 1, 2010, except for the level 3 disaggregation which is
effective for the Companys fiscal year beginning January 1,
2011. The adoption of the updated guidance had no impact on the Companys
consolidated financial position, results of operations or cash flows. |
7
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
1. |
|
SIGNIFICANT ACCOUNTING POLICIES (Continued) |
|
(c) |
|
Accounting changes (continued) |
|
|
|
In June 2009, the ASC guidance for consolidation accounting was updated to
require an entity to perform a qualitative analysis to determine whether the
enterprises variable interest gives it a controlling financial interest in a
Variable Interest Entity (VIE). This qualitative analysis identifies the
primary beneficiary of a VIE as the entity that has both of the following
characteristics: (i) the power to direct the activities of a VIE that most
significantly impact the entitys economic performance and (ii) the obligation to
absorb losses or receive benefits from the entity that could potentially be
significant to the VIE. The updated guidance was effective for the Companys
fiscal year beginning January 1, 2010. The adoption of the updated guidance had
no impact on the Companys consolidated financial position, results of operations
or cash flows. |
Generally, exploration costs are charged to operations in the period incurred until it has
been determined that a property has economically recoverable reserves, at which time
subsequent exploration costs and the costs incurred to develop a property are capitalized.
Summary of exploration expenditures by location:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended |
|
|
Nine Months Ended |
|
|
|
September 30, |
|
|
September 30, |
|
|
|
2010 |
|
|
2009 |
|
|
2010 |
|
|
2009 |
|
Mongolia |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Oyu Tolgoi (1) |
|
$ |
14,298 |
|
|
$ |
22,154 |
|
|
$ |
74,308 |
|
|
$ |
65,117 |
|
Coal Division |
|
|
14,676 |
|
|
|
5,598 |
|
|
|
35,547 |
|
|
|
14,061 |
|
Other Mongolia
Exploration |
|
|
1,393 |
|
|
|
385 |
|
|
|
2,927 |
|
|
|
1,058 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
30,367 |
|
|
|
28,137 |
|
|
|
112,782 |
|
|
|
80,236 |
|
Australia |
|
|
15,743 |
|
|
|
11,464 |
|
|
|
41,429 |
|
|
|
26,352 |
|
Indonesia |
|
|
903 |
|
|
|
1,103 |
|
|
|
2,182 |
|
|
|
2,382 |
|
Other |
|
|
1,118 |
|
|
|
245 |
|
|
|
2,644 |
|
|
|
899 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
48,131 |
|
|
$ |
40,949 |
|
|
$ |
159,037 |
|
|
$ |
109,869 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(1) |
|
Until March 31, 2010, exploration costs charged to operations included
development costs associated with the Oyu Tolgoi Project in Mongolia. On April 1, 2010,
Ivanhoe Mines commenced capitalizing Oyu Tolgoi Project development costs. As of this
date, reserve estimates for the Oyu Tolgoi Project had been announced and the procedural
and administrative conditions contained in the Investment Agreement were satisfied.
During the three and nine months ended September 30, 2010, additions to property, plant
and equipment included $204.4 million and $563.7 million, respectively, of Oyu Tolgoi
Project development costs. |
8
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
3. |
|
DISCONTINUED OPERATIONS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended |
|
|
Nine Months Ended |
|
|
|
September 30, |
|
|
September 30, |
|
|
|
2010 |
|
|
2009 |
|
|
2010 |
|
|
2009 |
|
Savage River (a) |
|
$ |
|
|
|
$ |
3,644 |
|
|
$ |
6,585 |
|
|
$ |
19,309 |
|
Indonesia Coal
Division (b) |
|
|
|
|
|
|
(25,547 |
) |
|
|
|
|
|
|
(32,150 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
|
|
|
$ |
(21,903 |
) |
|
$ |
6,585 |
|
|
$ |
(12,841 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
|
In February 2005, Ivanhoe Mines sold the Savage River Iron Ore Project (the
Project) in Tasmania, Australia for two initial payments totalling $21.5 million, plus
a series of five contingent, annual payments that commenced on March 31, 2006. The
annual payments are based on annual iron ore pellet tonnes sold and an escalating price
formula based on the prevailing annual Nibrasco/JSM pellet price. |
|
|
|
|
During the three month period ended June 30, 2010, Ivanhoe Mines received two payments
totalling $6.4 million in relation to the fifth annual contingent payment. The original
purchaser of the Savage River Project has disputed the estimated $22.1 million
remaining balance of the fifth annual contingent payment. Ivanhoe Mines is committed to
collecting the full amount of the fifth annual contingent payment and has included the
total estimated amount of $22.1 million in accounts receivable as at September 30,
2010. In September 2010, Ivanhoe Mines initiated arbitration proceedings. |
|
|
|
|
To date, Ivanhoe Mines has received $144.4 million in proceeds from the sale. |
|
|
(b) |
|
During December 2009, Ivanhoe Mines sold the Indonesia Coal Division, which was
composed entirely of the Mamahak Coal Project (Mamahak). Ivanhoe Mines divested its
85.0% interest in Mamahak to Kangaroo Resources Limited (Kangaroo) for consideration
comprising of $1.0 million cash and 50.0 million shares of Kangaroo possessing a fair
value of $8.8 million. Ivanhoe Mines incurred transaction costs of $1.0 million related
to the disposition of Mamahak. As a result of this transaction, Ivanhoe Mines held 6.7%
of the issued and outstanding shares of Kangaroo on December 23, 2009, the closing date,
and those shares are subject to a one year hold period. |
4. |
|
CASH AND CASH EQUIVALENTS |
Cash and cash equivalents at September 30, 2010 included SouthGobi Resources Ltd.s (Canada)
(57.3% owned) (SouthGobi) balance of $613.5 million (December 31, 2009 $357.3 million)
and Ivanhoe Australia Ltd.s (Australia) (62.1% owned) (Ivanhoe Australia) balance of
$174.4 million (December 31, 2009 $10.6 million), which were not available for Ivanhoe
Mines general corporate purposes.
9
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
|
|
|
|
|
|
|
|
|
|
|
September 30, |
|
|
December 31, |
|
|
|
2010 |
|
|
2009 |
|
|
|
|
|
|
|
|
|
|
Investments in companies subject to significant
influence: |
|
|
|
|
|
|
|
|
Altynalmas Gold Ltd. (a) |
|
$ |
1,367 |
|
|
$ |
9,860 |
|
Exco Resources N.L. (b) |
|
|
16,161 |
|
|
|
10,499 |
|
Investments available-for-sale (c) |
|
|
65,302 |
|
|
|
63,276 |
|
Investments held-for-trading (d) |
|
|
6,027 |
|
|
|
9,876 |
|
|
|
|
|
|
|
|
|
|
$ |
88,857 |
|
|
$ |
93,511 |
|
|
|
|
|
|
|
|
|
(a) |
|
On October 3, 2008, Ivanhoe Mines closed an agreement with several strategic
partners whereby Altynalmas Gold Ltd. (Altynalmas) issued shares to acquire a 100%
participating interest in Bakyrchik Mining Venture (BMV) and a 100% participating
interest in Intergold Capital LLP (IGC). Both IGC and BMV are limited liability
partnerships established under the laws of Kazakhstan that are engaged in the
exploration and development of minerals in Kazakhstan. As a result of this transaction,
Ivanhoe Mines investment in Altynalmas was diluted to 49%. Ivanhoe Mines ceased
consolidating Altynalmas on October 3, 2008 and commenced equity accounting for its
investment. |
|
|
|
|
On March 8, 2010, all of the parties to the original agreement agreed to put themselves
into the position they would be in as if a certain entity was not a party to the
original agreement. The corresponding amendments made to the original agreement
resulted in Ivanhoe Mines interest in Altynalmas increasing from 49% to 50%. |
|
|
|
|
|
|
|
|
|
|
|
September 30, |
|
|
December 31, |
|
|
|
2010 |
|
|
2009 |
|
|
|
|
|
|
|
|
|
|
Amount due from Altynalmas |
|
$ |
91,004 |
|
|
$ |
68,533 |
|
Carrying amount of equity method investment |
|
|
(89,637 |
) |
|
|
(58,673 |
) |
|
|
|
|
|
|
|
Net investment in Altynalmas |
|
$ |
1,367 |
|
|
$ |
9,860 |
|
|
|
|
|
|
|
|
|
|
|
Amounts advanced to Altynalmas bear interest compounded monthly at a rate per annum
equal to the one month London Inter-Bank Offered Rate plus 3.0% and are due on demand. |
|
|
|
|
During the nine month period ended September 30, 2010, Ivanhoe Mines recorded a
$30,964,000 (2009 $29,683,000) equity loss on this investment. |
|
|
(b) |
|
During the three month period ended September 30, 2010, Ivanhoe Mines acquired
13,486,365 shares of Exco Resources N.L. (Exco) at a cost of $5,323,000
(Aud$5,886,000). |
|
|
|
|
Also during the nine month period ended September 30, 2010, Ivanhoe Mines recorded a
$749,000 (2009 $1,156,000) equity loss on its investment in Exco. |
|
|
|
|
As at September 30, 2010, the market value of Ivanhoe Mines 22.9% investment in Exco
was $37,573,000 (Aud$38,851,000). |
10
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
5. |
|
LONG-TERM INVESTMENTS (Continued) |
|
(c) |
|
Investments available-for-sale |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
September 30, 2010 |
|
|
December 31, 2009 |
|
|
|
Equity |
|
|
Cost |
|
|
Unrealized |
|
|
Fair |
|
|
Equity |
|
|
Cost |
|
|
Unrealized |
|
|
Fair |
|
|
|
Interest |
|
|
Basis |
|
|
Gain |
|
|
Value |
|
|
Interest |
|
|
Basis |
|
|
Gain (Loss) |
|
|
Value |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Entrée Gold Inc. |
|
|
12.2 |
% |
|
$ |
19,957 |
|
|
$ |
19,864 |
|
|
$ |
39,821 |
|
|
|
14.3 |
% |
|
$ |
19,957 |
|
|
$ |
12,799 |
|
|
$ |
32,756 |
|
Emmerson Resources Limited |
|
|
10.0 |
% |
|
|
3,361 |
|
|
|
1,361 |
|
|
|
4,722 |
|
|
|
10.0 |
% |
|
|
3,107 |
|
|
|
6,637 |
|
|
|
9,744 |
|
Intec Ltd. (i) |
|
|
3.0 |
% |
|
|
36 |
|
|
|
|
|
|
|
36 |
|
|
|
4.8 |
% |
|
|
521 |
|
|
|
(3 |
) |
|
|
518 |
|
GoviEx Gold Inc. |
|
|
1.5 |
% |
|
|
1,043 |
|
|
|
|
|
|
|
1,043 |
|
|
|
1.5 |
% |
|
|
1,043 |
|
|
|
|
|
|
|
1,043 |
|
Ivanhoe Nickel & Platinum
Ltd. (ii) |
|
|
6.3 |
% |
|
|
19,492 |
|
|
|
|
|
|
|
19,492 |
|
|
|
6.1 |
% |
|
|
18,929 |
|
|
|
|
|
|
|
18,929 |
|
Other |
|
|
|
|
|
|
60 |
|
|
|
128 |
|
|
|
188 |
|
|
|
|
|
|
|
60 |
|
|
|
226 |
|
|
|
286 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
43,949 |
|
|
$ |
21,353 |
|
|
$ |
65,302 |
|
|
|
|
|
|
$ |
43,617 |
|
|
$ |
19,659 |
|
|
$ |
63,276 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(i) |
|
During the nine month period ended September 30, 2010, Ivanhoe Mines
recorded an impairment provision of $485,000 against the investment in Intec Ltd.
(Intec) based on an assessment of the fair value of Intec. |
|
(ii) |
|
During the three month period ended March 31, 2010, Ivanhoe Mines
acquired 125,665 common shares of Ivanhoe Nickel and Platinum Ltd. (Ivanplats) at
a cost of $563,000. |
As at September 30, 2010, Ivanhoe Mines held a 9.2% equity interest in Ivanplats on
a fully diluted basis.
|
(d) |
|
Investments held-for-trading |
As at September 30, 2010, the market value of Ivanhoe Mines 6.4% investment in Kangaroo
Resources Limited was $6,027,000, resulting in an unrealized loss of $3,849,000 during
the nine month period ended September 30, 2010.
6. |
|
OTHER LONG-TERM INVESTMENTS |
|
|
|
|
|
|
|
|
|
|
|
September 30, |
|
|
December 31, |
|
|
|
2010 |
|
|
2009 |
|
|
|
|
|
|
|
|
|
|
Long-Term Notes (a) |
|
$ |
28,265 |
|
|
$ |
24,689 |
|
Government of Mongolia Treasury Bills (b) |
|
|
78,463 |
|
|
|
73,152 |
|
Government of Mongolia Tax Prepayment (b) |
|
|
35,659 |
|
|
|
|
|
Money Market investments (c) |
|
|
70,032 |
|
|
|
47,194 |
|
|
|
|
|
|
|
|
|
|
$ |
212,419 |
|
|
$ |
145,035 |
|
|
|
|
|
|
|
|
11
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
6. |
|
OTHER LONG-TERM INVESTMENTS (Continued) |
As at September 30, 2010, the Company held $66.3 million principal amount of Long-Term
Notes (received in 2009 upon the completion of the Asset-Backed Commercial Paper
restructuring) which was recorded at a fair value of $28.3 million. The increase from
December 2009 in principal of $1.1 million was due to the strengthening of the Canadian
dollar ($1.3 million), offset by principal redemptions ($0.2 million). The Company has
designated the Long-Term Notes as held-for-trading. The Long-Term Notes are recorded at
fair value with unrealized holding gains and losses included in earnings.
There is a significant amount of uncertainty in estimating the amount and timing of
cash flows associated with the Long-Term Notes. The Company has estimated the fair
value of the Long-Term Notes considering information provided on the restructuring, the
best available public information regarding market conditions and other factors that a
market participant would consider for such investments.
The Company is aware of a limited number of trades in the Long-Term Notes that occurred
prior to September 30, 2010, but does not consider them to be of sufficient volume or
value to constitute an active market. Accordingly, the Company has not used these
trades to determine the fair value of its Long-Term Notes.
The Company has used a discounted cash flow approach to value the Long-Term Notes as at
September 30, 2010 incorporating the following assumptions:
|
|
|
|
|
Bankers Acceptance Rate: |
|
|
1.10 |
% |
Discount Rates: |
|
9% to 25 |
% |
Maturity Dates: |
|
6.2 years |
|
Expected Return of Principal: |
|
|
|
|
A-1 Notes |
|
|
100 |
% |
A-2 Notes |
|
|
100 |
% |
B Notes |
|
|
10 |
% |
C Notes |
|
|
0 |
% |
IA Notes |
|
|
0 |
% |
TA Notes |
|
|
100 |
% |
Based on the discounted cash flow model as at September 30, 2010, the fair value of the
Long-Term Notes was estimated at $28.3 million. As a result of this valuation, the
Company recorded an unrealized trading gain of $3.2 million for the nine month period
ended September 30, 2010.
Continuing uncertainties regarding the value of the assets that underlie the Long-Term
Notes, the amount and timing of cash flows and changes in general economic conditions
could give rise to a further change in the fair value of the Companys investment in
the Long-Term Notes, which would impact the Companys results from operations. A 1.0%
increase, representing 100 basis points, in the discount rate will decrease the fair
value of the Long-Term Notes by approximately $1.5 million.
12
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
6. |
|
OTHER LONG-TERM INVESTMENTS (Continued) |
|
(b) |
|
Government of Mongolia Treasury Bill and Tax Prepayment |
On October 6, 2009, Ivanhoe Mines agreed to purchase three Treasury Bills (T-Bills)
from the Mongolian Government, having an aggregate face value of $287.5 million, for
the aggregate sum of $250.0 million. The annual rate of interest on the T-Bills was set
at 3.0%. The initial T-Bill, with a face-value of $115.0 million, was purchased by
Ivanhoe Mines on October 20, 2009 for $100.0 million and will mature on October 20,
2014.
However, on March 31, 2010 Ivanhoe Mines agreed to an alternative arrangement for the
advancement of funds that would not involve the purchase of the remaining two T-Bills.
Specifically, rather than purchasing the second and third remaining T-Bills, with face
values of $57.5 million and $115.0 million respectively, Ivanhoe Mines has agreed to
make a series of tax prepayments.
|
|
|
The first tax prepayment of $50.0 million was made pursuant to this
arrangement on April 7, 2010. |
|
|
|
The second tax prepayment of $100.0 million will be made within 14 days of
Oyu Tolgoi LLC fully drawing down the financing necessary to enable the
complete construction of the Oyu Tolgoi Project, or on June 30, 2011,
whichever date is earlier. |
The annual rate of interest on the tax prepayments is 1.75% compounding quarterly from
the date on which such prepayments are made to the Mongolian Government by Ivanhoe
Mines. Unless already off-set fully against Mongolian taxes, the Mongolian Government
must immediately repay any remaining tax prepayment balance, including accrued
interest, on the fifth anniversary of the date the tax prepayment was made.
The Company has designated the T-Bill and first tax prepayment as available-for-sale
investments because they were not purchased with the intent of selling them in the near
term and the Companys intention to hold them to maturity is uncertain. The fair
values of the T-Bill and first tax prepayment are estimated based on available public
information regarding what market participants would consider for such investments.
Changes in the fair value of available-for-sale investments are recognized in
accumulated other comprehensive income.
The Company has used a discounted cash flow approach to value the T-Bill at September
30, 2010 incorporating the following assumptions:
|
|
|
|
|
|
|
T-Bill |
|
Face Value: |
|
$ |
115,000,000 |
|
Discount Rates: |
|
|
9.9 |
% |
Term to Maturity |
|
4.1 years |
|
Based on the discounted cash flow model as at September 30, 2010, the fair value of the
T-Bill was estimated at $78.5 million. As a result of this valuation, Ivanhoe Mines
recorded an unrealized gain of $3.2 million in accumulated other comprehensive income
for the nine month period ended September 30, 2010.
13
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
6. |
|
OTHER LONG-TERM INVESTMENTS (Continued) |
|
(b) |
|
Government of Mongolia Treasury Bill and Tax Prepayment (continued) |
The Company has used a discounted cash flow approach to value the first tax prepayment
at September 30, 2010 incorporating the following assumptions:
|
|
|
|
|
|
|
First Tax |
|
|
|
Prepayment |
|
Face Value: |
|
$ |
50,000,000 |
|
Discount Rates: |
|
|
9.9 |
% |
Term to Maturity |
|
4.5 years |
|
Based on the discounted cash flow model as at September 30, 2010, the fair value of the
first tax prepayment was estimated at $35.7 million. As a result of this valuation,
Ivanhoe Mines recorded an unrealized loss of $14.8 million in accumulated other
comprehensive income for the nine month period ended September 30, 2010.
|
(c) |
|
Money Market Investments |
As at September 30, 2010, Ivanhoe Mines held $70.0 million of money market investments
with remaining maturities in excess of one year.
7. |
|
PROPERTY, PLANT AND EQUIPMENT |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
September 30, |
|
|
December 31, |
|
|
|
2010 |
|
|
2009 |
|
|
|
|
|
|
|
Accumulated |
|
|
|
|
|
|
|
|
|
|
Accumulated |
|
|
|
|
|
|
|
|
|
|
Depletion and |
|
|
|
|
|
|
|
|
|
|
Depletion and |
|
|
|
|
|
|
|
|
|
|
Depreciation, |
|
|
|
|
|
|
|
|
|
|
Depreciation, |
|
|
|
|
|
|
|
|
|
|
Including |
|
|
Net Book |
|
|
|
|
|
|
Including |
|
|
Net Book |
|
|
|
Cost |
|
|
Write-downs |
|
|
Value |
|
|
Cost |
|
|
Write-downs |
|
|
Value |
|
Mining plant and equipment |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ovoot Tolgoi, Mongolia |
|
$ |
10,647 |
|
|
$ |
(1,141 |
) |
|
$ |
9,506 |
|
|
$ |
9,991 |
|
|
$ |
(359 |
) |
|
$ |
9,632 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Other mineral property interests |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Oyu Tolgoi, Mongolia |
|
$ |
43,792 |
|
|
$ |
(6,311 |
) |
|
$ |
37,481 |
|
|
$ |
43,792 |
|
|
$ |
(6,296 |
) |
|
$ |
37,496 |
|
Ovoot Tolgoi, Mongolia |
|
|
20,252 |
|
|
|
(544 |
) |
|
|
19,708 |
|
|
|
16,264 |
|
|
|
(83 |
) |
|
|
16,181 |
|
Cloncurry, Australia |
|
|
24,993 |
|
|
|
(126 |
) |
|
|
24,867 |
|
|
|
24,403 |
|
|
|
(126 |
) |
|
|
24,277 |
|
Other exploration projects |
|
|
1,244 |
|
|
|
(1,244 |
) |
|
|
|
|
|
|
1,335 |
|
|
|
(1,306 |
) |
|
|
29 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
90,281 |
|
|
$ |
(8,225 |
) |
|
$ |
82,056 |
|
|
$ |
85,794 |
|
|
$ |
(7,811 |
) |
|
$ |
77,983 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Other capital assets |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Oyu Tolgoi, Mongolia
(Note 2) |
|
$ |
22,616 |
|
|
$ |
(13,661 |
) |
|
$ |
8,955 |
|
|
$ |
16,119 |
|
|
$ |
(11,756 |
) |
|
$ |
4,363 |
|
Ovoot Tolgoi, Mongolia |
|
|
142,302 |
|
|
|
(17,027 |
) |
|
|
125,275 |
|
|
|
74,469 |
|
|
|
(8,323 |
) |
|
|
66,146 |
|
Cloncurry, Australia |
|
|
43,670 |
|
|
|
(2,334 |
) |
|
|
41,336 |
|
|
|
5,724 |
|
|
|
(1,557 |
) |
|
|
4,167 |
|
Other exploration projects |
|
|
3,378 |
|
|
|
(2,611 |
) |
|
|
767 |
|
|
|
2,657 |
|
|
|
(2,128 |
) |
|
|
529 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
211,966 |
|
|
$ |
(35,633 |
) |
|
$ |
176,333 |
|
|
$ |
98,969 |
|
|
$ |
(23,764 |
) |
|
$ |
75,205 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Capital works in progress |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Oyu Tolgoi, Mongolia
(Note 2) |
|
$ |
612,232 |
|
|
$ |
|
|
|
$ |
612,232 |
|
|
$ |
54,991 |
|
|
$ |
|
|
|
$ |
54,991 |
|
Ovoot Tolgoi, Mongolia |
|
|
7,540 |
|
|
|
|
|
|
|
7,540 |
|
|
|
970 |
|
|
|
|
|
|
|
970 |
|
Cloncurry, Australia |
|
|
1,252 |
|
|
|
|
|
|
|
1,252 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
621,024 |
|
|
$ |
|
|
|
$ |
621,024 |
|
|
$ |
55,961 |
|
|
$ |
|
|
|
$ |
55,961 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
933,918 |
|
|
$ |
(44,999 |
) |
|
$ |
888,919 |
|
|
$ |
250,715 |
|
|
$ |
(31,934 |
) |
|
$ |
218,781 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
8. |
|
AMOUNTS DUE UNDER CREDIT FACILITIES |
|
|
|
|
|
|
|
|
|
|
|
September 30, |
|
|
December 31, |
|
|
|
2010 |
|
|
2009 |
|
Current |
|
|
|
|
|
|
|
|
Non-revolving bank loans (a) |
|
$ |
14,486 |
|
|
$ |
14,544 |
|
Revolving line of credit facility (b) |
|
|
2,406 |
|
|
|
3,000 |
|
|
|
|
|
|
|
|
|
|
$ |
16,892 |
|
|
$ |
17,544 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Non-Current |
|
|
|
|
|
|
|
|
Two-year extendible loan facility (c) |
|
$ |
38,865 |
|
|
$ |
37,979 |
|
|
|
|
|
|
|
|
|
(a) |
|
In October 2007, Ivanhoe Mines obtained non-revolving bank loans which are due on
demand and secured against certain securities and other investments. |
|
(b) |
|
In December 2009, Ivanhoe Mines obtained a one year revolving line of credit
facility, which is secured against certain equipment in Mongolia. |
|
(c) |
|
In April 2009, Ivanhoe Mines obtained a non-revolving, two-year extendible loan
facility, which is secured against certain securities and other investments. |
9. |
|
CONVERTIBLE CREDIT FACILITIES |
|
|
|
|
|
|
|
|
|
|
|
September 30, |
|
|
December 31, |
|
|
|
2010 |
|
|
2009 |
|
|
|
|
|
|
|
|
|
|
Principal amount of convertible credit
facility |
|
$ |
350,000 |
|
|
$ |
350,000 |
|
Accrued paid-in-kind interest |
|
|
50,832 |
|
|
|
40,678 |
|
|
|
|
|
|
|
|
|
|
|
400,832 |
|
|
|
390,678 |
|
(Deduct) add: |
|
|
|
|
|
|
|
|
Beneficial conversion feature |
|
|
(36,314 |
) |
|
|
(30,250 |
) |
Share purchase warrants |
|
|
(9,403 |
) |
|
|
(9,403 |
) |
Accretion of discount |
|
|
45,717 |
|
|
|
27,891 |
|
|
|
|
|
|
|
|
|
|
|
400,832 |
|
|
|
378,916 |
|
Credited to share capital upon conversion |
|
|
(400,832 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
|
|
|
$ |
378,916 |
|
|
|
|
|
|
|
|
In September 2007, Rio Tinto provided the Company with a $350.0 million convertible
credit facility to finance ongoing mine development activities at the Oyu Tolgoi
Project. In 2007, the Company made an initial draw against the credit facility of
$150.0 million and further draws totalling $200.0 million were made in 2008.
15
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
9. |
|
CONVERTIBLE CREDIT FACILITIES (Continued) |
|
(a) |
|
Rio Tinto (continued) |
Amounts advanced under the credit facility bore interest at a rate per annum equal to
the three-month London Inter-Bank Offered Rate plus 3.3%, and matured on September 12,
2010. In September 2010, the Company issued 40.1 million common shares to Rio Tinto
upon the automatic conversion of the maturing convertible credit facility. The $350.0
million outstanding principal and $50.8 million accrued interest were converted at a
price of $10.00 per common share.
On the date of conversion, the $437.1 million aggregate carrying amount of the
convertible credit facility liability ($400.8 million) and associated beneficial
conversion feature ($36.3 million) was credited to share capital to reflect the common
shares issued.
As part of the credit facility transaction, Rio Tinto also received share purchase
warrants exercisable to purchase up to 35.0 million common shares of the Company at a
price of $10.00 per share for a period of five years (Note 10 (c)).
During the three and nine months ended September 30, 2010, Ivanhoe Mines capitalized
$2.0 million and $2.7 million of interest expense and $5.2 million and $6.2 million of
accretion expense, respectively, incurred on the convertible credit facility.
|
(b) |
|
China Investment Corporation |
|
|
|
|
|
|
|
|
|
|
|
September 30, |
|
|
December 31, |
|
|
|
2010 |
|
|
2009 |
|
|
|
|
|
|
|
|
|
|
Principal amount of convertible debenture |
|
$ |
500,000 |
|
|
$ |
500,000 |
|
|
|
|
|
|
|
|
|
|
(Deduct) add: |
|
|
|
|
|
|
|
|
Bifurcation of embedded derivative liability |
|
|
(313,292 |
) |
|
|
(313,292 |
) |
Accretion of discount |
|
|
55 |
|
|
|
10 |
|
Reduction of carrying amount upon
partial conversion |
|
|
(93,370 |
) |
|
|
|
|
|
|
|
|
|
|
|
Carrying amount of debt host contract |
|
|
93,393 |
|
|
|
186,718 |
|
|
|
|
|
|
|
|
|
|
Embedded derivative liability |
|
|
134,882 |
|
|
|
358,272 |
|
|
|
|
|
|
|
|
Convertible credit facility |
|
|
228,275 |
|
|
|
544,990 |
|
|
|
|
|
|
|
|
|
|
Accrued interest |
|
|
9,337 |
|
|
|
4,712 |
|
|
|
|
|
|
|
|
|
|
Transaction costs allocated to deferred
charges |
|
|
(2,800 |
) |
|
|
(5,601 |
) |
|
|
|
|
|
|
|
Net carrying amount of convertible debenture |
|
$ |
234,812 |
|
|
$ |
544,101 |
|
|
|
|
|
|
|
|
16
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
9. |
|
CONVERTIBLE CREDIT FACILITIES (Continued) |
|
(b) |
|
China Investment Corporation (continued) |
On November 19, 2009, SouthGobi issued a convertible debenture to a wholly-owned
subsidiary of China Investment Corporation (CIC) for $500.0 million. The convertible
debenture is secured, bears interest at 8.0% (6.4% payable semi-annually in cash and
1.6% payable annually in shares of SouthGobi) and has a term of 30 years. The
financing primarily will support an accelerated investment program in Mongolia and up
to $120.0 million of the financing may also be used for working capital, repayment of
debt due on funding, general and administrative expense and other general corporate
purposes.
Pursuant to the convertible debentures terms, SouthGobi had the right to call for the
conversion of up to $250.0 million of the convertible debenture upon SouthGobi
achieving a public float of 25.0% of its common shares under certain agreed
circumstances. On March 29, 2010, SouthGobi exercised this right and completed the
conversion of $250.0 million of the convertible debenture into 21.5 million shares at a
conversion price of $11.64 (Cdn$11.88). Also on March 29, 2010, SouthGobi settled the
$1.4 million accrued interest payable in shares on the $250.0 million converted by
issuing 0.1 million shares at the 50-day VWAP conversion price of $15.97 (Cdn$16.29).
On April 1, 2010, SouthGobi settled the outstanding accrued interest payable in cash on
the $250.0 million converted with a cash payment of $5.7 million.
As at March 29, 2010, the fair value of the embedded derivative liability
associated with the $250.0 million converted was $102.8 million, a decrease of $9.4
million compared to its fair value at December 31, 2009. The $347.6 million fair value
of the SouthGobi shares issued upon conversion exceeded the $193.3 million aggregate
carrying value of the debt host contract, embedded derivative liability and deferred
charges. The difference of $154.3 million was recorded as a loss on conversion of the
convertible debenture.
As at September 30, 2010, the fair value of the embedded derivative liability
associated with the remaining $250.0 million principal outstanding was determined to be
$134.9 million.
The embedded derivative liability was valued using a Monte Carlo simulation valuation
model. A Monte Carlo simulation model is a valuation model that relies on random
sampling and is often used when modeling systems with a large number of inputs and
where there is significant uncertainty in the future value of inputs and where the
movement in the inputs can be independent of each other. Some of the key inputs used
by the Monte Carlo simulation include: floor and ceiling conversion prices, risk-free
rate of return, expected volatility of SouthGobis share price, forward Cdn$ exchange
rate curves and spot Cdn$ exchange rates.
17
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
9. |
|
CONVERTIBLE CREDIT FACILITIES (Continued) |
|
(b) |
|
China Investment Corporation (continued) |
Assumptions used in the Monte Carlo valuation model are as follows:
|
|
|
|
|
|
|
|
|
|
|
September 30, |
|
|
December 31, |
|
|
|
2010 |
|
|
2009 |
|
|
|
|
|
|
|
|
|
|
Floor conversion price |
|
Cdn$ |
8.88 |
|
|
Cdn$ |
8.88 |
|
Ceiling conversion price |
|
Cdn$ |
11.88 |
|
|
Cdn$ |
11.88 |
|
Expected volatility |
|
|
74 |
% |
|
|
75 |
% |
Risk-free rate of return |
|
|
3.27 |
% |
|
|
4.09 |
% |
Spot Cdn$ exchange rate |
|
|
0.97 |
|
|
|
0.96 |
|
Forward Cdn$ exchange rate curve |
|
|
0.93 - 0.97 |
|
|
|
0.90 - 0.95 |
|
|
(a) |
|
Equity Incentive Plan |
Stock-based compensation charged to operations was allocated between exploration
expenses and general and administrative expenses as follows:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended |
|
|
Nine Months Ended |
|
|
|
September 30, |
|
|
September 30, |
|
|
|
2010 |
|
|
2009 |
|
|
2010 |
|
|
2009 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Exploration (i) |
|
$ |
6,437 |
|
|
$ |
4,513 |
|
|
$ |
18,691 |
|
|
$ |
16,085 |
|
General and administrative |
|
|
2,774 |
|
|
|
2,244 |
|
|
|
7,551 |
|
|
|
11,447 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
9,211 |
|
|
$ |
6,757 |
|
|
$ |
26,242 |
|
|
$ |
27,532 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(i) |
|
During the three and nine months ended September 30, 2010, stock-based
compensation of $1,590,000 and $3,189,000 (2009 $nil and $nil), respectively,
relating to the development of the Oyu Tolgoi Project was capitalized as property,
plant and equipment (Note 2). |
18
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
10. |
|
SHARE CAPITAL (Continued) |
|
(a) |
|
Equity Incentive Plan (continued) |
|
|
|
|
Stock-based compensation charged to operations was incurred by Ivanhoe Mines as follows: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended |
|
|
Nine Months Ended |
|
|
|
September 30, |
|
|
September 30, |
|
|
|
2010 |
|
|
2009 |
|
|
2010 |
|
|
2009 |
|
|
Ivanhoe Mines Ltd. (i) |
|
$ |
3,606 |
|
|
$ |
3,272 |
|
|
$ |
11,255 |
|
|
$ |
16,909 |
|
SouthGobi Resources Ltd. |
|
|
3,234 |
|
|
|
1,688 |
|
|
|
7,927 |
|
|
|
5,598 |
|
Ivanhoe Australia Ltd. |
|
|
2,371 |
|
|
|
1,797 |
|
|
|
7,060 |
|
|
|
5,025 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
9,211 |
|
|
$ |
6,757 |
|
|
$ |
26,242 |
|
|
$ |
27,532 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(i) |
|
During the nine months ended September 30, 2010, 2,612,500 options
were exercised, 134,000 options were cancelled and 1,312,500 options were granted.
These granted options have a weighted average exercise price of Cdn$15.51, lives
of seven years, and vest over periods ranging from one to four years. The
weighted average grant-date fair value of stock options granted during the nine
months ended September 30, 2010 was Cdn$9.02. The fair value of these options was
determined using the Black-Scholes option pricing model. The option valuation was
based on a weighted average expected life of 3.6 years, risk-free interest rate of
2.43%, expected volatility of 77%, and dividend yield of nil%. |
|
|
|
|
During the three and nine months ended September 30, 2010, stock-based
compensation of $1,590,000 and $3,189,000 (2009 $nil and $nil), respectively,
relating to the development of the Oyu Tolgoi Project was capitalized as
property, plant and equipment (Note 2). |
In March 2010, the Company issued 15.0 million shares to Rio Tinto at Cdn$16.31 per
share, for total proceeds of $241.1 million (Cdn$244.7 million) (Note 13 (b)).
In June 2010, Rio Tinto exercised its 46.0 million Series A warrants, which were
granted during 2006. Pursuant to the exercise of the Series A warrants, the Company
issued 46.0 million shares to Rio Tinto at $8.54 per share for total proceeds of $393.1
million. As a result, the $8.9 million carrying value of the Series A warrants was
reclassified from share purchase warrants to share capital.
In September 2010, the Company issued 40.1 million shares to Rio Tinto upon the
conversion of Rio Tintos maturing convertible credit facility (Note 9 (a) and 13 (b)).
19
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
10. |
|
SHARE CAPITAL (Continued) |
|
(b) |
|
Rio Tinto Placements (continued) |
As at September 30, 2010, 46,026,522 share purchase warrants granted to Rio Tinto
during 2006 were outstanding. These warrants have exercise prices ranging between
$8.38 and $9.02 per share and are exercisable until two years after the earlier of the
date an approved Investment Agreement is reached or October 27, 2009.
In addition to the share purchase warrants granted to Rio Tinto during 2006, the
following were granted to Rio Tinto during 2008 and were outstanding as at September
30, 2010:
|
(i) |
|
720,203 share purchase warrants with exercise prices of Cdn$3.15 per
share. These warrants are exercisable until one year after the earlier of the
date an approved Investment Agreement is reached or October 27, 2009. In October
2010, Rio Tinto exercised all 720,203 share purchase warrants. |
|
(ii) |
|
720,203 share purchase warrants with exercise prices of Cdn$3.15 per
share. These warrants are exercisable until two years after the earlier of the
date an approved Investment Agreement is reached or October 27, 2009. |
As part of the convertible credit facility disclosed in Note 9 (a), Rio Tinto received
share purchase warrants exercisable to purchase up to 35.0 million common shares of the
Company at a price of $10.00 per share at any time on or before October 24, 2012. As
at September 30, 2010, 35.0 million share purchase warrants were exercisable.
20
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
11. |
|
ACCUMULATED OTHER COMPREHENSIVE INCOME |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended |
|
|
Nine Months Ended |
|
|
|
September 30, |
|
|
September 30, |
|
|
|
2010 |
|
|
2009 |
|
|
2010 |
|
|
2009 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Accumulated OCI at beginning of period |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Long-term investments, net of tax of $nil, $nil, $1,896, $nil |
|
$ |
7,223 |
|
|
$ |
(3,674 |
) |
|
$ |
17,763 |
|
|
$ |
(8,635 |
) |
Other long-term investments, net of tax of $nil, $nil, $nil, $nil |
|
|
(40,690 |
) |
|
|
|
|
|
|
(27,448 |
) |
|
|
|
|
Currency translation adjustment, net of tax of $nil, $nil, $nil, $nil |
|
|
(8,198 |
) |
|
|
(11,622 |
) |
|
|
(6,015 |
) |
|
|
(18,256 |
) |
Noncontrolling interests |
|
|
15,537 |
|
|
|
2,042 |
|
|
|
1,122 |
|
|
|
2,669 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
(26,128 |
) |
|
$ |
(13,254 |
) |
|
$ |
(14,578 |
) |
|
$ |
(24,222 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Other comprehensive income (loss) for the period: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Changes in fair value of long-term investments |
|
$ |
14,133 |
|
|
$ |
34,105 |
|
|
$ |
1,694 |
|
|
$ |
39,066 |
|
Changes in fair value of other long-term investments |
|
|
1,703 |
|
|
|
|
|
|
|
(11,539 |
) |
|
|
|
|
Currency translation adjustments |
|
|
18,906 |
|
|
|
4,497 |
|
|
|
16,723 |
|
|
|
11,131 |
|
Noncontrolling interests |
|
|
(5,648 |
) |
|
|
(1,417 |
) |
|
|
8,767 |
|
|
|
(2,044 |
) |
Less: reclassification adjustments for gains/losses recorded in earnings: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Investments: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Other than temporary impairment charges |
|
|
|
|
|
|
|
|
|
|
3 |
|
|
|
|
|
Gains realized on sale |
|
|
|
|
|
|
(1,424 |
) |
|
|
|
|
|
|
(1,424 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
Other comprehensive income, before tax |
|
|
29,094 |
|
|
|
35,761 |
|
|
|
15,648 |
|
|
|
46,729 |
|
Income tax (recovery) expense related to OCI |
|
|
(1,340 |
) |
|
|
|
|
|
|
556 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Other comprehensive income, net of tax |
|
$ |
27,754 |
|
|
$ |
35,761 |
|
|
$ |
16,204 |
|
|
$ |
46,729 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Accumulated OCI at end of period |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Long-term investments, net of tax of $1,340, $nil, $1,340, $nil |
|
$ |
20,016 |
|
|
$ |
29,007 |
|
|
$ |
20,016 |
|
|
$ |
29,007 |
|
Other long-term investments, net of tax of $nil, $nil, $nil, $nil |
|
|
(38,987 |
) |
|
|
|
|
|
|
(38,987 |
) |
|
|
|
|
Currency translation adjustment, net of tax of $nil, $nil, $nil, $nil |
|
|
10,708 |
|
|
|
(7,125 |
) |
|
|
10,708 |
|
|
|
(7,125 |
) |
Noncontrolling interests |
|
|
9,889 |
|
|
|
625 |
|
|
|
9,889 |
|
|
|
625 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
1,626 |
|
|
$ |
22,507 |
|
|
$ |
1,626 |
|
|
$ |
22,507 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
21
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
12. |
|
NONCONTROLLING INTERESTS |
At September 30, 2010 there were noncontrolling interests in SouthGobi, Ivanhoe Australia and
Oyu Tolgoi LLC:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Noncontrolling Interests |
|
|
|
|
|
|
|
Ivanhoe |
|
|
Oyu Tolgoi |
|
|
|
|
|
|
SouthGobi |
|
|
Australia |
|
|
LLC (a) |
|
|
Total |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Balance, December 31, 2009 |
|
$ |
2,478 |
|
|
$ |
(1,526 |
) |
|
$ |
|
|
|
$ |
952 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Changes in noncontrolling interests arising
from changes in ownership interests |
|
|
309,419 |
|
|
|
79,687 |
|
|
|
(338,080 |
) |
|
|
51,026 |
|
Noncontrolling interests share of loss |
|
|
(23,053 |
) |
|
|
(7,718 |
) |
|
|
(11,233 |
) |
|
|
(42,004 |
) |
Noncontrolling interests share of other
comprehensive income |
|
|
|
|
|
|
4,488 |
|
|
|
768 |
|
|
|
5,256 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Balance, September 30, 2010 |
|
$ |
288,844 |
|
|
$ |
74,931 |
|
|
$ |
(348,545 |
) |
|
$ |
15,230 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
|
The Shareholders Agreement, which was signed and approved on October 6, 2009,
established the basis upon which the Mongolian Government would, in accordance with
Mongolian law, through its wholly-state-owned company, Erdenes MGL LLC, obtain and hold
an initial 34% equity interest in Oyu Tolgoi LLC and provides for the respective rights
and obligations of the shareholders of Oyu Tolgoi LLC. |
On May 31, 2010, pursuant to the terms of the Shareholders Agreement, the Mongolian
Government obtained a 34% interest in Oyu Tolgoi LLC upon the receipt of fully
registered shares of Oyu Tolgoi LLC. In accordance with the ASC guidance for
consolidation accounting, the Company continued to consolidate its remaining 66%
interest in Oyu Tolgoi LLC. No value was assigned to the consideration received by the
Company as the fair value of neither the consideration received nor the asset
relinquished was determinable within reasonable limits. Accordingly, on May 31, 2010,
the Company recognized a deficit noncontrolling interest balance of $338.1 million
associated with noncontrolling interests share of the carrying amount of Oyu Tolgoi
LLCs net deficit. Accumulated other comprehensive income and additional paid-in
capital were adjusted by $14.0 million and $324.1 million, respectively.
22
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
13. |
|
CASH FLOW INFORMATION |
|
(a) |
|
Reconciliation of net loss to net cash flow used in operating activities |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended |
|
|
Nine Months Ended |
|
|
|
September 30, |
|
|
September 30, |
|
|
|
2010 |
|
|
2009 |
|
|
2010 |
|
|
2009 |
|
|
Net loss |
|
$ |
(25,272 |
) |
|
$ |
(75,727 |
) |
|
$ |
(290,761 |
) |
|
$ |
(160,861 |
) |
Income from discontinued operations |
|
|
|
|
|
|
44,932 |
|
|
|
(6,585 |
) |
|
|
35,870 |
|
Items not involving use of cash |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Stock-based compensation |
|
|
9,211 |
|
|
|
6,757 |
|
|
|
26,242 |
|
|
|
27,532 |
|
Accretion expense |
|
|
3,085 |
|
|
|
3,643 |
|
|
|
11,838 |
|
|
|
10,653 |
|
General and administrative expenses |
|
|
|
|
|
|
1,978 |
|
|
|
3,421 |
|
|
|
1,978 |
|
Depreciation |
|
|
1,279 |
|
|
|
3,541 |
|
|
|
7,376 |
|
|
|
7,410 |
|
Gain on sale of other mineral property rights |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(3,000 |
) |
Write-down of carrying values of property, plant and equipment |
|
|
1,764 |
|
|
|
|
|
|
|
1,764 |
|
|
|
|
|
Accrued interest income |
|
|
(2,465 |
) |
|
|
|
|
|
|
(7,585 |
) |
|
|
|
|
Accrued interest expense |
|
|
5,918 |
|
|
|
3,804 |
|
|
|
13,243 |
|
|
|
12,644 |
|
Unrealized losses on long-term investments |
|
|
(1,362 |
) |
|
|
|
|
|
|
3,849 |
|
|
|
|
|
Unrealized gains on other long-term investments |
|
|
(2,019 |
) |
|
|
(649 |
) |
|
|
(3,528 |
) |
|
|
(15 |
) |
Realized gain on redemption of other long-term investments |
|
|
(34 |
) |
|
|
(198 |
) |
|
|
(121 |
) |
|
|
(1,334 |
) |
Change in fair value of embedded derivatives |
|
|
(49,772 |
) |
|
|
|
|
|
|
(120,633 |
) |
|
|
|
|
Loss on conversion of convertible debenture |
|
|
|
|
|
|
|
|
|
|
154,316 |
|
|
|
|
|
Unrealized foreign exchange gains |
|
|
(5,533 |
) |
|
|
(23,092 |
) |
|
|
(5,646 |
) |
|
|
(37,298 |
) |
Share of loss of significantly influenced investees |
|
|
8,503 |
|
|
|
23,041 |
|
|
|
31,713 |
|
|
|
30,839 |
|
Write-down of carrying value of inventory |
|
|
7,855 |
|
|
|
|
|
|
|
14,390 |
|
|
|
|
|
Gain on sale of long-term investments |
|
|
|
|
|
|
(1,424 |
) |
|
|
|
|
|
|
(1,424 |
) |
Write-down of carrying value of long-term investments |
|
|
68 |
|
|
|
|
|
|
|
485 |
|
|
|
|
|
Deferred income taxes |
|
|
(4,432 |
) |
|
|
(8,673 |
) |
|
|
(7,205 |
) |
|
|
(8,734 |
) |
Net change in non-cash operating working capital items: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(Increase) decrease in: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Accounts receivable |
|
|
(11,439 |
) |
|
|
1,293 |
|
|
|
(17,776 |
) |
|
|
(5,495 |
) |
Inventories |
|
|
(18,352 |
) |
|
|
(189 |
) |
|
|
(33,332 |
) |
|
|
2,724 |
|
Prepaid expenses |
|
|
(4,507 |
) |
|
|
(1,290 |
) |
|
|
(6,205 |
) |
|
|
(1,983 |
) |
Increase (decrease) in: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Accounts payable and accrued liabilities |
|
|
44,869 |
|
|
|
919 |
|
|
|
88,970 |
|
|
|
(2,903 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
Cash used in operating activities of continuing operations |
|
|
(42,635 |
) |
|
|
(21,334 |
) |
|
|
(141,770 |
) |
|
|
(93,397 |
) |
Cash used in operating activities of discontinued operations |
|
|
|
|
|
|
(25,547 |
) |
|
|
|
|
|
|
(32,150 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
Cash used in operating activities |
|
$ |
(42,635 |
) |
|
$ |
(46,881 |
) |
|
$ |
(141,770 |
) |
|
$ |
(125,547 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
23
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
13. |
|
CASH FLOW INFORMATION (Continued) |
|
(b) |
|
Supplementary information regarding other non-cash transactions |
|
|
|
|
The non-cash investing and financing activities relating to continuing operations
not already disclosed in the Consolidated Statements of Cash Flows were as follows: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended |
|
|
Nine Months Ended |
|
|
|
September 30, |
|
|
September 30, |
|
|
|
2010 |
|
|
2009 |
|
|
2010 |
|
|
2009 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Investing activities: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Acquisition of property, plant
and equipment (i) |
|
$ |
|
|
|
$ |
|
|
|
$ |
(195,357 |
) |
|
$ |
|
|
Financing activites: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Conversion of convertible
credit facility (Note 9 (a)) |
|
|
(400,832 |
) |
|
|
|
|
|
|
(400,832 |
) |
|
|
|
|
Partial conversion of convertible
debenture (Note 9 (b)) |
|
|
|
|
|
|
|
|
|
|
(349,079 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
(400,832 |
) |
|
$ |
|
|
|
$ |
(945,268 |
) |
|
$ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(i) |
|
In March 2010, the Company and Rio Tinto completed an agreement
whereby the Company issued 15.0 million common shares to Rio Tinto for net
proceeds of $241.1 million (Cdn$244.7 million) (Note 10 (b)). The Company used
$195.4 million of the proceeds to purchase from Rio Tinto key mining and milling
equipment to be installed during the construction of the Oyu Tolgoi Project. |
24
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended September 30, 2010 |
|
|
|
Exploration |
|
|
Coal |
|
|
Corporate |
|
|
Consolidated |
|
|
REVENUE |
|
$ |
|
|
|
$ |
6,597 |
|
|
$ |
|
|
|
$ |
6,597 |
|
COST OF SALES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Production and delivery |
|
|
|
|
|
|
(5,975 |
) |
|
|
|
|
|
|
(5,975 |
) |
Depreciation and depletion |
|
|
|
|
|
|
(1,027 |
) |
|
|
|
|
|
|
(1,027 |
) |
Write-down of carrying value of inventory |
|
|
|
|
|
|
(7,855 |
) |
|
|
|
|
|
|
(7,855 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
COST OF SALES |
|
|
|
|
|
|
(14,857 |
) |
|
|
|
|
|
|
(14,857 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
EXPENSES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Exploration |
|
|
(33,455 |
) |
|
|
(14,676 |
) |
|
|
|
|
|
|
(48,131 |
) |
General and administrative |
|
|
|
|
|
|
|
|
|
|
(15,005 |
) |
|
|
(15,005 |
) |
Depreciation |
|
|
(206 |
) |
|
|
(40 |
) |
|
|
(6 |
) |
|
|
(252 |
) |
Accretion of asset retirement obligations |
|
|
(23 |
) |
|
|
(28 |
) |
|
|
|
|
|
|
(51 |
) |
Gain on sale of other mineral property rights |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Write-down of carrying values of property, plant and
equipment |
|
|
|
|
|
|
(1,764 |
) |
|
|
|
|
|
|
(1,764 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL EXPENSES |
|
|
(33,684 |
) |
|
|
(31,365 |
) |
|
|
(15,011 |
) |
|
|
(80,060 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
OPERATING LOSS |
|
|
(33,684 |
) |
|
|
(24,768 |
) |
|
|
(15,011 |
) |
|
|
(73,463 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
OTHER INCOME (EXPENSES) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Interest income |
|
|
2,089 |
|
|
|
627 |
|
|
|
1,056 |
|
|
|
3,772 |
|
Interest expense |
|
|
|
|
|
|
(4,891 |
) |
|
|
(1,389 |
) |
|
|
(6,280 |
) |
Accretion of convertible credit facilities |
|
|
|
|
|
|
(13 |
) |
|
|
(3,021 |
) |
|
|
(3,034 |
) |
Foreign exchange gains |
|
|
(302 |
) |
|
|
853 |
|
|
|
4,783 |
|
|
|
5,334 |
|
Listing fees SouthGobi |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Unrealized gains (losses) on long-term investments |
|
|
|
|
|
|
1,363 |
|
|
|
|
|
|
|
1,363 |
|
Unrealized gains on other long-term investments |
|
|
|
|
|
|
373 |
|
|
|
1,646 |
|
|
|
2,019 |
|
Realized gain on redemption of other long-term investments |
|
|
|
|
|
|
|
|
|
|
34 |
|
|
|
34 |
|
Change in fair value of embedded derivatives |
|
|
|
|
|
|
49,772 |
|
|
|
|
|
|
|
49,772 |
|
Loss on conversion of convertible credit facility |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Write-down of carrying value of long-term investments |
|
|
|
|
|
|
|
|
|
|
(68 |
) |
|
|
(68 |
) |
Gain on sale of long-term investment |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
LOSS BEFORE INCOME TAXES AND OTHER ITEMS |
|
|
(31,897 |
) |
|
|
23,316 |
|
|
|
(11,970 |
) |
|
|
(20,551 |
) |
Recovery for income taxes |
|
|
10 |
|
|
|
2,240 |
|
|
|
1,532 |
|
|
|
3,782 |
|
Share of loss of significantly influenced investees |
|
|
(131 |
) |
|
|
|
|
|
|
(8,372 |
) |
|
|
(8,503 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
NET LOSS FROM CONTINUING OPERATIONS |
|
|
(32,018 |
) |
|
|
25,556 |
|
|
|
(18,810 |
) |
|
|
(25,272 |
) |
INCOME FROM DISCONTINUED OPERATIONS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NET LOSS |
|
|
(32,018 |
) |
|
|
25,556 |
|
|
|
(18,810 |
) |
|
|
(25,272 |
) |
NET LOSS ATTRIBUTABLE TO NONCONTROLLING
INTERESTS |
|
|
12,336 |
|
|
|
|
|
|
|
(11,925 |
) |
|
|
411 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NET LOSS ATTRIBUTABLE TO IVANHOE MINES LTD. |
|
$ |
(19,682 |
) |
|
$ |
25,556 |
|
|
$ |
(30,735 |
) |
|
$ |
(24,861 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
CAPITAL EXPENDITURES |
|
$ |
200,545 |
|
|
$ |
22,256 |
|
|
$ |
42 |
|
|
$ |
222,843 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL ASSETS |
|
$ |
1,174,620 |
|
|
$ |
942,990 |
|
|
$ |
669,890 |
|
|
$ |
2,787,500 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
During the three months ended September 30, 2010, all of the coal divisions revenue arose from
coal sales in Mongolia to four customers. Total revenues by customer were $3.7 million, $2.0
million, $0.8 million and $0.1 million.
25
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
14. |
|
SEGMENT DISCLOSURES (Continued) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended September 30, 2009 |
|
|
|
Exploration |
|
|
Coal |
|
|
Corporate |
|
|
Consolidated |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
REVENUE |
|
$ |
|
|
|
$ |
11,871 |
|
|
$ |
|
|
|
$ |
11,871 |
|
COST OF SALES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Production and delivery |
|
|
|
|
|
|
(6,435 |
) |
|
|
|
|
|
|
(6,435 |
) |
Depreciation and depletion |
|
|
|
|
|
|
(2,202 |
) |
|
|
|
|
|
|
(2,202 |
) |
Write-down of carrying value of inventory |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
COST OF SALES |
|
|
|
|
|
|
(8,637 |
) |
|
|
|
|
|
|
(8,637 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
EXPENSES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Exploration |
|
|
(35,007 |
) |
|
|
(5,942 |
) |
|
|
|
|
|
|
(40,949 |
) |
General and administrative |
|
|
|
|
|
|
|
|
|
|
(12,464 |
) |
|
|
(12,464 |
) |
Depreciation |
|
|
(1,327 |
) |
|
|
(7 |
) |
|
|
(5 |
) |
|
|
(1,339 |
) |
Accretion of asset retirement obligations |
|
|
(22 |
) |
|
|
(18 |
) |
|
|
|
|
|
|
(40 |
) |
Gain on sale of other mineral property rights |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Write-down of carrying values of property, plant and
equipment |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL EXPENSES |
|
|
(36,356 |
) |
|
|
(14,604 |
) |
|
|
(12,469 |
) |
|
|
(63,429 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
OPERATING LOSS |
|
|
(36,356 |
) |
|
|
(2,733 |
) |
|
|
(12,469 |
) |
|
|
(51,558 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
OTHER INCOME (EXPENSES) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Interest income |
|
|
181 |
|
|
|
4 |
|
|
|
327 |
|
|
|
512 |
|
Interest expense |
|
|
|
|
|
|
|
|
|
|
(4,066 |
) |
|
|
(4,066 |
) |
Accretion of convertible credit facilities |
|
|
|
|
|
|
|
|
|
|
(3,603 |
) |
|
|
(3,603 |
) |
Foreign exchange gains |
|
|
36 |
|
|
|
(276 |
) |
|
|
19,722 |
|
|
|
19,482 |
|
Listing fees SouthGobi |
|
|
|
|
|
|
(1,599 |
) |
|
|
|
|
|
|
(1,599 |
) |
Unrealized gains (losses) on long-term investments |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Unrealized gains on other long-term investments |
|
|
|
|
|
|
|
|
|
|
649 |
|
|
|
649 |
|
Realized gain on redemption of other long-term investments |
|
|
|
|
|
|
|
|
|
|
198 |
|
|
|
198 |
|
Change in fair value of embedded derivatives |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Loss on conversion of convertible credit facility |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Write-down of carrying value of long-term investments |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Gain on sale of long-term investment |
|
|
|
|
|
|
|
|
|
|
1,424 |
|
|
|
1,424 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
LOSS BEFORE INCOME TAXES AND OTHER ITEMS |
|
|
(36,139 |
) |
|
|
(4,604 |
) |
|
|
2,182 |
|
|
|
(38,561 |
) |
Recovery for income taxes |
|
|
(190 |
) |
|
|
7,973 |
|
|
|
(5 |
) |
|
|
7,778 |
|
Share of loss of significantly influenced investees |
|
|
(804 |
) |
|
|
|
|
|
|
(22,237 |
) |
|
|
(23,041 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
NET LOSS FROM CONTINUING OPERATIONS |
|
|
(37,133 |
) |
|
|
3,369 |
|
|
|
(20,060 |
) |
|
|
(53,824 |
) |
INCOME FROM DISCONTINUED OPERATIONS |
|
|
|
|
|
|
(25,547 |
) |
|
|
3,644 |
|
|
|
(21,903 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
NET LOSS |
|
|
(37,133 |
) |
|
|
(22,178 |
) |
|
|
(16,416 |
) |
|
|
(75,727 |
) |
NET LOSS ATTRIBUTABLE TO NONCONTROLLING
INTERESTS |
|
|
1,752 |
|
|
|
|
|
|
|
4,217 |
|
|
|
5,969 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NET LOSS ATTRIBUTABLE TO IVANHOE MINES LTD. |
|
$ |
(35,381 |
) |
|
$ |
(22,178 |
) |
|
$ |
(12,199 |
) |
|
$ |
(69,758 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
CAPITAL EXPENDITURES |
|
$ |
987 |
|
|
$ |
8,723 |
|
|
$ |
10 |
|
|
$ |
9,720 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL ASSETS |
|
$ |
208,161 |
|
|
$ |
120,471 |
|
|
$ |
407,163 |
|
|
$ |
735,795 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
During the three months ended September 30, 2009, all of the coal divisions revenue arose from
coal sales in Mongolia to three customers. Total revenues by customer were $7.5 million, $4.1
million and $0.3 million.
26
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
14. |
|
SEGMENT DISCLOSURES (Continued) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nine Months Ended September 30, 2010 |
|
|
|
Exploration |
|
|
Coal |
|
|
Corporate |
|
|
Consolidated |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
REVENUE |
|
$ |
|
|
|
$ |
38,182 |
|
|
$ |
|
|
|
$ |
38,182 |
|
COST OF SALES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Production and delivery |
|
|
|
|
|
|
(28,073 |
) |
|
|
|
|
|
|
(28,073 |
) |
Depreciation and depletion |
|
|
|
|
|
|
(5,854 |
) |
|
|
|
|
|
|
(5,854 |
) |
Write-down of carrying value of inventory |
|
|
|
|
|
|
(14,390 |
) |
|
|
|
|
|
|
(14,390 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
COST OF SALES |
|
|
|
|
|
|
(48,317 |
) |
|
|
|
|
|
|
(48,317 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
EXPENSES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Exploration |
|
|
(123,490 |
) |
|
|
(35,547 |
) |
|
|
|
|
|
|
(159,037 |
) |
General and administrative |
|
|
|
|
|
|
|
|
|
|
(38,052 |
) |
|
|
(38,052 |
) |
Depreciation |
|
|
(1,320 |
) |
|
|
(129 |
) |
|
|
(73 |
) |
|
|
(1,522 |
) |
Accretion of asset retirement obligations |
|
|
(67 |
) |
|
|
(75 |
) |
|
|
|
|
|
|
(142 |
) |
Gain on sale of other mineral property rights |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Write-down of carrying values of property, plant and
equipment |
|
|
|
|
|
|
(1,764 |
) |
|
|
|
|
|
|
(1,764 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL EXPENSES |
|
|
(124,877 |
) |
|
|
(85,832 |
) |
|
|
(38,125 |
) |
|
|
(248,834 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
OPERATING LOSS |
|
|
(124,877 |
) |
|
|
(47,650 |
) |
|
|
(38,125 |
) |
|
|
(210,652 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
OTHER INCOME (EXPENSES) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Interest income |
|
|
3,857 |
|
|
|
1,851 |
|
|
|
5,231 |
|
|
|
10,939 |
|
Interest expense |
|
|
|
|
|
|
(19,624 |
) |
|
|
(8,333 |
) |
|
|
(27,957 |
) |
Accretion of convertible credit facilities |
|
|
|
|
|
|
(46 |
) |
|
|
(11,650 |
) |
|
|
(11,696 |
) |
Foreign exchange gains |
|
|
(490 |
) |
|
|
252 |
|
|
|
2,383 |
|
|
|
2,145 |
|
Listing fees SouthGobi |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Unrealized gains (losses) on long-term investments |
|
|
|
|
|
|
(3,849 |
) |
|
|
|
|
|
|
(3,849 |
) |
Unrealized gains on other long-term investments |
|
|
|
|
|
|
343 |
|
|
|
3,185 |
|
|
|
3,528 |
|
Realized gain on redemption of other long-term investments |
|
|
|
|
|
|
|
|
|
|
121 |
|
|
|
121 |
|
Change in fair value of embedded derivatives |
|
|
|
|
|
|
120,633 |
|
|
|
|
|
|
|
120,633 |
|
Loss on conversion of convertible credit facility |
|
|
|
|
|
|
(154,316 |
) |
|
|
|
|
|
|
(154,316 |
) |
Write-down of carrying value of long-term investments |
|
|
|
|
|
|
|
|
|
|
(485 |
) |
|
|
(485 |
) |
Gain on sale of long-term investment |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
LOSS BEFORE INCOME TAXES AND OTHER ITEMS |
|
|
(121,510 |
) |
|
|
(102,406 |
) |
|
|
(47,673 |
) |
|
|
(271,589 |
) |
Recovery for income taxes |
|
|
(1,305 |
) |
|
|
5,381 |
|
|
|
1,880 |
|
|
|
5,956 |
|
Share of loss of significantly influenced investees |
|
|
(749 |
) |
|
|
|
|
|
|
(30,964 |
) |
|
|
(31,713 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
NET LOSS FROM CONTINUING OPERATIONS |
|
|
(123,564 |
) |
|
|
(97,025 |
) |
|
|
(76,757 |
) |
|
|
(297,346 |
) |
INCOME FROM DISCONTINUED OPERATIONS |
|
|
|
|
|
|
|
|
|
|
6,585 |
|
|
|
6,585 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NET LOSS |
|
|
(123,564 |
) |
|
|
(97,025 |
) |
|
|
(70,172 |
) |
|
|
(290,761 |
) |
NET LOSS ATTRIBUTABLE TO NONCONTROLLING
INTERESTS |
|
|
18,951 |
|
|
|
|
|
|
|
23,053 |
|
|
|
42,004 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NET LOSS ATTRIBUTABLE TO IVANHOE MINES LTD. |
|
$ |
(104,613 |
) |
|
$ |
(97,025 |
) |
|
$ |
(47,119 |
) |
|
$ |
(248,757 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
CAPITAL EXPENDITURES |
|
$ |
355,022 |
|
|
$ |
75,590 |
|
|
$ |
86 |
|
|
$ |
430,698 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL ASSETS |
|
$ |
1,174,620 |
|
|
$ |
942,990 |
|
|
$ |
669,890 |
|
|
$ |
2,787,500 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
During the nine months ended September 30, 2010, all of the coal divisions revenue arose from coal
sales in Mongolia to four customers. Total revenues by customer were $24.1 million, $12.8 million,
$1.2 million and $0.1 million.
27
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
14. |
|
SEGMENT DISCLOSURES (Continued) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nine Months Ended September 30, 2009 |
|
|
|
Exploration |
|
|
Coal |
|
|
Corporate |
|
|
Consolidated |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
REVENUE |
|
$ |
|
|
|
$ |
26,078 |
|
|
$ |
|
|
|
$ |
26,078 |
|
COST OF SALES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Production and delivery |
|
|
|
|
|
|
(16,746 |
) |
|
|
|
|
|
|
(16,746 |
) |
Depreciation and depletion |
|
|
|
|
|
|
(4,243 |
) |
|
|
|
|
|
|
(4,243 |
) |
Write-down of carrying value of inventory |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
COST OF SALES |
|
|
|
|
|
|
(20,989 |
) |
|
|
|
|
|
|
(20,989 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
EXPENSES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Exploration |
|
|
(95,807 |
) |
|
|
(14,062 |
) |
|
|
|
|
|
|
(109,869 |
) |
General and administrative |
|
|
|
|
|
|
|
|
|
|
(30,778 |
) |
|
|
(30,778 |
) |
Depreciation |
|
|
(3,087 |
) |
|
|
(14 |
) |
|
|
(66 |
) |
|
|
(3,167 |
) |
Accretion of asset retirement obligations |
|
|
(66 |
) |
|
|
(38 |
) |
|
|
|
|
|
|
(104 |
) |
Gain on sale of other mineral property rights |
|
|
3,000 |
|
|
|
|
|
|
|
|
|
|
|
3,000 |
|
Write-down of carrying values of property, plant and
equipment |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL EXPENSES |
|
|
(95,960 |
) |
|
|
(35,103 |
) |
|
|
(30,844 |
) |
|
|
(161,907 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
OPERATING LOSS |
|
|
(95,960 |
) |
|
|
(9,025 |
) |
|
|
(30,844 |
) |
|
|
(135,829 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
OTHER INCOME (EXPENSES) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Interest income |
|
|
913 |
|
|
|
16 |
|
|
|
1,013 |
|
|
|
1,942 |
|
Interest expense |
|
|
|
|
|
|
|
|
|
|
(13,083 |
) |
|
|
(13,083 |
) |
Accretion of convertible credit facilities |
|
|
|
|
|
|
|
|
|
|
(10,549 |
) |
|
|
(10,549 |
) |
Foreign exchange gains |
|
|
(1,065 |
) |
|
|
(1,222 |
) |
|
|
34,232 |
|
|
|
31,945 |
|
Listing fees SouthGobi |
|
|
|
|
|
|
(1,932 |
) |
|
|
|
|
|
|
(1,932 |
) |
Unrealized gains (losses) on long-term investments |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Unrealized gains on other long-term investments |
|
|
|
|
|
|
|
|
|
|
15 |
|
|
|
15 |
|
Realized gain on redemption of other long-term investments |
|
|
|
|
|
|
|
|
|
|
1,334 |
|
|
|
1,334 |
|
Change in fair value of embedded derivatives |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Loss on conversion of convertible credit facility |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Write-down of carrying value of long-term investments |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Gain on sale of long-term investment |
|
|
|
|
|
|
|
|
|
|
1,424 |
|
|
|
1,424 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
LOSS BEFORE INCOME TAXES AND OTHER ITEMS |
|
|
(96,112 |
) |
|
|
(12,163 |
) |
|
|
(16,458 |
) |
|
|
(124,733 |
) |
Recovery for income taxes |
|
|
(168 |
) |
|
|
7,796 |
|
|
|
(76 |
) |
|
|
7,552 |
|
Share of loss of significantly influenced investees |
|
|
(1,156 |
) |
|
|
|
|
|
|
(29,683 |
) |
|
|
(30,839 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
NET LOSS FROM CONTINUING OPERATIONS |
|
|
(97,436 |
) |
|
|
(4,367 |
) |
|
|
(46,217 |
) |
|
|
(148,020 |
) |
INCOME FROM DISCONTINUED OPERATIONS |
|
|
|
|
|
|
(32,150 |
) |
|
|
19,309 |
|
|
|
(12,841 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
NET LOSS |
|
|
(97,436 |
) |
|
|
(36,517 |
) |
|
|
(26,908 |
) |
|
|
(160,861 |
) |
NET LOSS ATTRIBUTABLE TO NONCONTROLLING
INTERESTS |
|
|
3,808 |
|
|
|
|
|
|
|
6,350 |
|
|
|
10,158 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NET LOSS ATTRIBUTABLE TO IVANHOE MINES LTD. |
|
$ |
(93,628 |
) |
|
$ |
(36,517 |
) |
|
$ |
(20,558 |
) |
|
$ |
(150,703 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
CAPITAL EXPENDITURES |
|
$ |
2,685 |
|
|
$ |
19,756 |
|
|
$ |
26 |
|
|
$ |
22,467 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL ASSETS |
|
$ |
208,161 |
|
|
$ |
120,471 |
|
|
$ |
407,163 |
|
|
$ |
735,795 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
During the nine months ended September 30, 2009, all of the coal divisions revenue arose from coal
sales in Mongolia to three customers. Total revenues by customer were $16.2 million, $9.6 million
and $0.3 million.
28
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
15. |
|
FAIR VALUE ACCOUNTING |
The ASC establishes a fair value hierarchy that prioritizes the inputs to valuation
techniques used to measure fair value. The hierarchy gives the highest priority to
unadjusted quoted prices in active markets for identical assets or liabilities and the lowest
priority to unobservable inputs. The three levels of the fair value hierarchy are as follows:
|
|
|
|
|
|
|
Level 1:
|
|
Quoted prices in active markets for identical assets or
liabilities that the reporting entity has the ability to access at the measurement
date. |
|
|
|
|
|
|
|
Level 2:
|
|
Quoted prices in markets that are not active, or inputs that are
observable, either directly or indirectly, for substantially the full term of the
asset or liability. |
|
|
|
|
|
|
|
Level 3:
|
|
Prices or valuation techniques that require inputs that are both
significant to the fair value measurement and unobservable. |
The following table sets forth the Companys assets and liabilities measured at fair value on
a recurring basis by level within the fair value hierarchy. Assets and liabilities are
classified in their entirety based on the lowest level of input that is significant to the
fair value measurement.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fair Value at September 30, 2010 |
|
|
|
Total |
|
|
Level 1 |
|
|
Level 2 |
|
|
Level 3 |
|
Assets: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Short-term investments |
|
$ |
7,505 |
|
|
$ |
7,505 |
|
|
$ |
|
|
|
$ |
|
|
Long-term investments |
|
|
108,902 |
|
|
|
87,471 |
|
|
|
21,431 |
|
|
|
|
|
Other long-term investments |
|
|
212,419 |
|
|
|
70,032 |
|
|
|
|
|
|
|
142,387 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
328,826 |
|
|
$ |
165,008 |
|
|
$ |
21,431 |
|
|
$ |
142,387 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Liabilities: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Embedded derivative liability |
|
$ |
134,882 |
|
|
$ |
|
|
|
$ |
134,882 |
|
|
$ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
134,882 |
|
|
$ |
|
|
|
$ |
134,882 |
|
|
$ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fair Value at December 31, 2009 |
|
|
|
Total |
|
|
Level 1 |
|
|
Level 2 |
|
|
Level 3 |
|
Assets: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Short-term investments |
|
$ |
14,999 |
|
|
$ |
14,999 |
|
|
$ |
|
|
|
$ |
|
|
Long-term investments |
|
|
86,443 |
|
|
|
62,410 |
|
|
|
24,033 |
|
|
|
|
|
Other long-term investments |
|
|
145,035 |
|
|
|
47,194 |
|
|
|
|
|
|
|
97,841 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
246,477 |
|
|
$ |
124,603 |
|
|
$ |
24,033 |
|
|
$ |
97,841 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Liabilities: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Embedded derivative liability |
|
$ |
358,272 |
|
|
$ |
|
|
|
$ |
358,272 |
|
|
$ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
358,272 |
|
|
$ |
|
|
|
$ |
358,272 |
|
|
$ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
29
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
15. |
|
FAIR VALUE ACCOUNTING (Continued) |
The Companys short-term and long-term investments are classified within Level 1 and 2 of the
fair value hierarchy as they are valued using quoted market prices of certain investments, as
well as quoted prices for similar investments.
The Companys other long-term investments are classified within Level 1 and 3 of the fair
value hierarchy and consist of the Long-Term Notes, T-Bill, first tax prepayment and Money
Market investments.
The Companys embedded derivative liability, included within convertible credit facilities
(Note 9 (b)), is classified within Level 2 of the fair value hierarchy as it is determined
using a Monte Carlo simulation valuation model, which uses readily observable market inputs.
The table below sets forth a summary of changes in the fair value of the Companys Level 3
financial assets (other long-term investments) for the nine months ended September 30, 2010.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Long-Term |
|
|
|
|
|
|
Tax |
|
|
|
|
|
|
Notes |
|
|
T-Bills |
|
|
Prepayment |
|
|
Totals |
|
Balance, December 31, 2009 |
|
$ |
24,689 |
|
|
$ |
73,152 |
|
|
$ |
|
|
|
$ |
97,841 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Additions |
|
|
|
|
|
|
|
|
|
|
50,000 |
|
|
|
50,000 |
|
Accrued interest |
|
|
|
|
|
|
2,087 |
|
|
|
423 |
|
|
|
2,510 |
|
Foreign exchange gains |
|
|
472 |
|
|
|
|
|
|
|
|
|
|
|
472 |
|
Fair value redeemed |
|
|
(81 |
) |
|
|
|
|
|
|
|
|
|
|
(81 |
) |
Unrealized gain (loss) |
|
|
3,185 |
|
|
|
3,224 |
|
|
|
(14,764 |
) |
|
|
(8,355 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
Balance, September 30, 2010 |
|
$ |
28,265 |
|
|
$ |
78,463 |
|
|
$ |
35,659 |
|
|
$ |
142,387 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
30
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
16. |
|
DISCLOSURES REGARDING FINANCIAL INSTRUMENTS |
|
(a) |
|
The estimated fair value of Ivanhoe Mines financial instruments was as follows: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
September 30, |
|
|
December 31, |
|
|
|
2010 |
|
|
2009 |
|
|
|
Carrying |
|
|
Fair |
|
|
Carrying |
|
|
Fair |
|
|
|
Amount |
|
|
Value |
|
|
Amount |
|
|
Value |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Cash and cash equivalents |
|
$ |
1,440,119 |
|
|
$ |
1,440,119 |
|
|
$ |
965,823 |
|
|
$ |
965,823 |
|
Short-term investments |
|
|
7,505 |
|
|
|
7,505 |
|
|
|
14,999 |
|
|
|
14,999 |
|
Accounts receivable |
|
|
60,159 |
|
|
|
60,159 |
|
|
|
39,349 |
|
|
|
39,349 |
|
Long-term investments |
|
|
88,857 |
|
|
|
199,906 |
|
|
|
93,511 |
|
|
|
154,976 |
|
Other long-term investments |
|
|
212,419 |
|
|
|
212,419 |
|
|
|
145,035 |
|
|
|
145,035 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Accounts payable and
accrued liabilities |
|
|
162,942 |
|
|
|
162,942 |
|
|
|
55,128 |
|
|
|
55,128 |
|
Amounts due under credit facilities |
|
|
55,757 |
|
|
|
55,757 |
|
|
|
55,523 |
|
|
|
55,523 |
|
Convertible credit facilities |
|
|
237,612 |
|
|
|
237,612 |
|
|
|
928,618 |
|
|
|
940,380 |
|
The fair value of Ivanhoe Mines long-term investments was determined by reference to
published market quotations, which may not be reflective of future values.
The fair value of Ivanhoe Mines other long-term investments, consisting of the
Long-Term Notes, T-Bill, first tax prepayment and Money Market investments, was
determined by considering the best available data regarding market conditions for such
investments, which may not be reflective of future values.
The fair value of the Rio Tinto convertible credit facility was estimated to
approximate the balance of principal and interest outstanding, due primarily to the
short-term maturity of this facility.
The fair value of the CIC convertible debenture was estimated to approximate the
aggregate carrying amount of the CIC convertible credit facility liability and
interest payable. This aggregate carrying amount includes the estimated fair value of
the embedded derivative liability which was determined using a Monte Carlo simulation
valuation model.
The fair values of Ivanhoe Mines remaining financial instruments were estimated to
approximate their carrying values, due primarily to the immediate or short-term
maturity of these financial instruments.
|
(b) |
|
Ivanhoe Mines is exposed to credit risk with respect to its accounts receivable.
The significant concentrations of credit risk are situated in Mongolia and Australia.
Ivanhoe
Mines does not mitigate the balance of this risk in light of the credit worthiness of
its major debtors. |
31
IVANHOE MINES LTD.
Notes to the Consolidated Financial Statements
(Stated in U.S. dollars unless otherwise noted; tabular amounts in thousands)
16. |
|
DISCLOSURES REGARDING FINANCIAL INSTRUMENTS (Continued) |
|
(c) |
|
Ivanhoe Mines is exposed to interest rate risk with respect to the variable rates
of interest incurred on the amounts due under credit facilities (Note 8). Interest rate
risk is concentrated in Canada. Ivanhoe Mines does not mitigate the balance of this
risk. |
Due to the size, complexity and nature of the Companys operations, various legal and tax
matters arise in the ordinary course of business. The Company accrues for such items when a
liability is both probable and the amount can be reasonably estimated. In the opinion of
management, these matters will not have a material effect on the consolidated financial
statements of the Company.
32
|
|
|
|
|
|
|
3
|
|
Interim Report
for the
three and
nine month
periods
ended
September 30,
2010.
|
|
Share Information
Common shares of Ivanhoe
Mines Ltd. are listed for
trading under the symbol IVN
on the New York Stock
Exchange, NASDAQ and the
Toronto Stock Exchange.
|
|
Investor Information
All financial reports, news
releases and corporate
information can be accessed on
our web site at
www.ivanhoe-mines.com |
|
|
|
|
|
|
|
At November 10,
2010, the Company
had 531.2 million
common shares
issued and
outstanding and
warrants and stock
options outstanding
for 100.5 million
additional common
shares. |
|
Transfer Agents and Registrars
CIBC Mellon Trust Company
320 Bay Street
Toronto, Ontario, Canada
M5H 4A6
Toll free in North America:
1-800-387-0825 |
|
Contact Information
Investors: Bill Trenaman
Media: Bob Williamson
Suite 654-999 Canada Place
Vancouver, B.C., Canada V6C 3E1
Email: info@ivanhoemines.com
Tel: (604) 688-5755 |
INTRODUCTION
This discussion and analysis of the financial condition and results of operations (MD&A) of Ivanhoe
Mines Ltd. should be read in conjunction with the unaudited consolidated financial statements of
Ivanhoe Mines Ltd. and the notes thereto for the three- and nine-month periods ended September 30,
2010, and with the audited consolidated financial statements of Ivanhoe Mines Ltd. and the notes
thereto for the year ended December 31, 2009. These financial statements have been prepared in
accordance with United States of America generally accepted accounting principles (U.S. GAAP). In
this MD&A, unless the context otherwise dictates, a reference to the Company refers to Ivanhoe
Mines Ltd. and a reference to Ivanhoe Mines refers to Ivanhoe Mines Ltd., together with its
subsidiaries. Additional information about the Company, including its Annual Information Form, is
available at www.sedar.com.
References to C$ refer to Canadian dollars, A$ to Australian dollars, and $ to United States
dollars.
This discussion and analysis contains forward-looking statements. Please refer to the cautionary
language on page 37.
The effective date of this MD&A is November 10, 2010.
OVERVIEW
IVANHOE MINES ANNOUNCES FINANCIAL RESULTS
AND REVIEW OF OPERATIONS FOR THE THIRD QUARTER OF 2010
HIGHLIGHTS
|
|
|
Full-scale construction at the Oyu Tolgoi copper and gold mine in Mongolia is progressing
ahead of schedule and there now are more than 5,500 workers on site. Ivanhoe Mines expects to
begin initial production of copper and gold at the Oyu Tolgoi Project in late 2012. |
|
|
|
|
On October 18, 2010, Ivanhoe Mines launched a strategic, conditional rights offering in
which all existing shareholders, subject to applicable law, may participate on a pro rata
basis in purchasing additional common shares. The rights offering is expected to raise
approximately $800 million to $1.0 billion. |
|
|
|
|
Also on October 18, 2010, Ivanhoe Mines announced that Executive Chairman Robert Friedland
re-assumed the duties and title of Chief Executive Officer as part of a series of
organizational changes that included the establishment of the Office of the Chairman as part
of an ongoing commitment to maximize shareholder value. |
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
|
|
|
Discussions are progressing with a group of international financial institutions on a
separate debt-financing package that is expected to close in the first half of 2011. The
proposed multi-billion-dollar package is being considered by a core lending group comprised
of the European Bank for Reconstruction and Development, the International Finance
Corporation, Export Development Canada, BNP Paribas and Standard Chartered. |
|
|
|
|
In September 2010, Ivanhoe Mines converted Rio Tintos maturing $350.0 million convertible
credit facility, plus accrued interest of $50.8 million, into approximately 40.1 million
common shares of Ivanhoe Mines, increasing Rio Tintos ownership in Ivanhoe Mines from 29.6%
to 34.9%. |
|
|
|
|
In September 2010, a new hole drilled at Oyu Tolgoi intercepted 938 metres of
near-continuous copper-gold mineralization between the Heruga Deposit and the Southern Oyu
deposits, making it the longest exploration drill intercept of copper and gold mineralization
recorded since Ivanhoe Mines began drilling at the Oyu Tolgoi Project in 2000. |
|
|
|
|
On September 30, 2010, Ivanhoe Mines 62%-owned subsidiary, Ivanhoe Australia (IVA-ASX),
completed the acquisition of the Osborne Copper and Gold Mining Complex, which includes a
two-million-tonne-per-annum concentrator located 53 kilometres south of Ivanhoe Australias
high-grade Merlin molybdenum and rhenium project in northwestern Queensland. |
|
|
|
|
On September 10, 2010, Ivanhoe Australia successfully completed a A$269 million equity
raising through the institutional component of its accelerated, non-renounceable, pro rata
entitlement offer and an institutional placement. |
|
|
|
|
Ivanhoe Australia shares are scheduled to begin trading on the Toronto Stock Exchange on
November 12, 2010, under the symbol IVA. |
|
|
|
|
During Q310, Ivanhoe Mines 57%-owned subsidiary, SouthGobi Resources (SGQ TSX; 1878 -
HK), reported coal sales of $6.6 million from its Ovoot Tolgoi mine in southern Mongolia,
representing approximately 194,000 tonnes of coal sold to customers. |
|
|
|
|
In July 2010, Ivanhoe Mines 50%-owned Altynalmas Gold began a definitive feasibility
study for the Kyzyl Gold Project in northeastern Kazakhstan. Altynalmas Gold has engaged
Fluor Canada Ltd., Crescent Technology Inc., Technip USA Inc., Environmental Resources
Management, Scott Wilson Roscoe Postle Associates Inc. and Sustainability East Asia LLC to
conduct the study. |
2
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
INDEX
The MD&A is comprised of the following sections:
|
|
|
|
|
1. Selected Quarterly Data |
|
|
|
|
2. Review of Operations |
|
|
|
|
A. Core Interests and Activities |
|
|
|
|
i. Mongolia |
|
|
|
|
ii. Australia |
|
|
|
|
iii. Kazakhstan |
|
|
|
|
iv. Other exploration |
|
|
|
|
v. Other developments |
|
|
|
|
B. Discontinued Operations |
|
|
|
|
C. Administrative and Other |
|
|
|
|
3. Liquidity and Capital Resources |
|
|
|
|
4. Share Capital |
|
|
|
|
5. Outlook |
|
|
|
|
6. Off-Balance-Sheet Arrangements |
|
|
|
|
7. Contractual Obligations |
|
|
|
|
8. Changes in Accounting Policies |
|
|
|
|
9. Critical Accounting Estimates |
|
|
|
|
10. Recent Accounting Pronouncements |
|
|
|
|
11. International Financial Reporting Standards |
|
|
|
|
12. Risks and Uncertainties |
|
|
|
|
13. Related-Party Transactions |
|
|
|
|
14. Changes in Internal Control over Financial Reporting |
|
|
|
|
15. Qualified Persons |
|
|
|
|
16. Cautionary Statements |
|
|
|
|
17. Forward-Looking Statements |
|
|
|
|
3
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
SELECTED QUARTERLY DATA
($ in millions of dollars, except per share information)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Quarter Ended |
|
|
|
Sep-30 |
|
|
Jun-30 |
|
|
Mar-31 |
|
|
Dec-31 |
|
|
|
2010 |
|
|
2010 |
|
|
2010 |
|
|
2009 |
|
Revenue |
|
$ |
6.6 |
|
|
$ |
17.7 |
|
|
$ |
13.9 |
|
|
$ |
9.9 |
|
Cost of sales |
|
|
(14.9 |
) |
|
|
(13.2 |
) |
|
|
(20.3 |
) |
|
|
(8.5 |
) |
Exploration expenses |
|
|
(48.1 |
) |
|
|
(39.5 |
) |
|
|
(71.4 |
) |
|
|
(67.2 |
) |
General and administrative |
|
|
(15.0 |
) |
|
|
(14.7 |
) |
|
|
(8.3 |
) |
|
|
(15.0 |
) |
Foreign exchange gains (losses) |
|
|
5.3 |
|
|
|
(4.9 |
) |
|
|
1.7 |
|
|
|
2.2 |
|
Change in fair value of embedded derivatives |
|
|
49.8 |
|
|
|
72.2 |
|
|
|
(1.4 |
) |
|
|
(45.0 |
) |
Loss on conversion of convertible credit facility |
|
|
|
|
|
|
|
|
|
|
(154.3 |
) |
|
|
|
|
Net loss from continuing operations |
|
|
(24.9 |
) |
|
|
(30.0 |
) |
|
|
(200.5 |
) |
|
|
(138.7 |
) |
Income (loss) from discontinued operations |
|
|
|
|
|
|
|
|
|
|
6.6 |
|
|
|
9.2 |
|
Net loss |
|
|
(24.9 |
) |
|
|
(30.0 |
) |
|
|
(193.9 |
) |
|
|
(129.5 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Net (loss) income per share basic and diluted |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Continuing operations |
|
$ |
(0.05 |
) |
|
$ |
(0.07 |
) |
|
$ |
(0.47 |
) |
|
$ |
(0.35 |
) |
Discontinued operations |
|
$ |
0.00 |
|
|
$ |
0.00 |
|
|
$ |
0.02 |
|
|
$ |
0.03 |
|
Total |
|
$ |
(0.05 |
) |
|
$ |
(0.07 |
) |
|
$ |
(0.45 |
) |
|
$ |
(0.32 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Quarter Ended |
|
|
|
Sep-30 |
|
|
Jun-30 |
|
|
Mar-31 |
|
|
Dec-31 |
|
|
|
2009 |
|
|
2009 |
|
|
2009 |
|
|
2008 |
|
Revenue |
|
$ |
11.9 |
|
|
$ |
10.7 |
|
|
$ |
3.5 |
|
|
$ |
3.1 |
|
Cost of sales |
|
|
(8.6 |
) |
|
|
(9.1 |
) |
|
|
(3.2 |
) |
|
|
(2.2 |
) |
Exploration expenses |
|
|
(40.9 |
) |
|
|
(35.2 |
) |
|
|
(34.1 |
) |
|
|
(73.0 |
) |
General and administrative |
|
|
(12.5 |
) |
|
|
(10.5 |
) |
|
|
(7.8 |
) |
|
|
(8.1 |
) |
Foreign exchange gains (losses) |
|
|
19.5 |
|
|
|
21.7 |
|
|
|
(9.3 |
) |
|
|
(40.6 |
) |
Writedown of other long-term investments |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(18.0 |
) |
Loss on conversion of convertible credit facility |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Net loss from continuing operations |
|
|
(47.8 |
) |
|
|
(27.0 |
) |
|
|
(63.4 |
) |
|
|
(165.0 |
) |
Income from discontinued operations |
|
|
(21.9 |
) |
|
|
2.1 |
|
|
|
7.4 |
|
|
|
5.0 |
|
Net loss |
|
|
(69.8 |
) |
|
|
(24.9 |
) |
|
|
(56.0 |
) |
|
|
(160.0 |
) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Net (loss) income per share basic and diluted |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Continuing operations |
|
$ |
(0.13 |
) |
|
$ |
(0.07 |
) |
|
$ |
(0.17 |
) |
|
$ |
(0.44 |
) |
Discontinued operations |
|
$ |
(0.05 |
) |
|
$ |
0.00 |
|
|
$ |
0.02 |
|
|
$ |
0.01 |
|
Total |
|
$ |
(0.18 |
) |
|
$ |
(0.07 |
) |
|
$ |
(0.15 |
) |
|
$ |
(0.43 |
) |
4
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
REVIEW OF OPERATIONS
Ivanhoe Mines is an international exploration and development company with activities concentrated
in Central Asia and the Asia Pacific Region. The Companys principal assets include:
|
|
|
A 100% interest in Ivanhoe Oyu Tolgoi (BVI) Ltd. that, together with a related company,
holds a 66% interest in Oyu Tolgoi LLC, whose principal asset is the Oyu Tolgoi copper and
gold project now under construction in southern Mongolia. |
|
|
|
|
A 57% interest in SouthGobi Resources, which is selling coal produced at its Ovoot Tolgoi
mine in southern Mongolia to customers in China and is conducting ongoing exploration and
development programs at several other Mongolian coal prospects. |
|
|
|
|
A 62% interest in Ivanhoe Australia, which is developing its copper-gold discoveries in
the Cloncurry region of Queensland, Australia, and also is planning the development of its
wholly-owned Merlin Project, a high-grade molybdenum and rhenium deposit. |
|
|
|
|
A 50% interest in Altynalmas Gold, which owns the Kyzyl Gold Project that hosts the
Bakyrchik and Bolshevik gold deposits in Kazakhstan. |
In Q310, Ivanhoe Mines recorded a net loss of $24.9 million ($0.05 per share) compared to a net
loss of $69.8 million ($0.18 per share) in Q309, representing a decrease of $44.9 million. Results
for Q310 mainly were affected by $48.1 million in exploration expenses, $14.9 million in cost of
sales, $15.0 million in general and administrative expenses, $6.3 million in interest expense and
$8.5 million in share of loss of significantly influenced investees. These amounts were offset by
coal revenue of $6.6 million, $3.8 million in interest income, $5.3 million in mainly unrealized
foreign exchange gains and a $49.8 million change in fair value of embedded derivatives.
Exploration expenses of $48.1 million in Q310 increased $7.2 million from $40.9 million in Q309.
Exploration expenses included $30.4 million spent in Mongolia ($28.1 million in Q309), primarily
for Oyu Tolgoi and Ovoot Tolgoi, and $15.7 million incurred by Ivanhoe Australia ($11.5 million in
Q309). Exploration costs are charged to operations in the period incurred and often represent the
bulk of Ivanhoe Mines operating loss for that period.
Ivanhoe Mines cash position, on a consolidated basis at September 30, 2010, was $1.4 billion. As
at November 10, 2010, Ivanhoe Mines current consolidated cash position is approximately $1.3
billion.
5
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
A. CORE INTERESTS AND ACTIVITIES
In Q310, Ivanhoe Mines expensed $48.1 million in exploration activities, compared to $40.9 million
in Q309. In Q310, most of Ivanhoe Mines exploration activities were focused in Mongolia and
Australia.
Exploration costs generally are charged to operations in the period incurred until it has been
determined that a property has economically recoverable reserves, at which time subsequent
exploration costs and the costs incurred to develop a property are capitalized.
Summary of exploration expenditures by location:
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended |
|
|
|
September 30, |
|
(Stated in $000s of dollars) |
|
2010 |
|
|
2009 |
|
Mongolia |
|
|
|
|
|
|
|
|
Oyu Tolgoi (1) |
|
$ |
14,298 |
|
|
$ |
22,154 |
|
Coal Division |
|
|
14,676 |
|
|
|
5,598 |
|
Other Mongolia Exploration |
|
|
1,393 |
|
|
|
385 |
|
|
|
|
|
|
|
|
|
|
|
30,367 |
|
|
|
28,137 |
|
Australia |
|
|
15,743 |
|
|
|
11,464 |
|
Indonesia |
|
|
903 |
|
|
|
1,103 |
|
Other |
|
|
1,118 |
|
|
|
245 |
|
|
|
|
|
|
|
|
|
|
$ |
48,131 |
|
|
$ |
40,949 |
|
|
|
|
|
|
|
|
|
|
|
(1) |
|
Until March 31, 2010, exploration costs charged to operations
included development costs associated with the Oyu Tolgoi Project. On April 1, 2010,
Ivanhoe Mines commenced capitalizing Oyu Tolgoi Project development costs. As of this
date, reserve estimates for the Oyu Tolgoi Project had been announced and the
procedural and administrative conditions contained in the Investment Agreement among
Ivanhoe Mines, Rio Tinto and the Government of Mongolia were satisfied. During Q310,
additions to property, plant and equipment included $204.4 million of Oyu Tolgoi
Project development costs. |
MONGOLIA
OYU TOLGOI COPPER-GOLD PROJECT (66% owned)
The Oyu Tolgoi Project is approximately 550 kilometres south of Ulaanbaatar, Mongolias capital
city, and 80 kilometres north of the Mongolia-China border. Mineralization on the property consists
of porphyry-style copper, gold, silver and molybdenum contained in a linear structural trend (the
Oyu Tolgoi Trend) with a strike length that extends over 20 kilometres. Mineral resources have been
identified in a series of deposits throughout this trend. They include, from south to north, the
Heruga Deposit, the Southern Oyu deposits (Southwest Oyu, South Oyu, Wedge and Central Oyu), and
the Hugo Dummett deposits (Hugo South, Hugo North and Hugo North Extension).
6
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
Ivanhoe Mines began capitalizing Oyu Tolgoi development costs on April 1, 2010. In Q310, Ivanhoe
Mines incurred exploration expenses of $14.3 million at Oyu Tolgoi compared to $22.2 million
incurred in Q309. During Q310, additions to property, plant and equipment included $204.4 million
of Oyu Tolgoi Project development costs.
Oyu Tolgoi copper-gold complex construction progressing ahead of schedule for initial production in
late 2012
Full-scale mine construction is underway at the Oyu Tolgoi Project. Production of the first
concentrate is expected in late 2012, with a build up to the start of commercial production in
2013. The Project initially is being developed as an open-pit operation, with mining starting at
the near-surface Southern Oyu deposits. A copper concentrator plant, related facilities and
necessary infrastructure supporting an initial throughput of 100,000 tonnes of ore per day are
being constructed to process the ore mined in the open pit. Mining of ore from the Southern Oyu
open pit is scheduled to begin in Q312, to provide feed for the commissioning of the concentrator.
An 85,000-tonne-per-day underground block-cave mining operation also is being developed at the Hugo
North Deposit, with initial production expected to begin in 2015. The throughput capacity of the
concentrator plant is expected to be expanded when the underground mine begins production.
Fluor Corporation is in charge of overall Oyu Tolgoi program management, as well as services
related to engineering, procurement and construction management for the ore processing plant and
mine-related infrastructure such as roads, water supply, a regional airport and administration
buildings. Fluor is executing the engineering for the Project from its Vancouver, Canada, and
Beijing, China, offices with operations being managed onsite in Mongolia.
Current activities related to the 100,000-tonne-per-day phase one copper-gold concentrator are
focused on finalizing the operational readiness plan. Detailed commissioning, operation and
maintenance plans are being developed for all the components of the concentrator circuits.
Representatives of various manufacturers and engineering groups are assisting with the preparation
of the operational readiness plan.
Approximately 41,000 cubic metres of concrete had been poured by the end of Q310 for the
foundations for the concentrator building, the foundations for the two 38-foot-diameter,
semi-autogenous grinding (SAG) mills and four ball mills, the pebble-crusher building and the
ore-reclaim tunnels. Work also continued with the excavations for the tailings-thickening ponds and
the preparation of the storage yard for the mechanical equipment. Erection of the structural steel
for the concentrator building has begun and the major contract for the mechanical, electrical and
piping work for the concentrator has been awarded. Surface excavation work for the primary crusher
also has commenced.
Detailed engineering for the ore concentrator was 83% complete at the end of Q310. Key
construction activities planned for Q410 include completing the pouring of concrete for the
pebble-crusher building and continuation of the erection of structural steel for the concentrator
building.
7
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
During Q310, Oyu Tolgoi LLC concluded the competitive bidding process for the main infrastructure
works, which include on-site infrastructure required to support the mine operations and the
70-kilometre water pipeline to supply the concentrator. Construction of the pipeline is expected to
start in early 2011.
Bidders packages are being prepared for construction of a 97-kilometre paved road from Oyu Tolgoi
to the Mongolia-China border at Gashuun Sukhait. This road will be the primary route for the export
of copper concentrate to China from Oyu Tolgoi. A dual-circuit, 220-kilovolt electrical
transmission line from a Chinese substation to Oyu Tolgoi is being designed, with a target
construction completion date of late 2012. The power line is expected to provide the electricity
for the initial mine operating period. Contracts for the road and power line are expected to be
awarded early in 2011.
Pre-stripping of open-pit mine expected to begin in mid-2011
The open-pit operation is on schedule to begin pre-stripping of the Southern Oyu deposits in
mid-2011, with first ore deliveries to the concentrator expected during Q312. Work is continuing
on the selection and optimization of the open-pit mining fleet; the tender is expected to be
awarded during Q410.
Underground development of Hugo North Mine proceeding ahead of schedule
The development of the first lift of the underground block-cave mine at the Hugo North Deposit
continued successfully during Q310. Lateral mine development on the 1,300-metre level at the Hugo
North underground deposit is ahead of schedule, with a year-to-date advance of 2,503 metres, well
ahead of the planned advance of 2,325 metres. More than 5,000 metres of underground development off
Shaft #1 has been completed to date.
Raise-bore drilling for the first of two ventilation shafts near Shaft #1 continued, with a
successful breakthrough of the pilot hole for the first lift of the raise (from the 512-metre level
to surface) and commencement of the pilot hole for the second lift of the raise (from the
1,300-metre level to the 512-metre level). Completion of the ventilation borehole will increase
ventilation capacity at the 1,300-metre level and allow for the introduction of two additional
underground development crews and equipment, expected in Q311.
The design and engineering of the Shaft #2 headframe has been finalized. Construction of a
97-metre-tall (approximately 31-storey), reinforced-concrete headframe for Shaft #2 is progressing
to plan. The structure for the Shaft #2 conveyor tunnel is nearing completion and the ventilation
plenum structure has been completed.
The sinking platform for Shaft #2 arrived at site and sinking of the 10-metre-diameter shaft is
expected to begin in Q311. Shaft #2, with a planned final depth of 1,335 metres below surface,
will be the main service shaft for the underground Hugo North block-cave mine. Shaft #2 also will
be used as the initial production shaft to hoist the Hugo North ore to the surface.
The underground development from Shaft #1 is expected to connect with the bottom of Shaft #2 in
early 2013 and production from the first lift of the Hugo North block-cave mine is scheduled to
commence in 2015.
8
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
Oyu Tolgoi skills training and community utilities programs well advanced
The Oyu Tolgoi Project staffing strategy relies heavily on the utilization of Mongolian nationals
being developed and trained during ongoing construction activities. More than 3,000 Mongolians are
employed by the Project. These construction employees will form the bulk of the eventual production
workforce, particularly within the open-pit operations. For those areas requiring specialized
skills, such as activities in the concentrator, a specific training plan is scheduled to begin
early in 2012.
A total of 60 operators and 25 electrical trades trainees began their training programs in
September 2010. The programs, developed at the Erdenet Technical College and the Darkhan Technical
College, primarily will provide skilled personnel for concentrator operations and maintenance. In
addition, 43 graduates from the mobile machinery mechanics course are expected to be available for
continued training at the Oyu Tolgoi site in July 2011.
Fourteen students from the local Khanbogd community have been selected for scholarships in tertiary
studies under Oyu Tolgois Sustainable Development and Communities program.
The Mongolian Urban Design Institute is implementing its contract for providing planning support to
the town of Khanbogd, the nearest community to Oyu Tolgoi. A pre-feasibility study is underway of
the short- and medium-term electricity requirements in the local communities of Khanbogd,
Bayan-Ovoo and Manlai. The detailed design of the bulk-water supply to Khanbogd remains on track
for construction beginning in late 2010 or early 2011.
Exploration
New drill hole at Oyu Tolgoi intercepted 938 metres of near-continuous
copper-gold mineralization between the Heruga Deposit and the Southern Oyu deposits
On September 28, 2010, Ivanhoe Mines announced that drill hole OTD1510 at Oyu Tolgoi intercepted
almost one kilometre of near-continuous copper and gold mineralization, making it the longest
exploration drill intercept of copper and gold mineralization recorded since Ivanhoe Mines began
drilling at the Oyu Tolgoi Project in 2000. Hole OTD1510 intercepted 112 metres grading 1.36 grams
of gold per tonne (g/t) and 0.34% copper, with a copper equivalent grade of 1.21% (CuEq), at a
down-hole depth of between 2,286 and 2,398 metres. The intercept included 20 metres grading 3.78
g/t gold and 0.64% copper, with a CuEq grade of 3.06%, at a down-hole depth of between 2,376 and
2,396 metres, and six metres of 8.4 g/t gold and 0.66% copper, with a CuEq grade of 6.05%, at a
down-hole depth of between 2,388 and 2,394 metres.
Individual two-metre samples near the bottom of hole OTD1510 returned gold assays of approximately
10 grams per tonne among the highest gold grades ever drilled at Oyu Tolgoi. Over the entire
938-metre intercept, OTD1510 averaged 0.42 g/t gold and 0.46% copper, with a CuEq grade of 0.76%,
at a down-hole depth of between 1,460 and 2,398 metres (true depth below surface of between
approximately 1,200 and 1,885 metres).
9
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
The area previously known as the New Discovery Zone has been renamed the Heruga North Zone. The
OTD1510 intercept indicates that Heruga North is part of a 2.5-kilometre, gold-rich mineralized
extension of the Heruga Deposit, stretching north from the southern border of the Oyu Tolgoi mining
licence to the Southern Oyu deposits.
Based on interpreted geology and a large, coincident, gradient-array induced polarization (IP)
chargeability anomaly identified by proprietary, deep-exploration technology, Hole OTD1510 was
targeted on a critical, 600-metre gap in the known mineralization between the northern,
fault-controlled limit of the Heruga Deposit and the former New Discovery Zone.
The 938-metre Heruga North intercept in Hole OTD1510 covers a horizontal distance of 643 metres and
a vertical distance of 681 metres. The hole was stopped after it entered the West Bat Fault, which
appears to form the western boundary of the high-grade mineralization. Ivanhoe Mines is drilling a
daughter hole OTD1510B to better delineate the extent of the gold-rich mineralization
encountered in OTD1510.
Ivanhoe Mines deep diamond drilling between the Heruga Deposit and the Southwest Oyu deposits
first identified what is now the Heruga North Zone in December 2008. Since the initial discovery,
Ivanhoe has completed approximately 43,500 metres of wide-spaced diamond drilling into the Heruga
North Zone. Geological modeling indicates that Heruga North is the northern continuation of the
Heruga Deposit, with a horizontal displacement of more than 500 metres along a fault between the
two zones. The top of Heruga North is approximately 1,100 metres below surface and slopes gradually
downward as it extends to the north. The Solongo Fault forms the current northern limit of
mineralization. Although the overall limits of the system have yet to be defined, an approximate
2.5-kilometre, northeast-trending corridor from the Heruga Deposit in the south to the Solongo
Fault in the north is potentially mineralized over a height of at least 700 metres and width of up
to 700 metres.
During Q310, Ivanhoe Mines completed 6,446 metres of drilling on the Oyu Tolgoi Project, comprised
of 3,899 metres at Heruga North and 2,547 metres in other parts of Oyu Tolgoi and the surrounding
area.
Less than half of the 20-kilometre-long mineralized trend at Oyu Tolgoi has been extensively
drill-tested to date. An ongoing exploration program using a proprietary, induced-polarization
technology has identified numerous additional exploration and development targets. Drilling
continues to be directed at expanding the Projects resources and reserves.
Joint Mine Development Plan being prepared to chart early start to Oyu Tolgoi production in 2012
The independent 2010 Oyu Tolgoi Integrated Development Plan, commissioned by Ivanhoe Mines, was
released in May 2010. The plan was prepared by a team of the worlds foremost engineering, mining
and environmental consultants, led by AMEC Minproc, of Australia, and including Stantec
Engineering, of the US.
10
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
As noted in Ivanhoe Mines May 14, 2010, news release, the Integrated Development Plan recommended
that Oyu Tolgoi LLC, the Mongolian company that owns the Oyu Tolgoi Project and is
developing and will operate the mining complex, conduct a comprehensive review to establish a
baseline for the Oyu Tolgoi Project with a goal of improving or optimizing value. The Integrated
Development Plan also recommended that its scenarios be reviewed and analyzed by the Oyu Tolgoi
Technical Committee to help determine detailed plans for the ongoing implementation of the Oyu
Tolgoi Project.
The fundamental elements of the 2010 Integrated Development Plan were completed before October 2009
when Rio Tinto, under terms of its private-placement agreement with Ivanhoe Mines, assumed voting
control of the Technical Committee through which Ivanhoe Mines and Rio Tinto jointly are overseeing
and supervising the development, operation and management of the Oyu Tolgoi Project. Three of the
Technical Committees five members, including the Chair, currently are appointed by Rio Tinto and
two members are appointed by Ivanhoe Mines.
The Technical Committee, independent of the Integrated Development Plan, has initiated its own
review and analysis of all relevant measures required to develop and operate Oyu Tolgois phase-one
open pit and phase-two underground mining and processing activities. The preparation of a Joint
Mine Development Plan for Oyu Tolgoi will continue into 2011. The Technical Committee is examining
projected operating costs, construction and development costs, production rates, scheduling,
financing and economic returns. It also is expected to involve extensive stakeholder analysis and
consultation on several levels, including among Ivanhoe Mines and Rio Tinto technical personnel and
the Oyu Tolgoi LLC Board of Directors.
There are indications from work by Fluor Corporation, the Oyu Tolgoi program management contractor,
and the Technical Committee that the Projects pre-production capital costs will be materially
higher than were estimated in the scenarios studied in the 2010 Integrated Development Plan.
Contributing factors include a more aggressive construction schedule that is expected to ensure an
earlier start to production, in 2012, with commensurate earlier generation of sales revenues,
fluctuations in foreign-currency exchange rates and escalation of costs for equipment, materials,
labour and preparation of the workforce for operations.
Development programs and budgets for the Oyu Tolgoi Project are within the jurisdiction of the
joint Technical Committee. Representatives of Ivanhoe Mines and Rio Tinto on the Technical
Committee have expressed differing opinions on several issues that could affect key aspects of
project development, including the determination and timing of capital and operating costs and
project scheduling. The extent to which these differences of opinion will be resolved or will
become matters of disagreement depends upon the results of ongoing and future evaluations and
consultations. Any disagreements between Ivanhoe Mines and Rio Tinto over development programs and
budgets for the Oyu Tolgoi Project could be decided by Rio Tintos voting majority on the Technical
Committee. If Rio Tinto, through the exercise of its voting majority, compels adoption of a Joint
Mine Development Plan that is significantly different from previously outlined scenarios, the
projected operating costs, construction and development costs, production and economic returns may
differ materially from those projected under the 2010 Integrated Development Plan.
11
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
Although the Technical Committee oversees and supervises the development, operation and management
of the Oyu Tolgoi Project, as outlined above, the Board of Directors of Oyu Tolgoi LLC also must
approve certain development, operational and management matters relating to the Project. It is
possible that the Oyu Tolgoi LLC Board may not agree with the views of the Technical Committee.
Ivanhoe Mines owns an indirect, 66% equity interest in Oyu Tolgoi LLC. Erdenes LLC, a Mongolian
company wholly owned by the Government of Mongolia, holds the remaining 34%. Six of the nine Oyu
Tolgoi LLC directors were appointed by Ivanhoe Mines and three were appointed by the Mongolian
Government. A Shareholders Agreement governs matters involving the business of Oyu Tolgoi LLC,
including the manner in which the Oyu Tolgoi LLC shareholders will fund their financial
contributions to the development of the Oyu Tolgoi Project.
Timely consensus on key issues among all stakeholders is essential to maintain the Oyu Tolgoi
Projects current development and start-up schedule. Any delays to the schedule potentially could
result in materially higher costs to Ivanhoe Mines.
Oyu Tolgoi debt-financing package expected to close in the first half of 2011
Discussions are progressing with a group of international financial institutions on a
debt-financing package that is targeted for completion in the first half of 2011. The proposed
multi-billion-dollar package is being considered by a core lending group comprised of the European
Bank for Reconstruction and Development, the International Finance Corporation, Export Development
Canada, BNP Paribas and Standard Chartered.
In May 2010, Ivanhoe Mines signed a joint mandate letter with the European Bank for Reconstruction
and Development (EBRD) and the World Bank Groups International Finance Corporation (IFC) for
evaluation of a major syndicated financing package for the construction of the planned Oyu Tolgoi
mining complex.
Under terms of the joint mandate letter, EBRD and IFC are considering providing a two-part package
consisting of:
|
|
|
up to $300 million each from EBRD and IFC, as part of a group of primary lenders, in
limited-recourse project financing under an A loan structure; and |
|
|
|
|
mobilization of a further $1.2 billion from commercial lenders under a B loan structure. |
IFC and EBRD financings are subject to detailed due diligence, including a review of the extensive
environmental and social studies conducted by the Oyu Tolgoi Project, and approval by their
respective managements and Boards of Directors.
Export Development Canada (EDC), the Canadian governments export credit agency, is considering
providing up to $500 million in direct project financing capacity, subject to necessary approvals,
including ensuring that the Oyu Tolgoi Project meets EDCs environmental and social impact review
requirements.
Ivanhoe Mines selected Paris-based BNP Paribas and London-based Standard Chartered to work with
EBRD, IFC and EDC in arranging the financing. The commercial banks will be coordinating the
involvement of other Export Credit agencies and other commercial banks that will be part of the
lenders syndicate being assembled.
12
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
Negotiations are proceeding on finalizing a detailed term sheet with the core lenders group
involving an upfront multi-billion-dollar commitment with a first tranche released on closing,
which is targeted for completion in the first half of 2011, and a second tranche released when the
underground mining plan is better defined (expected to be in 2012) with flexibility to adjust final
loan amounts at that time. The financing is structured as a true limited recourse project financing
with no recourse to Ivanhoe Mines following project completion and with long maturities and grace
periods appropriate for a large scale project such as Oyu Tolgoi.
All financing arrangements and detailed terms will be subject to agreement of the Ivanhoe Mines
Board of Directors and other related approval processes.
Ivanhoe Mines initiates strategic rights offering open to all shareholders
on a pro rata basis
On October 18, 2010, Ivanhoe Mines announced that it was launching a strategic, conditional rights
offering in which all existing shareholders, subject to applicable law, may participate on a pro
rata basis in purchasing additional common shares. The rights offering is expected to raise
approximately $800 million to $1.0 billion. Ivanhoe Mines intends to use 90% of the net proceeds
from the rights offering to continue to advance construction, development and exploration of Oyu
Tolgoi and the remaining 10% of the net proceeds for general and administrative expenses.
The announcement stated that the Ivanhoe Mines Board of Directors had unanimously agreed to proceed
with a rights offering as the best of several available alternative measures to help to secure the
independence and flexibility of Ivanhoe Mines to maintain the accelerated construction schedule at
Oyu Tolgoi and to establish a bridge to the previously announced debt financing package, outlined
immediately above.
A preliminary prospectus for the rights offering was filed with securities regulators in Canada and
the United States on October 18, 2010. Full details of the offering, including pricing, will be
disclosed in the final prospectus that currently is being prepared for filing.
Mr. Robert Friedland, the founder and largest individual shareholder of Ivanhoe Mines, has
indicated that he intends to participate in the rights offering to the maximum permitted level to
maintain his present 18.3% ownership stake in Ivanhoe Mines.
Subject to applicable law, a prospectus and a rights certificate or a Beneficial Owner Election
Form will be mailed to each shareholder after a record date has been set for issuance of the rights
in conjunction with the filing of the final prospectus. The rights offering will be open for
exercise for at least 21 days from the date of mailing to shareholders.
In keeping with international practice in rights offerings, each new common share of Ivanhoe Mines
available for purchase by rights holders will be offered at a discount to Ivanhoe Mines current
market price as at the date of the final prospectus. Subject to applicable law, all Ivanhoe Mines
shareholders will have the choice of deciding whether to participate and, by doing so, to maintain
their existing levels of ownership. It means, for example, that an individual shareholder with a
one per cent stake in Ivanhoe Mines will be issued rights to buy a maximum number of new shares
that would maintain that
shareholders stake at one per cent following completion of the rights offering, assuming all other
shareholders exercised their rights.
13
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
The completion of the rights offering also is conditional on at least 85% of the rights being
exercised by holders of rights, but this condition may be waived at the sole discretion of Ivanhoe
Mines.
An application will be submitted to the Toronto Stock Exchange to approve the listing of the rights
and the common shares issuable upon the exercise of the rights. Similar applications also will be
made to the New York Stock Exchange and the Nasdaq Stock Market to admit the rights for trading and
to list the common shares issuable upon the exercise of the rights, subject to Ivanhoe Mines
fulfilling listing requirements.
Shareholders who do not wish to exercise their rights to buy new common shares under the rights
offering will have the option of selling their rights through the Toronto Stock Exchange, the New
York Stock Exchange or the Nasdaq Stock Market. Shareholders who do not exercise all of their
rights consequently may have their present ownership interests in Ivanhoe Mines, as a percentage of
the total outstanding common shares, reduced to the extent other shareholders exercise their rights
under the rights offering.
Rio Tinto, as an accredited shareholder, will be fully entitled to exercise its rights in the
offering. Rio Tinto currently owns 34.9% of Ivanhoe Mines common shares. Ivanhoe Mines believes
that the rights offering is exempt from Rio Tintos right of first offer to acquire shares issued
by Ivanhoe Mines under terms of Ivanhoe Mines 2006 five-year private-placement agreement with Rio
Tinto, contrary to an assertion by Rio Tinto. Ivanhoe Mines also has advised Rio Tinto that Ivanhoe
Mines does not believe that alternative financing opportunities suggested by Rio Tinto are superior
to Ivanhoe Mines planned rights offering. Citi has been appointed dealer manager for the rights
offering.
MONGOLIA
COAL PROJECTS
SOUTHGOBI RESOURCES (57% owned)
Ongoing expansion of SouthGobis Ovoot Tolgoi coal mine
SouthGobi continues to mine and sell coal produced at its Ovoot Tolgoi Mine in Mongolias South
Gobi Region, approximately 40 kilometres north of the Shivee Khuren-Ceke crossing at the
Mongolia-China border.
In a major transportation infrastructure initiative, SouthGobi announced on October 25, 2010, that
it had entered into a $48 million contract to design and construct a paved highway dedicated to
hauling coal from the Ovoot Tolgoi Mine to a major trans-shipment terminal at Ceke, across the
border in China. The four-lane highway, to be completed by the end of 2012, will be 17 metres wide,
with a one metre central median, and provide SouthGobi with the capacity to ship well in excess of
20 million tonnes of coal per year.
14
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
The terminal at Ceke has rail connections directly to key industrial markets in China. A
north-south railway line connects Ceke with Jiayuguan City in Gansu Province and other markets in
Chinas interior. An east-west railway line from Ceke to Linhe, an industrial city in Chinas
eastern Inner Mongolia, is expected to be in commercial operation in 2011. This line is expected to
have an initial capacity of approximately 15 million tonnes per year, later increasing to
25 million tonnes per year. The line will enable coal to be shipped to markets to the east, such as
the region around Baotou and Hebei Province, and further east to ports on Chinas Bohai Gulf.
During June 2010, SouthGobi began construction of a basic coal-handling facility. The basic
coal-handling facility will include a 300-tonne-capacity dump hopper, which will receive
run-of-mine coal from the Ovoot Tolgoi Mine and feed a rotary breaker that will size coal to a
maximum of 50 millimetres and reject oversize ash. Interim screening operations will continue at
Ovoot Tolgoi until the permanent coal-handling facility is completed.
SouthGobi is studying the feasibility of additional coal beneficiation that may include dry and/or
wet separation plants. Bulk samples have been delivered to testing facilities in China; results are
pending.
In October 2010, SouthGobi approved the purchase of additional equipment, including one Liebherr
R9250 hydraulic excavator, which will replace the Liebherr 994 now in service, and an additional
Terex MT4400 truck. This purchase will provide better fleet flexibility as the new excavator will
be a back-hoe configuration and can load the larger MT 4400 trucks and the smaller TR100 trucks, as
well as mine the thinner seams more cleanly. A fifth equipment fleet has been approved, including
another Liebherr R9250 hydraulic excavator and two more MT4400 trucks, to accelerate production.
In Q310, the increased cost per tonne of sold coal primarily reflected the increased strip ratio
of 5.09 bank cubic metres of waste per tonne of coal, compared to a strip ratio of 2.98 for Q309.
As at September 30, 2010, the carrying amount of the Ovoot Tolgoi coal stockpiles inventory was
reviewed for impairment, which resulted in recording a $7.9 million write-down primarily associated
with the raw high-ash stockpiles. A total of $2.6 million of the write-down was due to the
inclusion of waste-removal costs associated with expansion of the open-pit as a cost of inventory
produced during Q310.
In Q310, SouthGobi shipped approximately 194,000 tonnes of coal at an average realized selling
price of approximately $37 per tonne. This compared to 457,000 tonnes of coal shipped in Q309 at
an average realized selling price of $28 per tonne. The lower sales volume resulted in $6.6 million
of revenue being recognized in Q310 compared to $11.9 million in Q309. Shipments in Q310 were
lower due to low availability of semi-soft coking coal from the Sunset Pits #5 seam in the
short-term mine plan and the limited screening capacity for the higher-ash, higher-sulphur coal
from the Sunset Pits #8, 9 & 10 seams.
In Q210, Ivanhoe Mines reported that there were two issues that had the potential to impact
SouthGobis results in the second half of 2010. Firstly, SouthGobis near-term mine plan included
proportionately less of the better-quality, raw, semi-soft coking coal coming from the Sunset Pits
#5 seam. Secondly, SouthGobi was experiencing areas of higher sulphur than originally expected in
mine plans and studies. SouthGobi previously indicated that some of the higher-sulphur coal
potentially would not be attractive to customers in its current form and may need to be stockpiled
until appropriate processing is in place, or until blending opportunities arose.
15
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
Results in Q310 were impacted by these two issues, while SouthGobi worked on various projects to
mitigate their effect. Some progress subsequently has been made and in October 2010 SouthGobi
announced an increased expected sales volume for the second half of 2010 of approximately 1.5
million tonnes. SouthGobi expects to achieve or exceed this revised sales estimate. Physical coal
shipments are running at record levels in terms of average daily movements by customers trucks.
Contracted sales of 527,000 tonnes during October 2010 exceeded the previous monthly record of
232,000 tonnes set in June 2009. SouthGobi now expects to finish 2010 with a substantial reduction
in unsold coal in its inventory.
SouthGobi has indicated that the pricing of individual coal products for Q410 is expected to
remain broadly the same as for Q310. However, the overall average selling price likely will be
substantially reduced to reflect the fact that a large proportion of sales are of the higher-ash
coal that remained in the stockpile at the end of Q310. The current selling price of the screened
higher-ash, higher-sulphur coal from the Sunset Pits # 8, 9 & 10 seams is approximately $26 per
tonne.
With the full commissioning of the third mining fleet in October 2010, the capacity to move
material in Q410 will be much higher than for Q310. Average capacities for the months of November
and December are expected to be 50% higher than the average monthly capacities in Q310.
Cost of sales was $14.9 million in Q310, compared to $8.6 million for Q309. The increase
primarily relates to the impairment of the raw high-ash coal stockpiles. Cost of sales is comprised
of the cost of the product sold, inventory write-downs, mine administration costs, equipment
depreciation, depletion of pre-production stripping costs and stock-based compensation costs.
Investment in Aspire Mining Limited
On October 26, 2010, SouthGobi announced an agreement with Aspire Mining Limited (Aspire) (ASX:
AKM) to acquire 105,726,650 common shares of Aspire in a private placement at a price of A$0.19 per
share, for an aggregate of approximately A$20.1 million. On completion of the private placement,
SouthGobi will hold approximately 19.9% of Aspire. SouthGobi also will have the right to nominate
one director to the Board of Aspire and the right to maintain its proportionate shareholding in
Aspire for a period of two years. Closing of the transaction is expected to be on or before January
31, 2011, and is subject to the approval of the Australian Stock Exchange and Australias Foreign
Investment Review Board.
Aspire owns 100% of the Ovoot Coking Coal Project in Mongolia, along with the Nurant and Shanagan
coal projects. In addition, Aspire owns a 49% interest in the Windy Knob gold and base metals
project in Western Australia.
Regional coal exploration
A number of SouthGobis exploration licences are associated with the broader Ovoot Tolgoi Complex
and Soumber Deposit. The 2010 exploration program includes drilling, trenching and geological
reconnaissance on a number of licence areas identified as having good potential for coking and
thermal coal deposits.
16
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
The 2010 exploration program began in March 2010. Year-to-date exploration activities include
60,646 cubic metres of trenching and more than 105,800 metres of drilling (core and reverse
circulation). Key targets so far have been the Soumber Deposit, fields surrounding the Soumber
Deposit and also the SW target, which is approximately six kilometres southwest of the Ovoot Tolgoi
Complex. The 2010 drilling program for the Soumber Deposit is complete; results from coal
laboratory analysis are pending.
The drilling program will focus on further definition of known coal occurrences that is intended to
bring them to a NI 43-101-compliant definition stage and to allow for registration with the
Mongolian Government as the next step toward expanding SouthGobis mining-licence holdings.
AUSTRALIA
IVANHOE AUSTRALIA (62% owned)
Ivanhoe Australia incurred exploration expenses of $15.7 million in Q310, compared to $11.5
million in Q309. The increase was largely related to costs incurred for the Merlin molybdenum and
rhenium project prefeasibility study and the commencement of the decline to access the Merlin
Deposit.
Ivanhoe Australias key projects, all situated on granted Mining Leases, are Merlin, Mount Dore and
Mount Elliott. During Q310, work focused on the completion of the equity raising, settlement of
the acquisition of the Osborne Mining Complex, the Merlin Resource Update and the commencement of
the Merlin decline.
A$269 million equity raising completed
On September 10, 2010, Ivanhoe Australia completed its accelerated, non-renounceable, pro rata
entitlement offer, raising gross proceeds of approximately A$269 million. The entitlement offer was
well supported by Ivanhoe Australias current international institutional shareholders, while also
attracting a large number of new domestic investors. As a result of the significant interest
received, the initial contemplated offering of A$231 million was increased to A$269 million.
The shares offered under the entitlement offer consisted of one ordinary share attaching one-half
of one option, with each full option entitling the holder to acquire one Ivanhoe Australia ordinary
share until September 20, 2011, at a price of A$3.38. A total of 46,729,404 options were issued
under the entitlement offer, which could raise a further A$158 million increasing the total
amount raised to approximately A$427 million.
Toronto Stock Exchange listing approved
Ivanhoe Australias application for a compliance listing on the Toronto Stock Exchange (TSX) now
has been approved and the stock will begin trading on the TSX on November 12, 2010. The dual
listing will enhance access to the international pool of resource investors.
17
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
Ivanhoe Australias headquarters will remain in Australia and Ivanhoe Australia will maintain its
listing on the Australian Stock Exchange. There will be no equity offering as part of the listing.
Strategic acquisition of Osborne Complex completed
On September 30, 2010, Ivanhoe Australia completed the strategic acquisition of the Osborne
Complex, which includes a two-million-tonne per annum concentrator, infrastructure and tenements.
Osborne is a significant purchase for Ivanhoe Australia and is expected to advance Ivanhoe
Australias plans for molybdenum and rhenium production and provide the opportunity for
supplementary copper and gold production. Importantly, the integration of the Osborne Complex has
the potential to elevate Ivanhoe Australia to producer status by late 2011, well ahead of previous
plans.
Consideration for the acquisition of the Osborne Complex consisted of: A$17.2 million in cash; a 2%
Net Smelter Return royalty capped at A$15.0 million from ore extracted from the Osborne tenements
only; and the assumption of all site environmental obligations, including the provision of an EPA
Financial Assurance of A$18.4 million (discounted).
Implementation of Ivanhoe Australias integration of its Osborne Complex and Cloncurry sites is
progressing well, with the following key initiatives undertaken during Q310:
|
|
|
The 53-kilometre road linking the Merlin Project with the Osborne Complex has been cleared
and permitted. A number of tender parties have been pre-qualified to enable construction of
the road to start in Q410. |
|
|
|
|
Approximately 35 former Osborne employees have joined Ivanhoe Australia since the
acquisition was announced, including a number of Osbornes key operating managers and
supervisors. Their skills and knowledge will help to ensure a high standard of care and
maintenance, facilitate mining studies of copper-gold sources and assist with a smooth
transition from development to operation. |
|
|
|
|
Ivanhoe Australia conducted a competitive tendering process for the sale of excess volumes
of contracted natural gas identified at the Osborne Complex to Q112. Sale negotiations were
concluded in early October 2010, resulting in net savings of approximately A$4 million to
Ivanhoe Australia. |
Decline roadway to access Merlin molybdenum and rhenium underway
The Merlin Deposit is the lowermost mineralized zone in the Mount Dore Deposit starting near the
surface and dipping east at between 45 and 55 degrees. To date, the deposit has been intersected to
approximately 500 metres down-dip. The overall mineralized zone at Merlin has an average true
thickness of approximately 20 metres. Mineralization has been found over a strike length of 1,300
metres in step-out holes. The mineralization thins to the north, where it also has been noted that
the copper, zinc and gold content increases. To the south, the mineralization flattens and pinches
out. The high-grade Little Wizard Zone represents the southern-most extent of molybdenum
mineralization of economic interest found to date. During Q310, work continued on infill drilling
on the Merlin Project to maximize the indicated resources with assay results confirming molybdenite
intersections.
Construction of the decline to provide underground access to the Merlin Deposit is underway, with
excavation of the box cut. Mining of Little Wizard Zone is expected in Q411.
18
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
The Merlin prefeasibility study work began during Q210 and is expected to be completed in Q410.
The prefeasibility study will examine the various mining, processing and infrastructure options to
develop the Merlin Deposit utilizing the Osborne processing facilities. A feasibility study then
will focus on the preferred development option and produce the financial data for project approval.
Environmental permitting will be undertaken in parallel with the studies and is expected to be
available at the end of the feasibility study, which is expected by Q311.
On August 4, 2010, Ivanhoe Australia released an updated independent resource estimate for the
Merlin Deposit prepared by Golder Associates, of Brisbane, Australia.
Mount Dore Deposit
The Mount Dore heap-leach solvent extraction-electrowinning scoping study continued during Q310
with a final report expected in Q410. Work undertaken during Q310 included preliminary open-pit
assessments, metallurgical test work, recovery modelling, preliminary engineering and preparation
of capital cost and operating cost estimates.
On August 4, 2010, Ivanhoe Australia released an updated independent resource estimate for the
Mount Dore Deposit prepared by Golder Associates of Brisbane, Australia.
Mount Elliott Project
The Mount Elliott Project hosts three principal zones of copper-gold mineralization: Mount Elliott,
SWAN and SWELL. Mineralization primarily is hosted in banded and brecciated calc-silicates and is
associated with albite-pyroxene-magnetite-chalcopyrite-pyrite alteration.
On October 21, 2010, Ivanhoe Australia released an updated independent resource estimate for the
Mount Elliott Project prepared by AMC Consultants. A detailed scoping study will commence when the
resource estimate has been finalized. The scoping study will evaluate the mining of both the
higher-grade portion of the SWAN zone from underground and an open pit to mine the top of the SWAN
zone and the remaining mineralization around and beneath the old Mount Elliot mine. The study also
will evaluate the possibility of processing ore at Ivanhoe Australias Osborne Complex.
Metallurgical testing of the SWAN mineralization has indicated high metal recoveries and readily
saleable concentrates for the sulphide ores.
Regional exploration
Ivanhoe Australia holds 14 Exploration Permits for Minerals (EPMs) and 20 Mining Leases covering a
total of 1,704 square kilometres. Ivanhoe Australia also has 21 EPM applications in process,
covering 2,744 square kilometres. The Osborne EPMs total 529 square kilometres and the Exco joint
venture EPMs total 493 square kilometres. Drilling on Ivanhoe Australias tenements in Q310
focused on the previously mined Starra 222 Deposit and Barnes Shaft Prospect.
19
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
In Q310, four holes were completed at Starra 222, targeting the along-strike projection of
previously mined mineralization. These holes intersected copper-gold mineralized ironstones. The
best intercept
to date is 58 metres at 1.76 grams of gold per tonne and 1.04% copper from 550 metres in hole
STQ1036, including 18 metres at 4.28 grams of gold per tonne and 1.07% copper from 551 metres.
Additional details are available in Ivanhoe Australias news release dated October 26, 2010.
In Q310, 17 diamond drill holes and 11 reverse-circulation holes were drilled at the Barnes Shaft
Prospect targeting copper-gold-cobalt mineralization. Significant mineralization was intersected in
14 holes and is tabulated in Ivanhoe Australias news release dated October 26, 2010.
Exploration on the Osborne ground began in October 2010 and will focus on the Houdini Prospect,
where drilling by Barrick in 2009 targeted a magnetic anomaly. A series of significant, high-grade
copper-gold intercepts were made near surface, including 16 metres at 3.08% copper and 0.58 grams
of gold per tonne.
KAZAKHSTAN
Kyzyl Gold Project (50% owned)
Ivanhoe Mines has a 50% interest in Altynalmas Gold, the company that holds 100% ownership of the
Kyzyl Gold Project in northeastern Kazakhstan. Following the successful completion of the
prefeasibility study in Q310, Altynalmas Gold is proceeding to advance the development of the
Kyzyl Gold Project.
Project drilling program continuing to confirm grades and extent of high-grade gold mineralization
In October 2009, Altynalmas Gold commenced a deep-level drilling program at the Kyzyl Gold Project
intended to upgrade the present mineral resource for inclusion in a prefeasibility study and
follow-on feasibility study.
During the nine months ended September 30, 2010, Altynalmas Gold completed a total of 68,392 metres
of drilling. Altynalmas Gold is continuing its drilling program, with a further 15,000 metres
planned for completion in Q410.
In Q310, 65 holes totalling 25,067 metres were completed and more than 4,100 samples were
collected and prepared for assay. Samples collected during Q310 drilling activities, including
Bakyrchik Lenses 1, 9 and 12, as well as the Promezhutochny and Globiki Log deposits, either are in
transit or being prepared for shipment to Canada for assaying.
On August 9, 2010, Ivanhoe Mines issued a news release containing a summary of Altynalmas Golds
drill results received to that date. Intersection widths and gold grades of the new drill holes
correlate well with the results of the earlier, Soviet-era drilling.
20
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
Project prefeasibility study completed; Fluor Canada retained to complete feasibility study for
planned gold mine
In August 2010, Scott Roscoe Postle Wilson Inc. produced an independent NI 43-101-compliant report
on the Kyzyl Gold Project (the Technical Report), filed on www.sedar.com, which confirmed the
economics of Altynalmas Golds development plan. The Technical Report estimated that probable
mineral reserves contained in Lenses 1, 9 & 10 of the Bakyrchik Deposit one of several deposits
comprising the Kyzyl Gold Project total 13.58 million tonnes, with a grade of 8.65 grams of gold
per tonne (g/t), containing 3.78 million ounces of gold, using a cut-off grade of 4.0 g/t gold and
a gold price of $900 per ounce. Estimated mineral resources, inclusive of reserves, total 13.82
million tonnes at a grade of 9.36 g/t gold for Indicated resources and 12.02 million tonnes at a
grade of 8.58 g/t gold for Inferred resources. Mineral resources were estimated using an average
long-term gold price of $1,000 per ounce.
The Technical Report is based on an underground mining operation producing an average of 368,000
ounces of gold per year during an initial mine life of up to 10 years. A summary of the Technical
Report is provided in Ivanhoe Mines June 30, 2010, news release.
In July 2010, Altynalmas Gold began a definitive feasibility study that is expected to be completed
in late Q111. Altynalmas Gold has engaged Fluor Canada Ltd., Crescent Technology Inc., Technip USA
Inc., Environmental Resources Management, Scott Wilson Roscoe Postle Associates Inc. and
Sustainability East Asia LLC to complete this work, which will be undertaken in parallel with
detailed engineering work.
Altynalmas Gold is investigating financing options for the Kyzyl Gold Project including, but not
limited to, an initial public offering, strategic investors, project financing or continued
financing from existing shareholders.
OTHER EXPLORATION
Ivanhoe Mines has active exploration programs in Indonesia and the Philippines. These programs
principally are being conducted through joint ventures and are focused on orogenic gold,
porphyry-related copper-gold, epithermal vein and breccia-hosted gold-silver and copper deposits.
Exploration has involved detailed data reviews, field traverses and systematic rock-chip and
channel sampling of all properties, trenching and, in some cases, scout diamond drilling. In
addition, Ivanhoe Mines conducted detailed reviews of projects and prospective belts in Canada and
Latin America. Work is ongoing in all these regions.
OTHER DEVELOPMENTS
Rio Tinto increased its interest in Ivanhoe Mines to 34.9% in September, 2010
In September 2010, Ivanhoe Mines issued 40.1 million common shares to Rio Tinto upon the conversion
of Rio Tintos maturing convertible credit facility. The Rio Tinto convertible credit facilitys
$350.0 million outstanding principal, plus accrued interest of $50.8 million, was converted at a
price of $10.00 per common share.
In October 2010, a further 0.7 million common shares were issued to Rio Tinto upon its exercise of
the first series of anti-dilution warrants granted to Rio Tinto under Rio Tintos private-placement
agreement with Ivanhoe Mines. Each anti-dilution warrant entitled Rio Tinto to acquire one common
share in exchange for the payment of C$3.15.
21
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
With these transactions, Rio Tinto now has invested approximately $1.7 billion in Ivanhoe Mines and
increased its ownership in Ivanhoe Mines to approximately 34.9%.
Executive changes; Office of the Chairman to evaluate strategic initiatives
On October 18, 2010, Ivanhoe Mines announced that Executive Chairman Robert Friedland was
re-assuming the duties and title of Chief Executive Officer in a series of organizational changes
that also have seen the establishment of the Office of the Chairman as part of an ongoing
commitment to maximize shareholder value. Mr. Friedland previously served as Chief Executive
Officer of Ivanhoe Mines for 10 years, from the Companys founding until 2006.
The Ivanhoe Mines Board of Directors approved President John Mackens relinquishment of the
position of Chief Executive Officer. As President, Mr. Macken will continue to lead the ongoing
construction of Ivanhoe Mines flagship Oyu Tolgoi copper-gold mining complex in southern Mongolia.
He is a member of the Ivanhoe Mines-Rio Tinto joint Oyu Tolgoi Technical Committee.
Mr. Macken also will continue as an Ivanhoe Mines representative on the Oyu Tolgoi LLC Board of
Directors. As the senior representative of the Operations Committee established by the Oyu Tolgoi
LLC Board, Mr. Macken will be responsible for guiding the strategic direction of construction and
development activities on behalf of the Board. Mr. Macken is one of six Ivanhoe Mines appointees
to the nine-member Oyu Tolgoi LLC Board; an Ivanhoe Mines appointee also is Chairman of the Board.
The Mongolian government, through its wholly-owned company Erdenes MGL LLC, is represented by three
directors on the Oyu Tolgoi LLC Board.
Joining Mr. Friedland in the Office of the Chairman are Peter Meredith, Ivanhoe Mines Deputy
Chairman for the past four years and former Chief Financial Officer, and Sam Riggall, who is
Executive Vice President of Ivanhoe Australia and now is taking on the added duties of Executive
Vice President, Business Development and Strategic Planning, with Ivanhoe Mines. Mr. Riggall
previously worked at Rio Tinto for more than a decade in a variety of roles covering project
generation and evaluation, business development and capital market transactions. He has significant
experience working in many parts of the world, where he managed a number of government negotiations
over mine development projects.
Mr. Meredith led the Ivanhoe Mines team and Mr. Riggall led the Rio Tinto team during the
successful negotiations with the Mongolian government that culminated in the approval of the
Investment Agreement in October 2009. Mr. Meredith and Mr. Riggall also are Directors of Oyu Tolgoi
LLC.
The Office of the Chairman, with facilities in Vancouver, London and Singapore, will lead the
assessment of potential strategic initiatives and direct any necessary negotiations to create and
enhance value for shareholders. The Office of the Chairman also will assume responsibilities within
Ivanhoe Mines related to the development of other subsidiary interests, including SouthGobi
Resources, Ivanhoe Australia and Altynalmas Gold.
22
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
Appointment of additional directors
On September 16, 2010, Ivanhoe Mines announced the appointments to the Ivanhoe Mines Board of
Directors of Michael Gordon, former Executive Vice President of Anglo American Plc, and Dan
Westbrook, former President, BP China Gas, Power & Upstream. Both directors occupied two vacant
seats on the board and serve as non-executive, independent board members.
On November 5, 2010, Ivanhoe Mines announced the appointment to the Ivanhoe Mines Board of
Directors of Robert B. Holland III, Executive Co-Chairman of Max Petroleum and former United States
Executive Director of the World Bank. Mr. Holland will serve as a non-executive, independent member
of the board and occupy the vacancy created by the retirement of Robert Hanson after more than a
decade as an Ivanhoe Mines director.
Mr. Gordon, Mr. Westbrook and Mr. Holland were nominated to the Ivanhoe Mines Board of Directors by
Rio Tinto, increasing the present number of Rio Tinto appointees to four. Tracy Stevenson, the
fourth Rio Tinto appointee, became an independent Ivanhoe Mines director on June 1, 2010. Under the
terms of the October 2006 private-placement agreement between Rio Tinto and Ivanhoe Mines, Rio
Tinto is entitled to nominate a proportionate share of members to the Ivanhoe Mines Board of
Directors, based on Rio Tintos shareholding in Ivanhoe Mines.
Independent arbitrator to hear claim and counter-claim
between Rio Tinto and Ivanhoe Mines in early 2011
On October 26, 2010, Ivanhoe Mines announced that it had delivered a statement of defence and
initiated a counter-claim as part of an ongoing arbitration proceeding launched by Rio Tinto on
July 9, 2010. The statement of defence rejects Rio Tintos claim that the shareholders rights plan
approved by Ivanhoe Mines shareholders on May 7, 2010, breached Rio Tintos contractual rights
under its agreements with Ivanhoe Mines.
The counter-claim contends that Rio Tinto has breached its covenants in its private-placement
agreement, signed with Ivanhoe Mines in October 2006, not to engage in activities that could affect
control of Ivanhoe Mines without Ivanhoe Mines permission.
An independent arbitrator has scheduled hearings of the claim and counter-claim between January 18
and February 5, 2011.
B. DISCONTINUED OPERATIONS
In February 2005, Ivanhoe Mines sold the Savage River Iron Ore Project in Tasmania, Australia, for
two initial cash payments totalling $21.5 million, plus a series of five contingent, annual
payments that commenced on March 31, 2006. From 2006 to 2009, these contingent payments totalled
$116.4 million.
During Q210, Ivanhoe Mines received two payments totalling $6.4 million in relation to the fifth
annual contingent payment. The original purchaser of the Savage River Project has disputed the
estimated $22.1 million remaining balance of the fifth annual contingent payment. Ivanhoe Mines is
committed to collecting the full amount of the fifth annual contingent payment and has included the
total estimated
amount of $22.1 million in accounts receivable as at September 30, 2010. In Q310, Ivanhoe Mines
initiated arbitration proceedings.
23
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
To date, Ivanhoe Mines has received $144.4 million in proceeds from the sale of the Savage River
Project.
C. ADMINISTRATIVE AND OTHER
General and administrative costs. General and administrative costs in Q310 were $15.0 million, an
increase of $2.5 million from Q309 ($12.5 million). The main reasons for the increase were higher
consulting costs and a $0.5 million increase in non-cash stock-based compensation expense.
Interest income. Interest income in Q310 of $3.8 million was $3.3 million higher than Q309 ($0.5
million). The main reasons for the increase were the recognition of $1.1 million (Q309 $0.2
million) interest income on Ivanhoe Australias increased average cash equivalents balance; $0.7
million (Q309 $nil) interest income on Ivanhoe Mines shareholder loan balance with Altynalmas
Gold; and the aggregate $0.9 million interest income earned on the Mongolian Government T-Bill and
first tax prepayment (Q309 $nil).
Interest expense. Interest expense in Q310 of $6.3 million was mainly attributable to $4.9 million
(Q309 $nil) in interest being incurred by SouthGobi on the convertible debenture issued to CIC
and $1.2 million (Q309 $3.8 million) incurred by Ivanhoe Mines on the Rio Tinto convertible
credit facility.
Foreign exchange gains. The $5.3 million foreign exchange gain during Q310 was mainly attributable
to the strengthening of the Canadian and Australian dollars against the U.S. dollar during Q310.
The majority of this foreign exchange gain was unrealized at September 30, 2010.
Share of loss of significantly influenced investees. The $8.5 million share of loss of
significantly influenced investees in Q310 represents Ivanhoe Mines share of Altynalmas Golds
($8.4 million) and Exco Resources N.L.s ($0.1 million) net losses.
Change in fair value of embedded derivatives. The $49.8 million change in fair value of embedded
derivatives relates to the Q310 change in fair value of the CIC convertible debentures embedded
derivative liability.
LIQUIDITY AND CAPITAL RESOURCES
Cash flow
Operating activities. The $42.6 million of cash used in operating activities in Q310 primarily was
the result of $41.7 million in cash exploration expenditures, $12.2 million in cash general and
administrative expenditures and a $10.6 million decrease in non-cash operating working capital.
Investing activities. The $234.0 million of cash used in investing activities in Q310 included
$222.8 million used in property, plant and equipment purchases mainly relating to Oyu Tolgoi
($182.6 million),
Ovoot Tolgoi ($22.3 million) and Ivanhoe Australias acquisition of the Osborne Complex ($17.0
million). There also were advances to Altynalmas Gold totalling $5.8 million.
24
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
Financing activities. The $242.3 million in cash provided by financing activities mainly was
attributable to $232.8 million received on the completion of Ivanhoe Australias equity raising and
$11.3 million received upon the exercise of stock options.
Liquidity and capital resources
At September 30, 2010, Ivanhoe Mines consolidated working capital was $1.4 billion, including cash
and cash equivalents of $1.4 billion, compared with working capital of $597.9 million and cash and
cash equivalents of $965.8 million at December 31, 2009. Included in the September 30, 2010, cash
and cash equivalents balance of $1.4 billion was $613.5 million of SouthGobis cash and cash
equivalents and $174.4 million of Ivanhoe Australias cash and cash equivalents, which were not
available for the Companys use.
As at November 10, 2010, Ivanhoe Mines current consolidated cash position was approximately $1.3
billion. Ivanhoe Mines, based on its current cash position and the value of investments in
publicly-traded subsidiaries, believes that its existing funds should be sufficient to fund its
minimum obligations, including general corporate activities, for at least the next 12 months.
Ivanhoe Mines cash position that is available for the Oyu Tolgoi Project, together with the future
proceeds from the expected exercise by Rio Tinto of its Ivanhoe Mines warrants and 90% of the
future net proceeds expected from the conditional rights offering are expected to total
approximately $2.2 billion, which is expected to provide the foundation for the funding of the Oyu
Tolgoi Project.
Negotiations are proceeding on finalizing a detailed term sheet with the core lenders group
involving an upfront, multi-billion dollar commitment with a first tranche released on closing,
which is targetted for completion in the first half of 2011, and a second tranche released when the
underground mining plan is better defined (expected to be in 2012), with flexibility to adjust
final loan amounts at that time. The financing is structured as a true limited-recourse project
financing with no recourse to Ivanhoe Mines following project completion and with long maturities
and grace periods appropriate for a large-scale project such as Oyu Tolgoi.
25
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
Carrying out the development and exploration of the Oyu Tolgoi Project and the various other
mineral properties in which Ivanhoe Mines holds interests depends upon Ivanhoe Mines ability to
obtain financing through capital markets, sales of non-core assets or other means. Ivanhoe Mines
expects to be able to meet its minimum obligations from its existing financial resources but these
funds will not be sufficient to meet all anticipated development expenditure requirements. The
Series B Warrants and the Series C Warrants held by Rio Tinto may, if exercised in full, account
for a portion of the development cost of the Oyu Tolgoi Project, but will be insufficient to fund
the entire development cost. There is no assurance that Rio Tinto will fully exercise either the
Series B Warrants or the Series C Warrants, both of which are exercisable at the sole discretion of
Rio Tinto. Even if Rio Tinto fully exercises the Series B Warrants and the Series C Warrants,
Ivanhoe Mines will require access to additional sources of capital including funds from the
successful completion of the rights offering and the implementation of a comprehensive financing
plan to complete the development of the Oyu Tolgoi
Project and to advance the development of its other mineral properties. The terms of the Oyu Tolgoi
Investment Agreement oblige Ivanhoe Mines to obtain, within two years of the agreements Effective
Date, project financing sufficient to complete the development activities necessary to establish
commercial production. Market volatility in precious and base metals may affect the terms upon
which debt financing or equity financing is available. Ivanhoe Mines operates in a region of the
world that is prone to economic and political upheaval and instability, which may make it more
difficult for Ivanhoe Mines to obtain debt financing from project lenders. Failure to obtain
additional financing on a timely basis, including successful completion of the rights offering, may
cause Ivanhoe Mines to postpone its development plans, forfeit rights in some or all of its
properties or joint ventures, reduce or terminate some or all of its operations or force Ivanhoe
Mines to raise funds from alternative sources on less favourable terms.
26
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
Financial instruments
The estimated fair value of Ivanhoe Mines financial instruments was as follows:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
September 30, |
|
|
December 31, |
|
|
|
2010 |
|
|
2009 |
|
|
|
Carrying |
|
|
Fair |
|
|
Carrying |
|
|
Fair |
|
(Stated in $000s of dollars) |
|
Amount |
|
|
Value |
|
|
Amount |
|
|
Value |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Financial Assets |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Held-for-trading financial assets |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Cash and cash equivalents |
|
$ |
1,440,119 |
|
|
$ |
1,440,119 |
|
|
$ |
965,823 |
|
|
$ |
965,823 |
|
Short-term investments |
|
|
7,505 |
|
|
|
7,505 |
|
|
|
14,999 |
|
|
|
14,999 |
|
Long-term investments |
|
|
6,027 |
|
|
|
6,027 |
|
|
|
9,876 |
|
|
|
9,876 |
|
Other long-term investments |
|
|
98,297 |
|
|
|
98,297 |
|
|
|
71,883 |
|
|
|
71,883 |
|
Available-for-sale financial assets |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Long-term investments |
|
|
65,302 |
|
|
|
65,302 |
|
|
|
63,276 |
|
|
|
63,276 |
|
Other long-term investments |
|
|
114,122 |
|
|
|
114,122 |
|
|
|
73,152 |
|
|
|
73,152 |
|
Loans and receivables |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Accounts receivable |
|
|
60,159 |
|
|
|
60,159 |
|
|
|
39,349 |
|
|
|
39,349 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Investments in companies subject to
significant influence |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Long-term investments |
|
|
17,528 |
|
|
|
128,577 |
|
|
|
20,359 |
|
|
|
81,824 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Financial Liabilities |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Accounts payable and accrued liabilities |
|
|
162,942 |
|
|
|
162,942 |
|
|
|
55,128 |
|
|
|
55,128 |
|
Amounts due under credit facilities |
|
|
55,757 |
|
|
|
55,757 |
|
|
|
55,523 |
|
|
|
55,523 |
|
CIC convertible credit facility
debt host contract and interest payable |
|
|
102,730 |
|
|
|
102,730 |
|
|
|
191,430 |
|
|
|
191,430 |
|
Rio Tinto convertible credit facility |
|
|
|
|
|
|
|
|
|
|
378,916 |
|
|
|
390,678 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Derivatives |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CIC convertible credit facility
embedded derivative liability |
|
|
134,882 |
|
|
|
134,882 |
|
|
|
358,272 |
|
|
|
358,272 |
|
The fair value of Ivanhoe Mines long-term investments was determined by reference to published
market quotations, which may not be reflective of future values.
The fair value of Ivanhoe Mines other long-term investments, consisting of the Long-Term Notes,
the Mongolian Treasury Bill and long-term money market instruments, was determined by considering
the best available data regarding market conditions for such investments, which may not be
reflective of future values.
The fair value of the Rio Tinto convertible credit facility was estimated to approximate the
balance of principal and interest outstanding, due primarily to the short-term maturity of this
facility.
27
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
The fair value of the CIC convertible debenture was estimated to approximate the aggregate carrying
amount of the CIC convertible credit facility liability and interest payable. This aggregate
carrying amount includes the estimated fair value of the embedded derivative liability, which was
determined using a Monte Carlo simulation valuation model.
The fair values of Ivanhoe Mines remaining financial instruments were estimated to approximate
their carrying values, due primarily to the immediate or short-term maturity of these financial
instruments.
The consolidated statements of operations include the following amounts of unrealized
gains (losses) from fair value adjustments to financial instruments:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended |
|
|
Nine Months Ended |
|
|
|
September 30, |
|
|
September 30, |
|
(Stated in $000s of dollars) |
|
2010 |
|
|
2009 |
|
|
2010 |
|
|
2009 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Unrealized gains (losses) on long-term
investments |
|
$ |
1,363 |
|
|
$ |
|
|
|
$ |
(3,849 |
) |
|
$ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Unrealized gains on other long-term
investments |
|
|
2,019 |
|
|
|
649 |
|
|
|
3,528 |
|
|
|
15 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Change in fair value of embedded derivatives |
|
|
49,772 |
|
|
|
|
|
|
|
120,633 |
|
|
|
|
|
The consolidated statement of accumulated other comprehensive income includes the following amounts
of unrealized gains (losses) from fair value adjustments to financial instruments:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended |
|
|
Nine Months Ended |
|
|
|
September 30, |
|
|
September 30, |
|
(Stated in $000s of dollars) |
|
2010 |
|
|
2009 |
|
|
2010 |
|
|
2009 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Changes in fair value of long-term
investments |
|
$ |
14,133 |
|
|
$ |
34,105 |
|
|
$ |
1,694 |
|
|
$ |
39,066 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Changes in fair value of other long-term
investments |
|
|
1,703 |
|
|
|
|
|
|
|
(11,539 |
) |
|
|
|
|
Ivanhoe Mines is exposed to credit risk with respect to its accounts receivable. The significant
concentrations of credit risk are situated in Mongolia and Australia. Ivanhoe Mines does not
mitigate the balance of this risk in light of the credit worthiness of its major debtors.
Ivanhoe Mines is exposed to interest-rate risk with respect to the variable rates of interest
incurred on the Rio Tinto convertible credit facility and amounts due under credit facilities.
Interest-rate risk is concentrated in Canada. Ivanhoe Mines does not mitigate the balance of this
risk.
28
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
SHARE CAPITAL
At November 10, 2010, the Company had a total of:
|
|
|
531.2 million common shares outstanding. |
|
|
|
|
18.8 million incentive stock options outstanding, with a weighted average exercise price
of C$9.33 per share. Each option is exercisable to purchase a common share of the Company
at prices ranging from C$2.82 to C$19.18 per share. |
|
|
|
|
46.0 million share-purchase warrants outstanding granted to Rio Tinto. The lives of
these warrants are determined by the date on which an approved Investment Agreement is
reached. The warrant determination date within the warrant terms presented below is the
earlier of the date on which an approved Investment Agreement is reached or October 27,
2009. |
The 46,026,522 Series B Warrants are non-transferable. Each warrant entitles Rio Tinto to
purchase one common share of the Company at a price of:
|
(i) |
|
$8.38 during the period commencing November 30, 2006 and ending 180 days
following the warrant determination date; |
|
|
(ii) |
|
$8.54 during the period commencing 181 days after the warrant determination
date and ending 365 days after the warrant determination date; |
|
|
(iii) |
|
$8.88 during the period commencing 366 days after the warrant determination
date and ending 545 days after the warrant determination date; and |
|
|
(iv) |
|
$9.02 during the period commencing 546 days after the warrant determination
date and ending 725 days after the warrant determination date. |
|
|
|
35.0 million Series C share-purchase warrants outstanding granted to Rio Tinto as part
of the $350.0 million credit facility agreement, with an exercise price of $10.00 per
share, which are exercisable until October 24, 2012. |
|
|
|
|
0.7 million share purchase warrants outstanding with an exercise price of C$3.15 per
share. These warrants were granted to Rio Tinto under certain anti-dilution provisions in
the 2006 private-placement agreement and have lives identical to the Series B warrants. |
OUTLOOK
The information below is in addition to the disclosure concerning specific operations included in
the Review of Operations section of this MD&A.
General Economic Conditions
The markets in which Ivanhoe Mines expects to sell its products have shown dramatic improvement
during the year, although prices for copper, gold and coal continue to be volatile. Increases in
coal and copper demand continue to be primarily centred in Asia. There continues to be significant
concern about the short- and medium-term global economic outlook, particularly given recent events
in Europe regarding actions taken by the European Central Bank and the International Monetary Fund;
however, stability appears to be returning to financial and commodity markets. The cost of
obtaining capital
continues to be volatile and there continues to be limited availability of funds. Accordingly,
management is reviewing the effects of the current conditions on Ivanhoe Mines business.
29
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
Exchange rates
The sale of Ivanhoe Mines coal products are denominated in US dollars.
Ivanhoe Mines holds a portion of its cash resources in currencies other than the US$. Ivanhoe Mines
expects to incur future expenditures in currencies other than the US$, most notably in Canadian and
Australian dollars. As a result, exchange gains and losses from holding Canadian and Australian
dollars primarily are unrealized and are expected to continue to fluctuate significantly given the
recent volatility in foreign exchange rates.
Capital expenditures
Ivanhoe Mines continues to review its capital spending in light of current market conditions.
In late 2009, the joint Ivanhoe Mines-Rio Tinto Oyu Tolgoi Technical Committee conditionally
approved a budget for 2010 to begin full-scale construction of the Oyu Tolgoi mining complex. That
budget subsequently was modified as construction activities commenced and now totals $914 million.
The 2010 budget provided for an early start on a site-wide development program at Oyu Tolgoi. The
budget included Ivanhoe Mines repurchase from Rio Tinto of $195.4 million of key mining and
milling equipment that was financed by the sale of 15 million shares to Rio Tinto at a price of
$16.07 per share (C$16.31 per share) for proceeds of $241.1 million (C$244.7 million).
The projected expenditures for the development and operation of the Oyu Tolgoi Project are based on
the 2010 Integrated Development Plan. The Integrated Development Plan established estimates of
resources, construction and development costs, operating costs and project economic returns based,
in part, on assumptions about future metal prices and future cost inputs, determined as at May
2010.
The Technical Committee, independent of the Integrated Development Plan, has initiated its own
review and analysis of all relevant measures required to develop and operate Oyu Tolgois phase-one
open pit and phase-two underground mining and processing activities. The preparation of a Joint
Mine Development Plan for Oyu Tolgoi will continue into 2011 and is expected to involve extensive
stakeholder analysis and consultation on several levels, including among Ivanhoe Mines and Rio
Tinto technical personnel and the Oyu Tolgoi LLC Board of Directors.
There are indications from work by Fluor Corporation, the Oyu Tolgoi program management contractor,
and the Technical Committee that the projects pre-production capital costs will be materially
higher than were estimated in the scenarios studied in the 2010 Integrated Development Plan.
Contributing factors include a more aggressive construction schedule that is expected to ensure an
earlier start to production, in 2012, with commensurate earlier generation of sales revenues,
fluctuations in foreign-currency exchange rates and escalation of costs for equipment, materials,
labour and preparation of the workforce for operations.
30
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
Development programs and budgets for the Oyu Tolgoi Project are within the jurisdiction of the
joint Technical Committee. Representatives of Ivanhoe Mines and Rio Tinto on the Technical
Committee have expressed differing opinions on several issues that could affect key aspects of
project development, including the determination and timing of capital and operating costs and
project scheduling. The extent to which these differences of opinion will be resolved or will
become matters of disagreement depends upon the results of ongoing and future evaluations and
consultations. Any disagreements between Ivanhoe Mines and Rio Tinto over development programs and
budgets for the Oyu Tolgoi Project could be decided by Rio Tintos voting majority on the Technical
Committee. If Rio Tinto, through the exercise of its voting majority, compels adoption of a Joint
Mine Development Plan that is significantly different from previously outlined scenarios, the
projected operating costs, construction and development costs, production and economic returns may
differ materially from those projected under the 2010 Integrated Development Plan.
Although the Technical Committee oversees and supervises the development, operation and management
of the Oyu Tolgoi Project, the Board of Directors of Oyu Tolgoi LLC also must approve certain
development, operational and management matters relating to the project. It is possible that the
Oyu Tolgoi LLC Board may not agree with the views of the Technical Committee. Ivanhoe Mines owns an
indirect, 66% equity interest in Oyu Tolgoi LLC. Erdenes LLC, a Mongolian company wholly owned by
the Government of Mongolia, holds the remaining 34%. Six of the nine Oyu Tolgoi LLC directors were
appointed by Ivanhoe Mines and three were appointed by the Mongolian Government. A Shareholders
Agreement governs matters involving the business of Oyu Tolgoi LLC, including the manner in which
the Oyu Tolgoi LLC shareholders will fund their financial contributions to the development of the
Oyu Tolgoi Project.
Timely consensus on key issues among all stakeholders is essential to maintain the Oyu Tolgoi
Projects current development and start-up schedule. Any delays to the schedule could adversely
affect Ivanhoe Mines financial performance and condition.
See Joint Mine Development Plan being prepared to chart early start to Oyu Tolgoi production in
2012 for more information on the capital expenditure review process currently underway.
The implementation of the activities contemplated by the 2010 budget and the creation of the
commitments required to advance the Oyu Tolgoi Project based on the current construction schedule
are contingent upon the timely availability of sufficient financial resources to fund these
activities and commitments. Various financing alternatives continue to be assessed, but there can
be no assurance that sufficient funding will be available as and when it will be required to
maintain the currently contemplated project development schedule.
See Liquidity and Capital Resources for more information on Ivanhoe Mines financing plans for
the Oyu Tolgoi Project.
Other information
The Company is actively involved in advancing several other projects. These activities are expected
to continue throughout the remainder of 2010, with a focus on subsidiary SouthGobi and its mining
of coal; subsidiary Ivanhoe Australia and its integration of the Osborne Complex, its activities on
its
Cloncurry tenements and its Tennant Creek joint-venture; and Altynalmas Gold and its drilling
program at the Kyzyl Gold Project. SouthGobi and Ivanhoe Australia have sufficient funds to advance
their operations and development plans for 2010. Ivanhoe Mines owns 50% of Altynalmas Gold, which
is reviewing its operating plans to determine the amount of funding that it will require from its
shareholders.
31
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
OFF-BALANCE-SHEET ARRANGEMENTS
During the quarter ended September 30, 2010, Ivanhoe Mines was not a party to any off-balance-sheet
arrangements that have, or are reasonably likely to have, a current or future effect on the results
of operations, financial condition, revenues or expenses, liquidity, capital expenditures or
capital resources of the Company.
CONTRACTUAL OBLIGATIONS
As at September 30, 2010, there were no significant changes in Ivanhoe Mines contractual
obligations from those disclosed in its MD&A for the year ended December 31, 2009, except for those
related to the Oyu Tolgoi Project in Mongolia. In Q310, Ivanhoe Mines entered into significant
contractual obligations in connection with the full-scale mine construction activity underway at
the Oyu Tolgoi Project.
The following table summarizes Ivanhoe Mines contractual obligations related to the Oyu Tolgoi
Project:
Oyu Tolgoi Project Payments Due by Period
($000s of U.S. dollars)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
December 31, |
|
|
|
September 30, 2010 |
|
|
2009 |
|
|
|
Less than 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
year |
|
|
1 - 3 years |
|
|
4 - 5 years |
|
|
After 5 years |
|
|
Total |
|
|
Total |
|
Operating leases (1) |
|
$ |
688 |
|
|
$ |
|
|
|
$ |
|
|
|
$ |
|
|
|
$ |
688 |
|
|
$ |
392 |
|
Purchase obligations (1) |
|
|
258,156 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
258,156 |
|
|
|
13,439 |
|
Other long-term obligations (2) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14,918 |
|
|
|
14,918 |
|
|
|
14,918 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total |
|
$ |
258,844 |
|
|
$ |
|
|
|
$ |
|
|
|
$ |
14,918 |
|
|
$ |
273,762 |
|
|
$ |
28,749 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(1) |
|
These amounts mainly represent various long-term contracts that include
commitments for future operating payments under contracts for drilling, engineering,
equipment purchases, rentals and other arrangements. |
|
(2) |
|
Other long-term obligations consist of asset retirement obligations. |
CHANGES IN ACCOUNTING POLICIES
In January 2010, the Financial Accounting Standards Board Accounting Standards Codification (ASC)
guidance for fair value measurements and disclosures was updated to require additional disclosures
related to transfers in and out of level 1 and 2 fair value measurements and enhanced detail in the
level 3 reconciliation. The updated guidance clarified the level of disaggregation required for
assets and liabilities and the disclosures required for inputs and valuation techniques to be used
to measure the fair value of assets and liabilities that fall in either level 2 or level 3. The
updated guidance was effective for the Companys fiscal year beginning January 1, 2010, except for
the level 3 disaggregation which is effective for the Companys fiscal year beginning January 1,
2011. The adoption of the updated guidance had no impact on the Companys consolidated financial
position, results of operations or cash flows.
32
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
In June 2009, the ASC guidance for consolidation accounting was updated to require an entity to
perform a qualitative analysis to determine whether the enterprises variable interest gives it a
controlling financial interest in a Variable Interest Entity (VIE). This qualitative analysis
identifies the primary beneficiary of a VIE as the entity that has both of the following
characteristics: (i) the power to direct the activities of a VIE that most significantly impact the
entitys economic performance and (ii) the obligation to absorb losses or receive benefits from the
entity that could potentially be significant to the VIE. The updated guidance was effective for the
Companys fiscal year beginning January 1, 2010. The adoption of the updated guidance had no
impact on the Companys consolidated financial position, results of operations or cash flows.
CRITICAL ACCOUNTING ESTIMATES
The preparation of financial statements in conformity with generally accepted accounting principles
in the United States requires the Company to establish accounting policies and to make estimates
that affect both the amount and timing of the recording of assets, liabilities, revenues and
expenses. Some of these estimates require judgments about matters that are inherently uncertain.
The Companys significant accounting policies, and the estimates derived therefrom, identified as
being critical are substantially unchanged from those disclosed in its MD&A for the year ended
December 31, 2009.
RECENT ACCOUNTING PRONOUNCEMENTS
There were no recently issued United States accounting pronouncements other than those the Company
previously disclosed in its MD&A for the year ended December 31, 2009 or those already adopted in
2010 and disclosed under Changes in Accounting Policies.
INTERNATIONAL FINANCIAL REPORTING STANDARDS
Ivanhoe Mines has been monitoring the deliberations and progress being made by accounting
standard-setting bodies and securities regulators in Canada and the United States on their plans
regarding convergence to International Financial Reporting Standards (IFRS). Ivanhoe Mines is a
domestic issuer under Canadian securities law and a foreign private issuer under US Securities
and Exchange Commission (SEC) regulations. Ivanhoe Mines files its financial statements with
Canadian and US securities regulators in accordance with US GAAP, as permitted under current
regulations. In
2008, the Accounting Standards Board in Canada and the Canadian Securities Administrators (CSA)
confirmed that domestic issuers will be required to transition to IFRS for fiscal years beginning
on or after January 1, 2011. On October 1, 2010, the CSA approved National Instrument 52-107,
Acceptable Accounting Principles and Auditing Standards (NI 52-107) which permits Canadian public
companies that are also SEC registrants the option to prepare their financial statements in
accordance with US GAAP. Under NI 52-107 there will be no requirement to provide a reconciliation
of the US GAAP financial statements to IFRS. Consequently, Ivanhoe Mines is not required to convert
to IFRS effective January 1, 2011.
33
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
RISKS AND UNCERTAINTIES
Material risks and uncertainties affecting Ivanhoe Mines, their potential impact, and the Companys
principal risk-management strategies are substantially unchanged from those disclosed in its MD&A
for the year ended December 31, 2009.
RELATED-PARTY TRANSACTIONS
The following tables summarize related-party expenses incurred by Ivanhoe Mines, primarily on a
cost-recovery basis, with an officer of a subsidiary of Ivanhoe Mines, a company affiliated with
Ivanhoe Mines, or with companies related by way of directors or shareholders in common. The tables
below summarize the transactions with related parties and the types of expenditures incurred with
related parties:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended |
|
|
Nine Months Ended |
|
|
|
September 30, |
|
|
September 30, |
|
(Stated in $000s of U.S. dollars) |
|
2010 |
|
|
2009 |
|
|
2010 |
|
|
2009 |
|
Global Mining Management (a) |
|
$ |
2,375 |
|
|
$ |
1,876 |
|
|
$ |
7,441 |
|
|
$ |
5,269 |
|
Ivanhoe Capital Aviation LLC (b) |
|
|
1,891 |
|
|
|
1,485 |
|
|
|
5,085 |
|
|
|
4,455 |
|
Fognani & Faught, PLLC (c) |
|
|
55 |
|
|
|
(149 |
) |
|
|
173 |
|
|
|
60 |
|
Ivanhoe Capital Corporation (d) |
|
|
218 |
|
|
|
|
|
|
|
333 |
|
|
|
|
|
Ivanhoe Capital Services Ltd. (e) |
|
|
206 |
|
|
|
172 |
|
|
|
525 |
|
|
|
448 |
|
Rio Tinto plc (f) |
|
|
1,642 |
|
|
|
2,156 |
|
|
|
6,573 |
|
|
|
6,423 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
6,387 |
|
|
$ |
5,540 |
|
|
$ |
20,130 |
|
|
$ |
16,655 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Three Months Ended |
|
|
Nine Months Ended |
|
|
|
September 30, |
|
|
September 30, |
|
|
|
2010 |
|
|
2009 |
|
|
2010 |
|
|
2009 |
|
Exploration and development |
|
$ |
1,642 |
|
|
$ |
2,156 |
|
|
$ |
6,573 |
|
|
$ |
6,423 |
|
Legal |
|
|
55 |
|
|
|
(149 |
) |
|
|
173 |
|
|
|
60 |
|
Office and administrative |
|
|
902 |
|
|
|
566 |
|
|
|
2,373 |
|
|
|
1,566 |
|
Salaries and benefits |
|
|
1,897 |
|
|
|
1,482 |
|
|
|
5,926 |
|
|
|
4,151 |
|
Travel (including aircraft rental) |
|
|
1,891 |
|
|
|
1,485 |
|
|
|
5,085 |
|
|
|
4,455 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$ |
6,387 |
|
|
$ |
5,540 |
|
|
$ |
20,130 |
|
|
$ |
16,655 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The above noted transactions were in the normal course of operations and were measured at the
exchange amount, which is the amount of consideration established and agreed to by the related
parties.
34
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
Accounts receivable and accounts payable at September 30, 2010, included $0.7 million and $5.9
million, respectively (December 31, 2009 $0.7 million and $4.8 million, respectively), which were
due from/to a company under common control, a company affiliated with Ivanhoe Mines, or companies
related by way of directors in common.
(a) |
|
Global Mining Management Corporation (Global) is a private company based in Vancouver owned
equally by seven companies, one of which is Ivanhoe Mines. Global has a director in common
with the Company. Global provides administration, accounting and other office services to the
Company on a cost-recovery basis. |
|
(b) |
|
Ivanhoe Capital Aviation LLC (Aviation) is a private company 100%-owned by the Companys
Chairman. Aviation operates aircraft which are rented by the Company on a cost-recovery basis. |
|
(c) |
|
An officer of a subsidiary of Ivanhoe Mines is associated with Fognani & Faught, PLLC, a
legal firm that provides legal services to Ivanhoe Mines. |
|
(d) |
|
Ivanhoe Capital Corporation (ICC) is a private company 100%-owned by the Companys Chairman.
ICC provides administration and other office services out of London, England on a
cost-recovery basis. |
|
(e) |
|
Ivanhoe Capital Services Ltd. (ICS) is a private company 100%-owned by the Companys
Chairman. ICS provides management services out of Singapore on a cost-recovery basis. |
|
(f) |
|
Rio Tinto owns 34.9% of Ivanhoe Mines. Rio Tinto provides engineering-related services for
the Oyu Tolgoi Project on a cost-recovery basis. |
In March 2010, Ivanhoe Mines and Rio Tinto completed an agreement whereby the Company issued
15 million common shares to Rio Tinto for net proceeds of $241.1 million (C$244.7 million).
Ivanhoe Mines used $195.4 million of the proceeds to purchase from Rio Tinto key mining and
milling equipment to be installed during the construction of the Oyu Tolgoi Project.
In June 2010, Rio Tinto exercised its 46.0 million Series A warrants four months ahead of
schedule. Upon the exercise of the Series A warrants, Ivanhoe Mines issued 46.0 million
common shares to Rio Tinto at $8.54 per share, for total proceeds of $393.1 million. The
proceeds will be used to finance ongoing mine development activities at the Oyu Tolgoi
Project.
In September 2010, Ivanhoe Mines issued 40.1 million common shares to Rio Tinto upon the
conversion of Rio Tintos maturing convertible credit facility. The Rio Tinto convertible
credit facilitys $350.0 million outstanding principal, plus accrued interest of $50.8
million, was converted at a price of $10.00 per common share.
In October 2010, a further 0.7 million common shares were issued to Rio Tinto upon its
exercise of the first series of anti-dilution warrants granted to Rio Tinto under Rio
Tintos private-
placement agreement with Ivanhoe Mines. Each anti-dilution warrant entitled Rio Tinto to
acquire one common share in exchange for the payment of C$3.15.
35
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
Ivanhoe Mines has a 50% interest in Altynalmas Gold. During the nine months ended September 30,
2010, Ivanhoe Mines recognized $4.3 million (nine months ended September 30, 2009 Nil) in
interest income on its shareholder loan balance with Altynalmas Gold.
The Companys Chairman has a 34% interest in Ivanhoe Nickel and Platinum Ltd. (Ivanplats). During
Q110, Ivanhoe Mines acquired 125,665 common shares of Ivanplats from an unrelated party at a cost
of $563,000. As at September 30, 2010, Ivanhoe Mines held a 9.2% equity interest in Ivanplats on a
fully diluted basis.
CHANGES IN INTERNAL CONTROL OVER FINANCIAL REPORTING
During the three months ended September 30, 2010, there were no changes in the Companys internal
control over financial reporting that have materially affected, or are reasonably likely to
materially affect, the Companys internal control over financial reporting.
QUALIFIED PERSONS
Disclosures of a scientific or technical nature in this MD&A in respect of each of Ivanhoe Mines
material mineral resource properties were prepared by, or under the supervision of, the qualified
persons (as that term is defined in NI 43-101) listed below:
|
|
|
|
|
Project |
|
Qualified Person |
|
Relationship to Ivanhoe Mines |
Oyu Tolgoi Project
|
|
Stephen Torr, P.Geo, Ivanhoe Mines
|
|
Employee of the Company |
|
|
|
|
|
Ovoot Tolgoi Project
|
|
Stephen Torr, P.Geo, Ivanhoe Mines
|
|
Employee of the Company |
CAUTIONARY STATEMENTS
LANGUAGE REGARDING RESERVES AND RESOURCES
Readers are advised that NI 43-101 Standards of Disclosure for Mineral Projects (NI 43-101) of the
Canadian Securities Administrators requires that each category of mineral reserves and mineral
resources be reported separately. For detailed information related to Company resources and
reserves, readers should refer to the Annual Information Form of the Company for the year ended
December 31, 2009, and other continuous disclosure documents filed by the Company since January 1,
2010, at www.sedar.com.
NOTE TO UNITED STATES INVESTORS CONCERNING ESTIMATES OF MEASURED, INDICATED AND INFERRED RESOURCES
36
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
This document, including the documents incorporated by reference herein, has been prepared in
accordance with the requirements of securities laws in effect in Canada, which differ from the
requirements of United States securities laws. Without limiting the foregoing, this document,
including the documents incorporated by reference herein, uses the terms measured, indicated
and inferred resources. United States investors are advised that, while such terms are recognized
and required by Canadian securities laws, the SEC does not recognize them. Under United States
standards, mineralization may not be classified as a reserve unless the determination has been
made that the mineralization could be economically and legally produced or extracted at the time
the reserve determination is made. United States investors are cautioned not to assume that all or
any part of measured or indicated resources will ever be converted into reserves. Further,
inferred resources have a great amount of uncertainty as to their existence and as to whether
they can be mined legally or economically. It cannot be assumed that all or any part of the
inferred resources will ever be upgraded to a higher category. Therefore, United States investors
are also cautioned not to assume that all or any part of the inferred resources exist, or that they
can be mined legally or economically. Disclosure of contained ounces is a permitted disclosure
under Canadian regulations; however, the SEC only permits issuers to report resources as in place
tonnage and grade without reference to unit measures. Accordingly, information concerning
descriptions of mineralization and resources contained in this document, or in the documents
incorporated by reference, may not be comparable to information made public by United States
companies subject to the reporting and disclosure requirements of the SEC. National Instrument
43-101 Standards of Disclosure for Mineral Projects (NI 43-101) is a rule developed by the Canadian
Securities Administrators that establishes standards for all public disclosure an issuer makes of
scientific and technical information concerning mineral projects. Unless otherwise indicated, all
reserve and resource estimates contained in or incorporated by reference in this document have been
prepared in accordance with NI 43-101. These standards differ significantly from the requirements
of the SEC, and reserve and resource information contained herein and incorporated by reference
herein may not be comparable to similar information disclosed by U.S. companies. NI 43-101 permits
a historical estimate made prior to the adoption of NI 43-101 that does not comply with NI 43-101
to be disclosed using the historical terminology if the disclosure: (a) identifies the source and
date of the historical estimate; (b) comments on the relevance and reliability of the historical
estimate; (c) states whether the historical estimate uses categories other than those prescribed by
NI 43-101; and (d) includes any more recent estimates or data available.
FORWARD-LOOKING STATEMENTS
Certain statements made herein, including statements relating to matters that are not historical
facts and statements of our beliefs, intentions and expectations about developments, results and
events which will or may occur in the future, constitute forward-looking information within the
meaning of applicable Canadian securities legislation and forward-looking statements within the
meaning of the safe harbor provisions of the United States Private Securities Litigation Reform
Act of 1995. Forward-looking information and statements are typically identified by words such as
anticipate, could, should, expect, seek, may, intend, likely, plan, estimate,
will, believe and similar expressions suggesting future outcomes or statements regarding an
outlook. These include, but are not limited to: statements respecting anticipated business
activities; planned expenditures; corporate strategies; proposed acquisitions and dispositions of
assets; discussions with third parties respecting material agreements; the schedule for carrying
out and
37
IVANHOE MINES LTD.
MANAGEMENTS DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS
(Stated in U.S. dollars, except where noted)
completing construction of the Oyu Tolgoi
Project; the estimated commencement of pre-stripping of the Southern Oyu open pit deposits; the
estimated delivery of the first ores from the Southern Oyu open pit to the concentrator; the
estimated schedule to bring the Oyu Tolgoi Project into initial production and commercial
production; statements related to the anticipated capital costs of the Oyu Tolgoi Project; the
expected timing of production from the first lift of the Hugo North block-cave mine; possible
expansion scenarios for the Oyu Tolgoi Project; the commencement of construction of the water
pipeline, paved road and electrical transmission power line to the Oyu Tolgoi Project; completion
of the pouring of concrete for the pebble crushing building and erection of structural steel for
the concentrator building at the Oyu Tolgoi Project; the Oyu Tolgoi Projects anticipated yearly
production of copper and gold; the ability of Ivanhoe Mines to arrange acceptable financing
commitments for the Oyu Tolgoi Project; implementation of the Oyu Tolgoi Projects training and
development strategy; target milling rates, mining plans and production forecasts for the coal mine
at Ovoot Tolgoi, Mongolia; the schedule for carrying out and completing an expansion of the
production capability of the Ovoot Tolgoi Coal Project; anticipated outcomes with respect to the
ongoing marketing of coal products from the Ovoot Tolgoi Coal Project; the anticipated timing of
payback of capital invested in the Ovoot Tolgoi Coal Project; statements with respect to the
expected closing of the Oyu Tolgoi debt-financing package; statements respecting future equity
investments in Ivanhoe Mines by Rio Tinto; the impact of arbitration proceedings with Rio Tinto;
statements with respect to the timing and the expected amount to be raised under the planned rights
offering; the impact of assertions made by Rio Tinto that the rights offering offends its rights
under the Private Placement Agreement and the shareholders agreement between Mr. Friedland and Rio
Tinto; the statement that the integration of the Osborne Complex has the potential to elevate
Ivanhoe Australia to producer status by late 2011; the statement that Altynalmas Golds definitive
feasibility study is expected to be completed in late Q111; the impact of amendments to the laws
of Mongolia and other countries in which Ivanhoe Mines carries on business, particularly with
respect to taxation; and the anticipated timing, cost and outcome of plans to continue the
development of non-core projects, and other statements that are not historical facts.
All such forward-looking information and statements are based on certain assumptions and analyses
made by Ivanhoe Mines management in light of their experience and perception of historical trends,
current conditions and expected future developments, as well as other factors management believes
are appropriate in the circumstances. These statements, however, are subject to a variety of risks
and uncertainties and other factors that could cause actual events or results to differ materially
from those projected in the forward-looking information or statements. Important factors that could
cause actual results to differ from these forward-looking statements include those described under
the heading Risks and Uncertainties elsewhere in the Companys MD&A. The reader is cautioned not
to place undue reliance on forward-looking information or statements.
The MD&A also contains references to estimates of mineral reserves and mineral resources. The
estimation of reserves and resources is inherently uncertain and involves subjective judgments
about many relevant factors. The accuracy of any such estimates is a function of the quantity and
quality of available data, and of the assumptions made and judgments used in engineering and
geological interpretation, which may prove to be unreliable. There can be no assurance that these
estimates will be accurate or that such mineral reserves and mineral resources can be mined or
processed profitably. Mineral resources that are not mineral reserves do not have demonstrated
economic viability. Except as required by law, the Company does not assume the obligation to revise
or update these forward-looking statements after the date of this document or to revise them to
reflect the occurrence of future unanticipated events.
38
Form 52-109F2
Certification of interim filings full certificate
I, Robert Friedland, Chairman and Chief Executive Officer of Ivanhoe Mines Ltd., certify the
following:
|
1. |
|
Review: I have reviewed the interim financial statements and interim MD&A (together, the
interim filings) of Ivanhoe Mines Ltd. (the issuer) for the interim period ended September 30, 2010. |
|
|
2. |
|
No misrepresentations: Based on my knowledge, having exercised reasonable diligence, the interim
filings do not contain any untrue statement of a material fact or omit to state a material fact
required to be stated or that is necessary to make a statement not misleading in light of the circumstances
under which it was made, with respect to the period covered by the interim filings. |
|
|
3. |
|
Fair presentation: Based on my knowledge, having exercised reasonable diligence, the interim
financial statements together with the other financial information included in the interim filings
fairly present in all material respects the financial condition, results of operations and cash flows of
the issuer, as of the date of and for the periods presented in the interim filings. |
|
|
4. |
|
Responsibility: The issuers other certifying officer(s) and I are responsible for establishing
and maintaining disclosure controls and procedures (DC&P) and internal control over financial reporting
(ICFR), as those terms are defined in National Instrument 52-109 Certification of Disclosure in
Issuers Annual and Interim Filings, for the issuer. |
|
|
5. |
|
Design: Subject to the limitations, if any, described in paragraphs 5.2 and 5.3, the issuers
other certifying
officer(s) and I have, as at the end of the period covered by the interim filings |
|
(a) |
|
designed DC&P, or caused it to be designed under our supervision, to provide reasonable assurance that |
|
(i) |
|
material information relating to the issuer is made known to us by others, particularly
during the period in which the interim filings are being prepared; and |
|
|
(ii) |
|
information required to be disclosed by the issuer in its annual filings, interim filings or
other reports filed or submitted by it under securities legislation is recorded,
processed, summarized and reported within the time periods specified in securities
legislation; and |
|
(b) |
|
designed ICFR, or caused it to be designed under our supervision, to provide reasonable
assurance regarding the reliability of financial reporting and the preparation of financial
statements for external purposes in accordance with the issuers GAAP. |
|
5.1 |
|
Control framework: The control framework the issuers other certifying officer(s) and I used to
design the issuers ICFR is the Internal Control Integrated Framework issued by the Committee of
Sponsoring Organizations of the Treadway Commission (COSO). |
|
|
5.2 |
|
ICFR material weakness relating to design: N/A |
|
|
5.3 |
|
Limitation on scope of design: N/A |
|
|
6. |
|
Reporting changes in ICFR: The issuer has disclosed in its interim MD&A any change in the
issuers ICFR that occurred during the period beginning on July 1, 2010 and ended on September 30, 2010
that has materially affected, or is reasonably likely to materially affect, the issuers ICFR. |
Date: November 10, 2010
Robert Friedland
Robert Friedland
Chairman and Chief Executive Officer
Ivanhoe Mines Ltd.
FORM 52-109F2
Certification of interim filings full certificate
I, Tony Giardini, Chief Financial Officer of Ivanhoe Mines Ltd., certify the following:
|
1. |
|
Review: I have reviewed the interim financial statements and interim MD&A (together, the
interim filings) of Ivanhoe Mines Ltd. (the issuer) for the interim period ended September 30, 2010. |
|
|
2. |
|
No misrepresentations: Based on my knowledge, having exercised reasonable diligence, the interim
filings do not contain any untrue statement of a material fact or omit to state a material fact
required to be stated or that is necessary to make a statement not misleading in light of the circumstances
under which it was made, with respect to the period covered by the interim filings. |
|
|
3. |
|
Fair presentation: Based on my knowledge, having exercised reasonable diligence, the interim
financial statements together with the other financial information included in the interim filings
fairly present in all material respects the financial condition, results of operations and cash flows of
the issuer, as of the date of and for the periods presented in the interim filings. |
|
|
4. |
|
Responsibility: The issuers other certifying officer(s) and I are responsible for establishing
and maintaining disclosure controls and procedures (DC&P) and internal control over financial reporting
(ICFR), as those terms are defined in National Instrument 52-109 Certification of Disclosure in
Issuers Annual and Interim Filings, for the issuer. |
|
|
5. |
|
Design: Subject to the limitations, if any, described in paragraphs 5.2 and 5.3, the issuers
other certifying officer(s) and I have, as at the end of the period covered by the interim filings |
|
(a) |
|
designed DC&P, or caused it to be designed under our supervision, to provide reasonable
assurance that |
|
(i) |
|
material information relating to the issuer is made known to us by others, particularly
during the period in which the interim filings are being prepared; and |
|
|
(ii) |
|
information required to be disclosed by the issuer in its annual filings, interim filings or
other reports filed or submitted by it under securities legislation is recorded,
processed, summarized and reported within the time periods specified in securities
legislation; and |
|
(b) |
|
designed ICFR, or caused it to be designed under our supervision, to provide reasonable
assurance regarding the reliability of financial reporting and the preparation of financial
statements for external purposes in accordance with the issuers GAAP. |
|
5.1 |
|
Control framework: The control framework the issuers other certifying officer(s) and I used to
design the issuers ICFR is the Internal Control Integrated Framework issued by the Committee of
Sponsoring Organizations of the Treadway Commission (COSO). |
|
|
5.2 |
|
ICFR material weakness relating to design: N/A |
|
|
5.3 |
|
Limitation on scope of design: N/A |
|
|
6. |
|
Reporting changes in ICFR: The issuer has disclosed in its interim MD&A any change in the
issuers ICFR that occurred during the period beginning on July 1, 2010 and ended on September 30, 2010
that has materially affected, or is reasonably likely to materially affect, the issuers ICFR. |
Date: November 10, 2010
Tony Giardini
Tony Giardini
Chief Financial Officer
Ivanhoe Mines Ltd.